4804 S SLAUSON AVE 90230

Certificate Information: 4804 S SLAUSON AVE 90230

Application / Permit
20010-10000-03345
Plan Check / Job No.
B20LA17497
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED 3 STORY DUPLEX WITH ATTACHED 4-CAR GARAGE. SCOPE WILL ALSO INCLDE AN ATTACHED ACESSORY DWELLING UINT PER ORDINANCE.
Permit Issued
Issued on 6/15/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 MICHAEL LOPEZ
Corrections Issued 11/5/2020 MICHAEL LOPEZ
Quality Review Completed 11/25/2020 PRANITA SHAH
Applicant returned to address corrections 6/24/2021 MICHAEL LOPEZ
Applicant returned to address corrections 6/25/2021 MICHAEL LOPEZ
Applicant returned to address corrections 1/4/2022 MICHAEL LOPEZ
Applicant returned to address corrections 5/20/2022 MICHAEL LOPEZ
Plan Check Approved 10/24/2022 NGHI SU
Issued 6/15/2023 APPLICANT
CofO in Progress 7/3/2025 MICHAEL ALLEN
Permit Finaled 7/8/2025 RICHARD STEINBACH
CofO Issued 7/8/2025 RICHARD STEINBACH
Permit Finaled 7/8/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 12/4/2020 CECILIO NAVARRO
Highway dedication Cleared 12/17/2020 RAYMOND MUGAMBWA
Hydrant and Access approval Cleared 1/11/2021 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 3/2/2021 CECILIO NAVARRO
Sewer availability Cleared 3/2/2021 CECILIO NAVARRO
Specific Plan Cleared 4/20/2021 FREDDY GARCIA
Frnt yard landscape/Water mgmt Cleared 4/29/2021 ANACANY HURTADO
Address approval Cleared 7/27/2021 CATHERINE ADROVER
Low Impact Development Cleared 10/16/2021 TA ANH
Roof/Waste drainage to street Cleared 10/19/2021 WALLIE JONG
Hold Cleared 8/7/2023 GRACE PANGILINAN
Hold Cleared 8/7/2023 MARIA V VASQUEZ

Contact Information

Architect Page,, Allison Y O; Lic. No.: C33409 3738 BUCKINGHAM ROAD      LOS ANGELES, CA 90016
Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/28/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 8/28/2023 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/13/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 9/13/2023 Corrections Issued BOBBY KEY
Excavation/Setback/Form/Re-Bar 9/27/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 9/27/2023 Not Ready for Inspection JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/29/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 9/29/2023 Partial Approval JESUS RODRIGUEZ
Sewer 9/29/2023 Partial Approval JESUS RODRIGUEZ
Deputy Reinf. Concrete 10/3/2023 Conditional Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 10/16/2023 Conditional Approval JESUS RODRIGUEZ
Deputy Steel/Welding 10/16/2023 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/24/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 10/24/2023 Approved JESUS RODRIGUEZ
Sewer 10/24/2023 Approved JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/21/2023 Approved JESUS RODRIGUEZ
Deputy Steel/Welding 12/11/2023 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Partial Approval JESUS RODRIGUEZ
Structural Steel Frame 1/23/2024 Conditional Approval JESUS RODRIGUEZ
Deputy Steel/Welding 1/26/2024 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/9/2024 Corrections Issued JESUS RODRIGUEZ
Structural Steel Frame 2/9/2024 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 4/2/2024 Corrections Issued JESUS RODRIGUEZ
Pre-Inspection 4/2/2024 Partial Inspection RICHARD STEINBACH
Special/Order Compliance 4/2/2024 Partial Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Not Ready for Inspection JESUS RODRIGUEZ
Deputy Wood Construction 4/10/2024 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Partial Approval RICHARD STEINBACH
ELECTRICAL-Rough 7/11/2024 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Partial Approval STEPHANIE SWANSON
HVAC-Rough 7/11/2024 Not Ready for Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 7/18/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 7/25/2024 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Corrections Issued JESUS RODRIGUEZ
Shower Pan 8/6/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/13/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 10/1/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 10/1/2024 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 10/4/2024 Approved JESUS PINEDA
PLUMBING-Rough 10/4/2024 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 10/7/2024 Approved JESUS PINEDA
PLUMBING-Rough 10/7/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 10/11/2024 Corrections Issued JESUS PINEDA
Verify Sprinkler Sign Off 10/11/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 10/16/2024 Approved JESUS PINEDA
Green Building Rough 10/16/2024 Approved JESUS PINEDA
MERV13>=Rough 10/16/2024 Approved JESUS PINEDA
Insulation 10/17/2024 Partial Inspection JESUS PINEDA
Drywall Nailing 11/7/2024 Partial Approval JESUS PINEDA
Insulation 11/7/2024 Corrections Issued JESUS PINEDA
Drywall Nailing 11/18/2024 Partial Approval JESUS PINEDA
Insulation 11/18/2024 Approved JESUS PINEDA
Drywall Nailing 11/26/2024 Approved REGINA MENDEZ
Special/Order Compliance 3/13/2025 Corrections Issued JESUS PINEDA
Underground Mechanical 4/3/2025 Partial Inspection MICHAEL ALLEN
Underground Mechanical 4/11/2025 Approved MICHAEL ALLEN
Grounding or Bonding 4/14/2025 Not Ready for Inspection MICHAEL ALLEN
Underground Mechanical 4/14/2025 Approved MICHAEL ALLEN
Gas Test 4/17/2025 Corrections Issued MICHAEL ALLEN
Underground Mechanical 4/17/2025 Conditional Approval MICHAEL ALLEN
Gas Test 4/18/2025 Approved MICHAEL ALLEN
Underground Mechanical 4/18/2025 Approved MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 5/1/2025 Partial Inspection MICHAEL ALLEN
ELECTRICAL-Final 5/6/2025 Corrections Issued MICHAEL ALLEN
Service/Power Release 5/6/2025 Not Ready for Inspection MICHAEL ALLEN
ELECTRICAL-Final 5/13/2025 Partial Approval MICHAEL ALLEN
Grounding or Bonding 5/13/2025 Not Ready for Inspection MICHAEL ALLEN
Service/Power Release 5/13/2025 Not Ready for Inspection MICHAEL ALLEN
ELECTRICAL-Final 5/16/2025 Approved MICHAEL ALLEN
Service/Power Release 5/16/2025 Approved MICHAEL ALLEN
HVAC-Final 5/20/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Final 6/4/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Approved JESUS PINEDA
Final 6/20/2025 Partial Approval MICHAEL ALLEN
Green Building Final 6/20/2025 Approved MICHAEL ALLEN
HVAC-Final 6/20/2025 Approved MICHAEL ALLEN
MERV13>=Final 6/20/2025 Approved MICHAEL ALLEN
Smoke Detectors 6/20/2025 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 6/20/2025 Approved MICHAEL ALLEN
Final 6/25/2025 Corrections Issued MICHAEL ALLEN
HVAC-Final 6/25/2025 Approved MICHAEL ALLEN
Final 6/27/2025 Partial Approval MICHAEL ALLEN
Final 7/2/2025 OK to Issue CofO MICHAEL ALLEN