230 S AVONDALE AVE 90049

Certificate Information: 230 S AVONDALE AVE 90049

Application / Permit
20010-10000-03339
Plan Check / Job No.
B20LA17482
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY ACCESSORY STRUCTURE W/ADU ON 2ND FLOOR
Permit Issued
Issued on 2/18/2021
Issuing Office
Current Status
CofO Issued on 2/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 MAHNAZ NOURHASHEMI
Corrections Issued 10/9/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 10/21/2020 TIEN JEN WANG
Building Plans Picked Up 10/22/2020 APPLICANT
Applicant returned to address corrections 1/13/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 2/18/2021 MAHNAZ NOURHASHEMI
Issued 2/18/2021 APPLICANT
CofO in Progress 1/27/2023 JESUS RODRIGUEZ
Permit Finaled 2/6/2023 DANIEL ORRANTE
CofO Issued 2/6/2023 DANIEL ORRANTE
Permit Finaled 2/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/24/2020 BARTON HOLMES
Specific Plan Cleared 12/1/2020 VALERIA CEJA
Hydrant and Access approval Cleared 12/18/2020 MATTHEW CRAIG
Address approval Cleared 2/8/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/8/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 2/8/2021 DINAH GARIN
Sewer availability Cleared 2/8/2021 DINAH GARIN

Contact Information

Contractor Valle/Reinis Builders Inc; Lic. No.: 839178-B 11661 SAN VICENTE BLVD STE 302      LOS ANGELES, CA 90049
Engineer Shah,, Kamal Rajendra; Lic. No.: C46200 28611 HASKELL CANYON RD      SANTA CLARITA, CA 91390

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/20/2021 Partial Approval JOHN KIDWELL
Underground Mechanical 5/20/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/25/2021 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/15/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 8/4/2021 No Access for Inspection JOHN KIDWELL
HVAC-Rough 8/4/2021 No Access for Inspection JOHN KIDWELL
PLUMBING-Rough 8/4/2021 No Access for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 8/5/2021 Approved JOHN KIDWELL
ELECTRICAL-Rough 8/5/2021 Approved JOHN KIDWELL
Green Building Rough 8/5/2021 Approved JOHN KIDWELL
HVAC-Rough 8/5/2021 Approved JOHN KIDWELL
PLUMBING-Rough 8/5/2021 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 8/5/2021 Approved JOHN KIDWELL
Drywall Nailing 1/24/2022 Approved EVAN COOPER
Insulation 1/24/2022 Approved EVAN COOPER
Shower Pan 2/10/2022 Approved JUAN VALENZUELA
Gas Test 3/31/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 3/31/2022 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 7/1/2022 SGSOV Not Ready JUAN VALENZUELA
Sewer 7/1/2022 Approved JUAN VALENZUELA
Underground Mechanical 7/1/2022 Partial Approval JUAN VALENZUELA
Final 11/23/2022 Partial Inspection JUAN VALENZUELA
Gas Test 11/23/2022 Approved JUAN VALENZUELA
Green Building Final 11/23/2022 Partial Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Approved JUAN VALENZUELA
Service/Power Release 11/23/2022 Partial Inspection JUAN VALENZUELA
Smoke Detectors 11/23/2022 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Final 12/7/2022 Corrections Issued KEVIN SARGSYAN
Green Building Final 12/7/2022 Corrections Issued KEVIN SARGSYAN
Smoke Detectors 12/7/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 12/10/2022 Approved CHRISTOPHER WILSON
Service/Power Release 12/10/2022 Approved CHRISTOPHER WILSON
Service/Power Release 12/10/2022 Off-Hour Fees Due
Final 1/27/2023 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 1/27/2023 Approved JESUS RODRIGUEZ
HVAC-Final 1/27/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 1/27/2023 Approved JESUS RODRIGUEZ
Smoke Detectors 1/27/2023 Approved JESUS RODRIGUEZ