8946 S DALTON AVE 90047

Certificate Information: 8946 S DALTON AVE 90047

Application / Permit
20010-10000-03377
Plan Check / Job No.
B20LA17616
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Supplemental to permit 20014-10000-01253 to revise work description to be "New one-story, detached Accessory Dwelling Unit (589.74 SF) per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(g). All work per Engineered Design." 1 of 2
Permit Issued
Issued on 3/5/2021
Issuing Office
Current Status
CofO Issued on 11/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2020 APPLICANT
Assigned to Plan Check Engineer 10/2/2020 SINA KHOSRAVI
Corrections Issued 10/8/2020 SINA KHOSRAVI
Applicant returned to address corrections 11/12/2020 CHRISTOPHER KOMANCHECK
Applicant returned to address corrections 12/14/2020 GEORGE ALVAREZ
Refund in Progress 12/30/2020 TERENCE SHIA
Refund Closed 12/30/2020 TERENCE SHIA
Plan Check Approved 3/4/2021 SAMUEL GONZALEZ
Issued 3/5/2021 APPLICANT
Building Plans Picked Up 3/11/2021 APPLICANT
CofO in Progress 8/27/2021 FREDDIE RIVERA
No Progress 10/25/2021 FREDDIE RIVERA
CofO in Progress 10/29/2021 FREDDIE RIVERA
Permit Finaled 11/19/2021 DEROLD HAUFF
CofO Issued 11/19/2021 DEROLD HAUFF
Permit Finaled 11/19/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/11/2020 ROSA SILVA
Hydrant and Access approval Cleared 12/22/2020 JEREMY CARTER
Low Impact Development Cleared 2/18/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/22/2021 CELINA MORENO

Contact Information

Contractor Ingenious Construction Inc; Lic. No.: 1009311-B 6727 3RD AVENUE      LOS ANGELES, CA 90043
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2021 Corrections Issued FREDDIE RIVERA
Pre-Inspection 4/16/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/1/2021 Partial Inspection EUGENE CASSIDY
ELECTRICAL-Rough 6/1/2021 Approved EUGENE CASSIDY
Green Building Rough 6/1/2021 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 6/1/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 6/1/2021 Corrections Issued EUGENE CASSIDY
Verify Sprinkler Sign Off 6/1/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/4/2021 Not Ready for Inspection SABAS ALONSO
Green Building Rough 6/4/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 6/4/2021 Partial Approval SABAS ALONSO
PLUMBING-Rough 6/4/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 6/10/2021 Approved EUGENE CASSIDY
Insulation 6/10/2021 Approved EUGENE CASSIDY
Drywall Nailing 6/14/2021 Approved FREDDIE RIVERA
HVAC-Rough 6/14/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 6/18/2021 Approved ALFREDO BALANDRA
ELECTRICAL-Final 8/20/2021 Approved FREDDIE RIVERA
Green Building Final 8/20/2021 Approved FREDDIE RIVERA
HVAC-Final 8/20/2021 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 8/20/2021 Approved FREDDIE RIVERA
Final 8/24/2021 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 8/24/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/24/2021 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 8/24/2021 Approved FREDDIE RIVERA
Final 8/26/2021 OK to Issue CofO FREDDIE RIVERA
Service/Power Release 8/26/2021 Approved FREDDIE RIVERA
Special/Order Compliance 9/20/2021 Corrections Issued FREDDIE RIVERA
Special/Order Compliance 10/27/2021 Not Ready for Inspection FREDDIE RIVERA