1621 W 208TH ST 90501

Certificate Information: 1621 W 208TH ST 90501

Application / Permit
20010-10000-03335
Plan Check / Job No.
B20LA17466
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY DWELLING AT MIDDLE OF LOT WITH 1-CAR ATTACHED GARAGE & 1 UNCOVERED PARKING STALL
Permit Issued
Issued on 8/25/2021
Issuing Office
Current Status
CofO Issued on 7/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 PRANITA SHAH
Corrections Issued 12/8/2020 PRANITA SHAH
Quality Review Completed 12/24/2020 MINYE PAK
Building Plans Picked Up 12/29/2020 APPLICANT
Applicant returned to address corrections 7/23/2021 PRANITA SHAH
Plan Check Approved 8/25/2021 PRANITA SHAH
Issued 8/25/2021 APPLICANT
CofO in Progress 7/7/2022 EUGENE CASSIDY
Permit Finaled 7/14/2022 DEROLD HAUFF
CofO Issued 7/14/2022 DEROLD HAUFF
Permit Finaled 7/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/29/2021 ERIK BEASLEY
Highway dedication Cleared 1/29/2021 ERIK BEASLEY
Permit Cleared 1/29/2021 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 3/10/2021 ERIK BEASLEY
Sewer availability Cleared 3/10/2021 ERIK BEASLEY
Hydrant and Access approval Cleared 5/13/2021 KURT CORRAL
Low Impact Development Cleared 5/16/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/17/2021 JEANIE LAM
Frnt yard landscape/Water mgmt Cleared 5/20/2021 RUBEN VASQUEZ
Trees in Parkway Cleared 6/2/2021 JOHN KIM

Contact Information

Contractor California Realty & Investment Group Inc; Lic. No.: 929543-B PO BOX 40322      DOWNEY, CA 90239
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/30/2021 Partial Approval JOHN KLARIN
Deputy Steel/Welding 9/9/2021 Approved JOHN KLARIN
Footing/Foundation/Slab 9/13/2021 Corrections Issued ANSON MAGLASANG
Footing/Foundation/Slab 10/4/2021 Partial Approval JOHN KLARIN
Deputy Steel/Welding 10/28/2021 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 11/3/2021 Partial Approval JOHN KLARIN
Green Building Rough 11/3/2021 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 11/3/2021 Not Ready for Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 11/18/2021 Partial Approval JOHN KLARIN
Deputy Wood Construction 1/28/2022 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 2/1/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 2/1/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 2/1/2022 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 2/1/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 2/1/2022 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 2/1/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 2/4/2022 Conditional Approval EUGENE CASSIDY
HVAC-Rough 2/4/2022 Conditional Approval EUGENE CASSIDY
PLUMBING-Rough 2/4/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 2/9/2022 Approved EUGENE CASSIDY
Green Building Rough 2/9/2022 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 2/9/2022 Approved EUGENE CASSIDY
Insulation 2/22/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 2/22/2022 Partial Approval EUGENE CASSIDY
Drywall Nailing 2/28/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 6/6/2022 Corrections Issued EUGENE CASSIDY
HVAC-Final 6/6/2022 Approved EUGENE CASSIDY
PLUMBING-Final 6/6/2022 Approved EUGENE CASSIDY
Drywall Nailing 6/10/2022 Approved EUGENE CASSIDY
Final 6/10/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 6/10/2022 Approved EUGENE CASSIDY
Green Building Final 6/10/2022 Approved EUGENE CASSIDY
HVAC-Final 6/10/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/10/2022 SGSOV Approved EUGENE CASSIDY
Service/Power Release 6/10/2022 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 6/10/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 6/28/2022 Approved EUGENE CASSIDY
Final 6/28/2022 OK to Issue CofO EUGENE CASSIDY
Service/Power Release 6/28/2022 Approved EUGENE CASSIDY