6125 W FOUNTAIN AVE 90028
Certificate Information: 6125 W FOUNTAIN AVE 90028
- Application / Permit
- 20010-10000-03329
- Plan Check / Job No.
- B20LA17399
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 2-story accessory dwelling unit with parking below. LID PLANS REQUIRED PRIOR TO C OF O.
- Permit Issued
- Issued on 7/5/2022
- Issuing Office
- Current Status
- Issued on 7/5/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | JOE VO |
| Corrections Issued | 10/28/2020 | JOE VO |
| Quality Review Completed | 12/1/2020 | MINYE PAK |
| Applicant returned to address corrections | 1/20/2022 | JOE VO |
| Plan Check Approved | 3/21/2022 | JOE VO |
| No Progress | 3/21/2022 | JOE VO |
| Plan Check Approved | 5/9/2022 | JOE VO |
| Issued | 7/5/2022 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/2/2021 | MATTHEW CRAIG |
| Redevelopment Project Area | Cleared | 4/15/2021 | DAVID URITA |
| Address approval | Cleared | 5/12/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2021 | CELINA MORENO |
| Sewer availability | Cleared | 5/13/2021 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 2/22/2022 | CELINA MORENO |
| Highway dedication | Cleared | 6/9/2022 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/28/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/6/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Pre-Inspection | 12/6/2022 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 12/6/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/28/2022 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 12/28/2022 | Partial Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 8/1/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 9/13/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/27/2023 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 12/27/2023 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 12/27/2023 | Partial Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 12/27/2023 | Approved | STUART CHAPMAN |
| Wood Frame | 12/27/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 1/2/2024 | Partial Approval | ROY SPAULDING |
| Green Building Rough | 1/2/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 3/19/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 3/19/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 3/19/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 3/20/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 3/20/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 4/26/2024 | Approved | ROY SPAULDING |
| Insulation | 11/5/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 4/7/2025 | Approved | CRAIG VAUGHAN |
| Sewer | 4/7/2025 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 4/14/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/21/2025 | Approved | BRIAN SULLIVAN |