1408 S GLENAVON AVE 90291

Certificate Information: 1408 S GLENAVON AVE 90291

Application / Permit
20010-10000-03392
Plan Check / Job No.
B20LA17688
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED (N) ADU PER ORDINANCE ( 2-STORY) ***SEE COMMENT SECTION***
Permit Issued
Issued on 10/18/2021
Issuing Office
Current Status
CofO Issued on 9/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 CARLOS MONTES
Corrections Issued 10/27/2020 CARLOS MONTES
Quality Review Completed 11/12/2020 WING SUEN
Applicant returned to address corrections 2/2/2021 CARLOS MONTES
Applicant returned to address corrections 4/7/2021 CARLOS MONTES
Plan Check Approved 9/30/2021 CARLOS MONTES
Issued 10/18/2021 APPLICANT
Building Plans Picked Up 10/27/2021 APPLICANT
CofO in Progress 9/21/2023 HERBERT GIRON
Permit Finaled 9/27/2023 DANIEL ORRANTE
CofO Issued 9/27/2023 DANIEL ORRANTE
Permit Finaled 9/27/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction within easement Cleared 3/29/2021 RIDWAN HARDY
Specific Plan Cleared 5/5/2021 PETE EYRE
Address approval Cleared 5/11/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/12/2021 DINAH GARIN
Sewer availability Cleared 5/12/2021 DINAH GARIN
Grading Pre-Inspection Cleared 5/19/2021 PATRICK MISCHLICH
GPI Written Notices Cleared 6/4/2021 CARLOS MONTES
Low Impact Development Cleared 6/14/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 6/30/2021 RAYMOND MUGAMBWA
Hydrant and Access approval Cleared 7/13/2021 GREGORY HOERNER
Miscellaneous Cleared 9/15/2021 JENSON LEE

Contact Information

Contractor Kreation G1 Construction; Lic. No.: 1042068-B 11330 S GREVILLEA AVE APT 1      INGLEWOOD, CA 90304

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/15/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 12/15/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 12/16/2021 Partial Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 12/21/2021 Approved DAVID FEILER
Footing/Foundation/Slab 12/21/2021 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 1/18/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 3/2/2022 Partial Approval DAVID FEILER
Sewer 3/2/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Partial Approval DAVID FEILER
HVAC-Rough 5/6/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 5/13/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 5/13/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 5/18/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 5/18/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/18/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 6/8/2022 Not Ready for Inspection JESUS RODRIGUEZ
Verify Sprinkler Sign Off 6/8/2022 Not Ready for Inspection JESUS RODRIGUEZ
Shower Pan 8/16/2022 Corrections Issued CLAYTON GRAHAM
Shower Pan 8/30/2022 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 10/6/2022 Approved DAVID FEILER
Green Building Rough 10/6/2022 Approved DAVID FEILER
Interior/Exterior Lathing 10/6/2022 Partial Inspection DAVID FEILER
Insulation 10/13/2022 Approved DAVID FEILER
Interior/Exterior Lathing 10/27/2022 Approved CLAYTON GRAHAM
Drywall Nailing 11/3/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/3/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 12/27/2022 Approved EVAN COOPER
Final 5/19/2023 Corrections Issued EVAN COOPER
HVAC-Final 5/19/2023 Approved EVAN COOPER
PLUMBING-Final 5/19/2023 Approved EVAN COOPER
ELECTRICAL-Final 8/23/2023 Corrections Issued HERBERT GIRON
Final 8/23/2023 Corrections Issued HERBERT GIRON
Green Building Final 8/23/2023 Corrections Issued HERBERT GIRON
Service/Power Release 8/23/2023 Corrections Issued HERBERT GIRON
Final 9/19/2023 Corrections Issued HERBERT GIRON
Green Building Final 9/19/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Approved HERBERT GIRON
Service/Power Release 9/19/2023 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 9/19/2023 Approved HERBERT GIRON
ELECTRICAL-Final 9/21/2023 Approved HERBERT GIRON
Final 9/21/2023 OK to Issue CofO HERBERT GIRON
Service/Power Release 9/21/2023 Approved HERBERT GIRON