3013 N WARWICK AVE 90032
Certificate Information: 3013 N WARWICK AVE 90032
- Application / Permit
- 20010-10000-03324
- Plan Check / Job No.
- B20LA17396
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c) - (d)
- Permit Issued
- Issued on 7/3/2021
- Issuing Office
- Current Status
- CofO Issued on 11/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | LAMAR DAVIS |
| Corrections Issued | 10/27/2020 | LAMAR DAVIS |
| Quality Review Completed | 11/5/2020 | TU HUA |
| Applicant returned to address corrections | 3/3/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 4/14/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 5/3/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 6/9/2021 | LAMAR DAVIS |
| Plan Check Approved | 6/18/2021 | LAMAR DAVIS |
| Issued | 7/3/2021 | APPLICANT |
| CofO in Progress | 10/19/2022 | AMY COLIN |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
| CofO Issued | 11/5/2022 | DEROLD HAUFF |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 11/20/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 5/20/2021 | SUNG JOON WON |
| Hydrant and Access approval | Cleared | 6/1/2021 | KURT CORRAL |
| GPI Written Notices | Cleared | 6/9/2021 | ROBERT HUGHES |
| Grading Pre-Inspection | Cleared | 6/9/2021 | ROBERT HUGHES |
| Roof/Waste drainage to street | Cleared | 6/16/2021 | RENZ SORIANO |
| Miscellaneous | Cleared | 6/17/2021 | LAMAR DAVIS |
| Hold | Cleared | 8/6/2021 | JASON SHEETS |
Contact Information
| Architect | Gonzalez,, Javier; Lic. No.: C25477 | 1090 W 11TH STREET APT 3 SAN PEDRO, CA 90731 |
| Contractor | Owner-Builder | , |
| Engineer | Cosentino,, Joseph; Lic. No.: C53176 | 820 ISABELLA MONTEREY PARK, CA 91754 |
| Engineer | Smith,, Randall James; Lic. No.: L5189 | 2935 HENRIETTA AVE LA CRESCENTA, CA 91214 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/22/2021 | Not Ready for Inspection | COREY HUPP |
| Underground Mechanical | 9/22/2021 | Partial Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 9/30/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 12/6/2021 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 12/6/2021 | No Access for Inspection | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 12/6/2021 | Approved | COREY HUPP |
| Underground Mechanical | 12/6/2021 | Approved | COREY HUPP |
| Verify Sprinkler Sign Off | 12/6/2021 | Not Ready for Inspection | COREY HUPP |
| Deputy Wood Construction | 1/20/2022 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/27/2022 | Approved | RUBEN SALAS |
| Green Building Rough | 1/27/2022 | Approved | RUBEN SALAS |
| Verify Sprinkler Sign Off | 1/27/2022 | Approved | RUBEN SALAS |
| Wood Frame | 1/27/2022 | Approved | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 2/16/2022 | Partial Approval | RUBEN SALAS |
| Drywall Nailing | 3/3/2022 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 3/8/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/20/2022 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 4/20/2022 | Approved | AMY COLIN |
| Green Building Final | 4/20/2022 | Corrections Issued | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 4/20/2022 | SGSOV Approved | AMY COLIN |
| Service/Power Release | 4/20/2022 | Not Ready for Inspection | AMY COLIN |
| Smoke Detectors | 4/20/2022 | Approved | AMY COLIN |
| Final | 5/5/2022 | Corrections Issued | RUBEN SALAS |
| Green Building Final | 5/5/2022 | Approved | RUBEN SALAS |
| Service/Power Release | 5/5/2022 | Not Ready for Inspection | RUBEN SALAS |
| Service/Power Release | 5/16/2022 | Approved | RUBEN SALAS |
| Final | 10/11/2022 | Partial Inspection | AMY COLIN |
| Final | 10/19/2022 | OK to Issue CofO | AMY COLIN |