13159 W PSOMAS WAY 90066
Certificate Information: 13159 W PSOMAS WAY 90066
- Application / Permit
- 20010-10000-03355
- Plan Check / Job No.
- B20LA17525
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY ADU PER CA GOVT. CODE 65852.2(e)(1)(B) AND APPLICABLE PART OF LAMC12.22A.33(c)-(d),(g), Fully Sprinkler, NFPA-13D
- Permit Issued
- Issued on 2/16/2021
- Issuing Office
- Current Status
- CofO Issued on 10/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | SAM CHANG |
| Corrections Issued | 10/20/2020 | SAM CHANG |
| Quality Review Completed | 10/29/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 10/30/2020 | APPLICANT |
| Applicant returned to address corrections | 11/24/2020 | SAM CHANG |
| Applicant returned to address corrections | 1/7/2021 | SAM CHANG |
| Plan Check Approved | 1/12/2021 | SAM CHANG |
| Issued | 2/16/2021 | APPLICANT |
| CofO in Progress | 10/6/2022 | RICHARD STEINBACH |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
| CofO Issued | 10/6/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/24/2020 | RIDWAN HARDY |
| Specific Plan | Cleared | 11/9/2020 | PEDRO AYALA |
| CPC | Cleared | 11/10/2020 | PABLO ESTRADA |
| CPC | Cleared | 11/10/2020 | PABLO ESTRADA |
| Address approval | Cleared | 11/16/2020 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2020 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 11/17/2020 | HISASHI KOBAYAKAWA |
| Trees in Parkway | Cleared | 11/30/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 12/11/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/22/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/22/2020 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 1/12/2021 | SAM CHANG |
| Grading Pre-Inspection | Cleared | 1/12/2021 | SAM CHANG |
Contact Information
| Contractor | Zepeda Juan; Lic. No.: 1028796-B | 9525 HUNT AVE SOUTH GATE, CA 90280 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Rowlands,, James; Lic. No.: GE740 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/22/2021 | Partial Approval | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 5/6/2021 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/6/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/14/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/14/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 3/14/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Insulation | 3/14/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/14/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/14/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 4/1/2022 | Approved | ANDREW NAVE |
| Insulation | 4/1/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 4/1/2022 | Partial Approval | ANDREW NAVE |
| Shower Pan | 4/20/2022 | Approved | PATRICK QUALEY |
| Pre-Inspection | 4/28/2022 | Partial Inspection | PATRICK QUALEY |
| Interior/Exterior Lathing | 5/2/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 6/2/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/2/2022 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 6/2/2022 | Approved | JESUS RODRIGUEZ |
| Gas Test | 6/28/2022 | Approved | PATRICK QUALEY |
| Gas Test | 7/29/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 9/9/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 9/9/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 9/9/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/15/2022 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 9/15/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Final | 9/20/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 9/20/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 9/20/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 9/20/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Smoke Detectors | 9/20/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/23/2022 | Approved | JESUS RODRIGUEZ |
| Final | 10/5/2022 | OK to Issue CofO | JESUS RODRIGUEZ |
| Service/Power Release | 10/5/2022 | Approved | JESUS RODRIGUEZ |