13159 W PSOMAS WAY 90066

Certificate Information: 13159 W PSOMAS WAY 90066

Application / Permit
20010-10000-03355
Plan Check / Job No.
B20LA17525
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY ADU PER CA GOVT. CODE 65852.2(e)(1)(B) AND APPLICABLE PART OF LAMC12.22A.33(c)-(d),(g), Fully Sprinkler, NFPA-13D
Permit Issued
Issued on 2/16/2021
Issuing Office
Current Status
CofO Issued on 10/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 SAM CHANG
Corrections Issued 10/20/2020 SAM CHANG
Quality Review Completed 10/29/2020 TIEN JEN WANG
Building Plans Picked Up 10/30/2020 APPLICANT
Applicant returned to address corrections 11/24/2020 SAM CHANG
Applicant returned to address corrections 1/7/2021 SAM CHANG
Plan Check Approved 1/12/2021 SAM CHANG
Issued 2/16/2021 APPLICANT
CofO in Progress 10/6/2022 RICHARD STEINBACH
Permit Finaled 10/6/2022 DANIEL ORRANTE
CofO Issued 10/6/2022 DANIEL ORRANTE
Permit Finaled 10/6/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 10/24/2020 RIDWAN HARDY
Specific Plan Cleared 11/9/2020 PEDRO AYALA
CPC Cleared 11/10/2020 PABLO ESTRADA
CPC Cleared 11/10/2020 PABLO ESTRADA
Address approval Cleared 11/16/2020 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 11/17/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 11/17/2020 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 11/30/2020 JOHN KIM
Hydrant and Access approval Cleared 12/11/2020 MATTHEW CRAIG
Low Impact Development Cleared 12/22/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/22/2020 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 1/12/2021 SAM CHANG
Grading Pre-Inspection Cleared 1/12/2021 SAM CHANG

Contact Information

Contractor Zepeda Juan; Lic. No.: 1028796-B 9525 HUNT AVE      SOUTH GATE, CA 90280
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Rowlands,, James; Lic. No.: GE740 10954 SANTA MONICA BLVD      LOS ANGELES, CA 90025

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/22/2021 Partial Approval ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 5/6/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 5/6/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/9/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 3/14/2022 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 3/14/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 3/14/2022 Corrections Issued JESUS RODRIGUEZ
Insulation 3/14/2022 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 3/14/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 3/14/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 4/1/2022 Approved ANDREW NAVE
Insulation 4/1/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 4/1/2022 Partial Approval ANDREW NAVE
Shower Pan 4/20/2022 Approved PATRICK QUALEY
Pre-Inspection 4/28/2022 Partial Inspection PATRICK QUALEY
Interior/Exterior Lathing 5/2/2022 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 6/2/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 6/2/2022 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 6/2/2022 Approved JESUS RODRIGUEZ
Gas Test 6/28/2022 Approved PATRICK QUALEY
Gas Test 7/29/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 9/9/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 9/9/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 9/9/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 9/15/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Final 9/15/2022 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Final 9/20/2022 Corrections Issued JESUS RODRIGUEZ
Final 9/20/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 9/20/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/20/2022 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 9/20/2022 Not Ready for Inspection JESUS RODRIGUEZ
Smoke Detectors 9/20/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 9/23/2022 Approved JESUS RODRIGUEZ
Final 10/5/2022 OK to Issue CofO JESUS RODRIGUEZ
Service/Power Release 10/5/2022 Approved JESUS RODRIGUEZ