1621 W 208TH ST 90501
Certificate Information: 1621 W 208TH ST 90501
- Application / Permit
- 20010-10000-03335
- Plan Check / Job No.
- B20LA17466
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SINGLE FAMILY DWELLING AT MIDDLE OF LOT WITH 1-CAR ATTACHED GARAGE & 1 UNCOVERED PARKING STALL
- Permit Issued
- Issued on 8/25/2021
- Issuing Office
- Current Status
- CofO Issued on 7/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | PRANITA SHAH |
| Corrections Issued | 12/8/2020 | PRANITA SHAH |
| Quality Review Completed | 12/24/2020 | MINYE PAK |
| Building Plans Picked Up | 12/29/2020 | APPLICANT |
| Applicant returned to address corrections | 7/23/2021 | PRANITA SHAH |
| Plan Check Approved | 8/25/2021 | PRANITA SHAH |
| Issued | 8/25/2021 | APPLICANT |
| CofO in Progress | 7/7/2022 | EUGENE CASSIDY |
| Permit Finaled | 7/14/2022 | DEROLD HAUFF |
| CofO Issued | 7/14/2022 | DEROLD HAUFF |
| Permit Finaled | 7/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2021 | ERIK BEASLEY |
| Highway dedication | Cleared | 1/29/2021 | ERIK BEASLEY |
| Permit | Cleared | 1/29/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/10/2021 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 5/13/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 5/16/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/17/2021 | JEANIE LAM |
| Frnt yard landscape/Water mgmt | Cleared | 5/20/2021 | RUBEN VASQUEZ |
| Trees in Parkway | Cleared | 6/2/2021 | JOHN KIM |
Contact Information
| Contractor | California Realty & Investment Group Inc; Lic. No.: 929543-B | PO BOX 40322 DOWNEY, CA 90239 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/30/2021 | Partial Approval | JOHN KLARIN |
| Deputy Steel/Welding | 9/9/2021 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 9/13/2021 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 10/4/2021 | Partial Approval | JOHN KLARIN |
| Deputy Steel/Welding | 10/28/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2021 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 11/3/2021 | Not Ready for Inspection | JOHN KLARIN |
| Verify Sprinkler Sign Off | 11/3/2021 | Not Ready for Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2021 | Partial Approval | JOHN KLARIN |
| Deputy Wood Construction | 1/28/2022 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/1/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 2/1/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 2/1/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 2/1/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 2/1/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 2/1/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 2/4/2022 | Conditional Approval | EUGENE CASSIDY |
| HVAC-Rough | 2/4/2022 | Conditional Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 2/4/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/9/2022 | Approved | EUGENE CASSIDY |
| Green Building Rough | 2/9/2022 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 2/9/2022 | Approved | EUGENE CASSIDY |
| Insulation | 2/22/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/22/2022 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 2/28/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/6/2022 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 6/6/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 6/6/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 6/10/2022 | Approved | EUGENE CASSIDY |
| Final | 6/10/2022 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/10/2022 | Approved | EUGENE CASSIDY |
| Green Building Final | 6/10/2022 | Approved | EUGENE CASSIDY |
| HVAC-Final | 6/10/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 6/10/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 6/10/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/28/2022 | Approved | EUGENE CASSIDY |
| Final | 6/28/2022 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 6/28/2022 | Approved | EUGENE CASSIDY |