230 S AVONDALE AVE 90049
Certificate Information: 230 S AVONDALE AVE 90049
- Application / Permit
- 20010-10000-03339
- Plan Check / Job No.
- B20LA17482
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ACCESSORY STRUCTURE W/ADU ON 2ND FLOOR
- Permit Issued
- Issued on 2/18/2021
- Issuing Office
- Current Status
- CofO Issued on 2/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/9/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/21/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 10/22/2020 | APPLICANT |
| Applicant returned to address corrections | 1/13/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 2/18/2021 | MAHNAZ NOURHASHEMI |
| Issued | 2/18/2021 | APPLICANT |
| CofO in Progress | 1/27/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 2/6/2023 | DANIEL ORRANTE |
| CofO Issued | 2/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/24/2020 | BARTON HOLMES |
| Specific Plan | Cleared | 12/1/2020 | VALERIA CEJA |
| Hydrant and Access approval | Cleared | 12/18/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 2/8/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 2/8/2021 | DINAH GARIN |
| Sewer availability | Cleared | 2/8/2021 | DINAH GARIN |
Contact Information
| Contractor | Valle/Reinis Builders Inc; Lic. No.: 839178-B | 11661 SAN VICENTE BLVD STE 302 LOS ANGELES, CA 90049 |
| Engineer | Shah,, Kamal Rajendra; Lic. No.: C46200 | 28611 HASKELL CANYON RD SANTA CLARITA, CA 91390 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/20/2021 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 5/20/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/25/2021 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2021 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 8/4/2021 | No Access for Inspection | JOHN KIDWELL |
| HVAC-Rough | 8/4/2021 | No Access for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 8/4/2021 | No Access for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 8/5/2021 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 8/5/2021 | Approved | JOHN KIDWELL |
| Green Building Rough | 8/5/2021 | Approved | JOHN KIDWELL |
| HVAC-Rough | 8/5/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 8/5/2021 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 8/5/2021 | Approved | JOHN KIDWELL |
| Drywall Nailing | 1/24/2022 | Approved | EVAN COOPER |
| Insulation | 1/24/2022 | Approved | EVAN COOPER |
| Shower Pan | 2/10/2022 | Approved | JUAN VALENZUELA |
| Gas Test | 3/31/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 3/31/2022 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Not Ready | JUAN VALENZUELA |
| Sewer | 7/1/2022 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 7/1/2022 | Partial Approval | JUAN VALENZUELA |
| Final | 11/23/2022 | Partial Inspection | JUAN VALENZUELA |
| Gas Test | 11/23/2022 | Approved | JUAN VALENZUELA |
| Green Building Final | 11/23/2022 | Partial Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 11/23/2022 | Partial Inspection | JUAN VALENZUELA |
| Smoke Detectors | 11/23/2022 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/7/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 12/7/2022 | Corrections Issued | KEVIN SARGSYAN |
| Smoke Detectors | 12/7/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 12/10/2022 | Approved | CHRISTOPHER WILSON |
| Service/Power Release | 12/10/2022 | Approved | CHRISTOPHER WILSON |
| Service/Power Release | 12/10/2022 | Off-Hour Fees Due | |
| Final | 1/27/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 1/27/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 1/27/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 1/27/2023 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 1/27/2023 | Approved | JESUS RODRIGUEZ |