2216 W NORWALK AVE 90041
Certificate Information: 2216 W NORWALK AVE 90041
- Application / Permit
- 20010-10000-03398
- Plan Check / Job No.
- B20LA13712
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 4 STORY SINGLE FAMILY DWELLING. UNIT#5 (lot5) "SMALL LOT SUBDIVISION PURSUANT TO TENTATIVE TRACT MAP NO 82846-SL . A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED"
- Permit Issued
- Issued on 8/21/2024
- Issuing Office
- Metro
- Current Status
- Issued on 8/21/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2020 | MINA HABIB |
| Corrections Issued | 9/28/2020 | MINA HABIB |
| Quality Review Completed | 10/7/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 10/13/2020 | APPLICANT |
| Applicant returned to address corrections | 2/17/2021 | MINA HABIB |
| Applicant returned to address corrections | 5/5/2021 | MINA HABIB |
| Applicant returned to address corrections | 6/14/2021 | MINA HABIB |
| Applicant returned to address corrections | 9/9/2021 | MINA HABIB |
| Applicant returned to address corrections | 9/10/2021 | MINA HABIB |
| Applicant returned to address corrections | 9/30/2021 | MINA HABIB |
| Applicant returned to address corrections | 10/7/2021 | MINA HABIB |
| Applicant returned to address corrections | 10/8/2021 | MINA HABIB |
| Applicant returned to address corrections | 10/25/2021 | MINA HABIB |
| Applicant returned to address corrections | 2/10/2022 | MINA HABIB |
| Applicant returned to address corrections | 3/16/2022 | MINA HABIB |
| Applicant returned to address corrections | 4/14/2022 | MINA HABIB |
| Applicant returned to address corrections | 4/19/2022 | MINA HABIB |
| Applicant returned to address corrections | 4/20/2022 | MINA HABIB |
| Applicant returned to address corrections | 7/27/2022 | MINA HABIB |
| Applicant returned to address corrections | 8/9/2022 | MINA HABIB |
| Applicant returned to address corrections | 9/1/2022 | MINA HABIB |
| Applicant returned to address corrections | 11/3/2022 | MINA HABIB |
| Applicant returned to address corrections | 1/27/2023 | MINA HABIB |
| Applicant returned to address corrections | 2/14/2023 | MINA HABIB |
| Applicant returned to address corrections | 3/16/2023 | MINA HABIB |
| Plan Check Approved | 3/24/2023 | MINA HABIB |
| Issued | 8/21/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2021 | WALLIE JONG |
| Permit | Cleared | 4/13/2021 | WALLIE JONG |
| Trees in Parkway | Cleared | 4/14/2021 | JOHN KIM |
| Address approval | Cleared | 4/23/2021 | CECILIO NAVARRO |
| Miscellaneous | Cleared | 4/27/2021 | ALBERT TAM |
| Sewer availability | Cleared | 4/29/2021 | WALLIE JONG |
| Highway dedication | Cleared | 4/30/2021 | LINDA MARGARET |
| Roof/Waste drainage to street | Cleared | 4/30/2021 | LINDA MARGARET |
| Miscellaneous | Cleared | 5/20/2021 | ANACANY HURTADO |
| Construction near power lines | Cleared | 5/24/2021 | OSCAR CASTRO |
| Construction within easement | Cleared | 5/24/2021 | OSCAR CASTRO |
| Hydrant and Access approval | Cleared | 6/5/2021 | ROBERT DUFF |
| Building over 36-ft | Cleared | 6/14/2021 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 6/14/2021 | MINA HABIB |
| Grading Pre-Inspection | Cleared | 6/14/2021 | MINA HABIB |
| Frnt yard landscape/Water mgmt | Cleared | 7/2/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 7/2/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 7/2/2021 | ANACANY HURTADO |
| Low Impact Development | Cleared | 7/7/2021 | ANDRES COVARRUBIAS |
| Green Code | Cleared | 3/16/2022 | MINA HABIB |
| Work Adjacent to Public Way | Cleared | 3/21/2023 | KHOUNG LE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jones,, Ryan Keith; Lic. No.: GE2852 | 1253 W MASLINE ST COVINA, CA 91722 |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 1/15/2025 | Conditional Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 1/16/2025 | Partial Approval | BRENDAN MORELLI |
| Deputy Reinf. Concrete | 1/27/2025 | Conditional Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 1/30/2025 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 1/30/2025 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 1/30/2025 | Partial Approval | BRENDAN MORELLI |
| Deputy Reinf. Concrete | 2/21/2025 | Conditional Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 2/21/2025 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 3/6/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 4/1/2025 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 4/1/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 5/23/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2025 | Partial Approval | NICHOLAS LOPEZ |
| Drywall Nailing | 6/24/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2025 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 7/31/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Partial Approval | BRENDAN MORELLI |
| Special/Order Compliance | 9/3/2025 | Corrections Issued | BRENDAN MORELLI |
| Deputy Wood Construction | 9/4/2025 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Partial Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 9/23/2025 | Conditional Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 9/26/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 10/6/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2025 | Partial Approval | BRENDAN MORELLI |
| HVAC-Rough | 10/6/2025 | Partial Approval | BRENDAN MORELLI |
| Insulation | 10/6/2025 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 10/14/2025 | No Access for Inspection | BRENDAN MORELLI |
| Deputy Wood Construction | 10/16/2025 | Conditional Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 10/16/2025 | Partial Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 10/27/2025 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2025 | Partial Approval | BRENDAN MORELLI |
| Shower Pan | 11/14/2025 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2025 | Approved | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 12/2/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 12/8/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 12/8/2025 | Approved | NICHOLAS LOPEZ |
| Verify Sprinkler Sign Off | 12/8/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 12/16/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 12/18/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Drywall Nailing | 12/23/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 12/23/2025 | Partial Approval | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 2/11/2026 | Approved | NICHOLAS LOPEZ |
| Pre-Inspection | 2/11/2026 | Partial Inspection | NICHOLAS LOPEZ |
| Underground Mechanical | 4/2/2026 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Final | 4/27/2026 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 4/27/2026 | Partial Inspection | NICHOLAS LOPEZ |
| PLUMBING-Final | 5/1/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Special/Order Compliance | 5/1/2026 | Partial Approval | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 5/12/2026 | Approved | BRENDAN MORELLI |