13161 W PSOMAS WAY 90066

Certificate Information: 13161 W PSOMAS WAY 90066

Application / Permit
20010-10000-03354
Plan Check / Job No.
B20LA17525
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD W/ ATTACHED 3- CAR GARAGE AND ROOF DECK, Fully Sprinkler, NFPA-13D
Permit Issued
Issued on 2/16/2021
Issuing Office
Current Status
CofO Issued on 10/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 SAM CHANG
Corrections Issued 10/20/2020 SAM CHANG
Quality Review Completed 10/29/2020 TIEN JEN WANG
Building Plans Picked Up 10/30/2020 APPLICANT
Applicant returned to address corrections 11/24/2020 SAM CHANG
Applicant returned to address corrections 1/7/2021 SAM CHANG
Plan Check Approved 1/12/2021 SAM CHANG
Issued 2/16/2021 APPLICANT
CofO in Progress 10/6/2022 JESUS RODRIGUEZ
Permit Finaled 10/6/2022 DANIEL ORRANTE
CofO Issued 10/6/2022 DANIEL ORRANTE
Permit Finaled 10/6/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 10/24/2020 RIDWAN HARDY
Specific Plan Cleared 11/9/2020 PEDRO AYALA
CPC Cleared 11/10/2020 PABLO ESTRADA
CPC Cleared 11/10/2020 PABLO ESTRADA
Frnt yard landscape/Water mgmt Cleared 11/10/2020 PABLO ESTRADA
Eng Process Fee Ord 176,300 Cleared 11/17/2020 HISASHI KOBAYAKAWA
Permit Cleared 11/17/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 11/17/2020 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 11/18/2020 JOHN KIM
GPI Written Notices Cleared 11/25/2020 SAM CHANG
Grading Pre-Inspection Cleared 11/25/2020 SAM CHANG
Hydrant and Access approval Cleared 12/11/2020 MATTHEW CRAIG
Low Impact Development Cleared 12/22/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/22/2020 HISASHI KOBAYAKAWA
Green Code Cleared 1/12/2021 SAM CHANG

Contact Information

Contractor Zepeda Juan; Lic. No.: 1028796-B 9525 HUNT AVE      SOUTH GATE, CA 90280
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Rowlands,, James; Lic. No.: GE740 10954 SANTA MONICA BLVD      LOS ANGELES, CA 90025

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/21/2021 Partial Approval ENRIQUE MIRELES
PLUMBING-Rough 4/22/2021 Not Ready for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 5/5/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 5/5/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/9/2021 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/30/2021 Conditional Approval BRENDAN LOONEY
BUILDING-Rough-Frame 10/28/2021 Corrections Issued ENRIQUE MIRELES
Green Building Rough 10/28/2021 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 10/28/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 12/7/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 12/7/2021 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 12/9/2021 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/9/2021 Partial Inspection ENRIQUE MIRELES
Green Building Rough 12/9/2021 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 12/9/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 2/22/2022 Approved ENRIQUE MIRELES
HVAC-Rough 2/22/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 2/22/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/1/2022 Corrections Issued ENRIQUE MIRELES
Insulation 3/7/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 3/21/2022 Approved STEPHANIE SWANSON
Drywall Nailing 3/21/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 3/21/2022 Partial Approval STEPHANIE SWANSON
Verify Sprinkler Sign Off 3/21/2022 Approved STEPHANIE SWANSON
Shower Pan 4/19/2022 Approved PATRICK QUALEY
Interior/Exterior Lathing 5/2/2022 Approved KRISTEN CAUSEY
Gas Test 6/28/2022 Approved PATRICK QUALEY
Special/Order Compliance 7/21/2022 Corrections Issued EVAN COOPER
ELECTRICAL-Final 9/8/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Final 9/8/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 9/9/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 9/15/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Final 9/15/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 9/20/2022 Corrections Issued JESUS RODRIGUEZ
Final 9/20/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 9/20/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/20/2022 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 9/20/2022 Corrections Issued JESUS RODRIGUEZ
Smoke Detectors 9/20/2022 Approved JESUS RODRIGUEZ
Final 10/4/2022 Partial Approval JESUS RODRIGUEZ
Service/Power Release 10/4/2022 Approved JESUS RODRIGUEZ
Final 10/6/2022 Conditional Approval JESUS RODRIGUEZ