312 N WESTMORELAND AVE 90004
Certificate Information: 312 N WESTMORELAND AVE 90004
- Application / Permit
- 20010-10000-03386
- Plan Check / Job No.
- B20LA17646
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Other-See Work Description
- Work Description
- NEW ARTIST STUDIO.
- Permit Issued
- Issued on 12/3/2021
- Issuing Office
- Current Status
- CofO Issued on 8/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | KEVIN MORALES |
| Corrections Issued | 11/18/2020 | KEVIN MORALES |
| Quality Review Completed | 11/23/2020 | EUGENE BARBEAU |
| Disabled Access Plans Picked Up | 12/17/2020 | APPLICANT |
| Green Plans Picked Up | 6/4/2021 | APPLICANT |
| Applicant returned to address corrections | 6/16/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 7/20/2021 | KEVIN MORALES |
| Plan Check Approved | 12/3/2021 | KEVIN MORALES |
| Issued | 12/3/2021 | APPLICANT |
| Building Plans Picked Up | 12/10/2021 | APPLICANT |
| TCO Issued (Expire Date: 12-04-2023) | 6/7/2023 | TED RIES |
| CofO in Progress | 8/4/2023 | TED RIES |
| CofO Issued | 8/4/2023 | TED RIES |
| Permit Finaled | 8/4/2023 | TED RIES |
Permit Application Clearance Information
| Address approval | Cleared | 2/17/2021 | WALLIE JONG |
| Permit | Cleared | 2/17/2021 | WALLIE JONG |
| Green Code | Cleared | 4/5/2021 | KEVIN MORALES |
| Hydrant and Access approval | Cleared | 5/24/2021 | MATTHEW CRAIG |
| Historic Resource Verification | Cleared | 5/25/2021 | MICAELA TORRES-GIL |
| Sewer availability | Cleared | 6/14/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2021 | WALLIE JONG |
| Trees in Parkway | Cleared | 7/1/2021 | JOHN KIM |
| Bicycle Parking | Cleared | 8/13/2021 | JEREMY CHOK |
| Low Impact Development | Cleared | 8/30/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/2/2021 | STEVE MELGAR |
| DAS Clearance | Cleared | 9/23/2021 | KEVIN MORALES |
| GPI Written Notices | Cleared | 10/6/2021 | KEVIN MORALES |
| Grading Pre-Inspection | Cleared | 10/6/2021 | KEVIN MORALES |
| "Q" conditions | Cleared | 10/26/2021 | DANIEL CORONADO |
| Specific Plan | Cleared | 10/26/2021 | DANIEL CORONADO |
| "T" removal | Cleared | 11/10/2021 | DANIEL CORONADO |
| Redevelopment Project Area | Cleared | 11/10/2021 | DAVID URITA |
Contact Information
| Architect | Abramson,, Trevor David; Lic. No.: C17597 | 8924 LINDBLADE STREET CULVER CITY, CA 90232 |
| Contractor | L E Waters Construction Company; Lic. No.: 638709-B | 6767 FOREST LAWN DR STE 300 LOS ANGELES, CA 90068 |
| Engineer | Davis,, Richard Hays; Lic. No.: C48082 | 2015 CANTATA DR LOS ANGELES, CA 90068 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/23/2022 | Partial Approval | DANIEL MC AULIFFE |
| METHANE-Barrier | 2/23/2022 | Partial Inspection | DANIEL MC AULIFFE |
| METHANE-Subgrade | 2/23/2022 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 3/3/2022 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 3/8/2022 | Conditional Approval | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 3/9/2022 | Partial Approval | DANIEL MC AULIFFE |
| METHANE-Barrier | 3/9/2022 | Not Ready for Inspection | DANIEL MC AULIFFE |
| METHANE-Subgrade | 3/9/2022 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 3/18/2022 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Masonry | 4/1/2022 | Conditional Approval | DANIEL MC AULIFFE |
| METHANE-Barrier | 4/6/2022 | Not Ready for Inspection | DANIEL MC AULIFFE |
| METHANE-Subgrade | 4/6/2022 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Masonry Wall/Backfill | 4/6/2022 | Partial Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 4/18/2022 | Approved | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 4/18/2022 | Partial Approval | DANIEL MC AULIFFE |
| METHANE-Barrier | 4/18/2022 | Approved | DANIEL MC AULIFFE |
| METHANE-Subgrade | 4/18/2022 | Partial Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 4/19/2022 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 4/20/2022 | Conditional Approval | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 4/22/2022 | Partial Approval | DANIEL MC AULIFFE |
| METHANE-Subgrade | 4/22/2022 | Approved | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 4/25/2022 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 4/26/2022 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 4/27/2022 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Masonry | 5/2/2022 | Conditional Approval | TED RIES |
| Footing/Foundation/Slab | 5/2/2022 | Partial Approval | TED RIES |
| Deputy Reinf. Masonry | 5/9/2022 | Conditional Approval | TED RIES |
| Reinforced Masonry Frame | 5/9/2022 | Partial Approval | TED RIES |
| Deputy Reinf. Masonry | 5/10/2022 | Approved | TED RIES |
| Footing/Foundation/Slab | 5/16/2022 | Partial Approval | TED RIES |
| Green Building Rough | 6/7/2022 | Not Ready for Inspection | TED RIES |
| METHANE-Rough | 6/7/2022 | Approved | TED RIES |
| Reinforced Concrete Frame | 6/7/2022 | Not Ready for Inspection | TED RIES |
| Verify Sprinkler Sign Off | 6/7/2022 | Not Ready for Inspection | TED RIES |
| Wood Frame | 6/7/2022 | Partial Approval | TED RIES |
| Deputy Steel/Welding | 6/22/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Drilled-In Anchors | 7/12/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Wood Construction | 7/18/2022 | Conditional Approval | WINSTON DUNNING |
| Green Building Rough | 7/19/2022 | Conditional Approval | DARRYL ARNOLD |
| Verify Sprinkler Sign Off | 7/19/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 7/19/2022 | Conditional Approval | DARRYL ARNOLD |
| Green Building Rough | 7/25/2022 | Not Ready for Inspection | TED RIES |
| Verify Sprinkler Sign Off | 7/25/2022 | Not Ready for Inspection | TED RIES |
| Wood Frame | 7/25/2022 | Partial Approval | TED RIES |
| Green Building Rough | 9/8/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Light Gage Steel Frame | 9/8/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 9/8/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Green Building Rough | 9/13/2022 | Approved | JAMES POWERS |
| Light Gage Steel Frame | 9/13/2022 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 9/13/2022 | Not Ready for Inspection | JAMES POWERS |
| Drywall Nailing | 9/26/2022 | Approved | DAVID BURKHEAD |
| Final | 5/9/2023 | Conditional Approval | TED RIES |
| Footing/Foundation/Slab | 5/9/2023 | Approved | TED RIES |
| Green Building Final | 5/9/2023 | Approved | TED RIES |
| Reinforced Masonry Frame | 5/9/2023 | Approved | TED RIES |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV No Gas | TED RIES |
| Smoke Detectors | 5/9/2023 | Approved | TED RIES |
| Structural Steel Frame | 5/9/2023 | Approved | TED RIES |
| Verify Sprinkler Sign Off | 5/9/2023 | Approved | TED RIES |
| Wood Frame | 5/9/2023 | Approved | TED RIES |