907-907 1/2 E VERNON AVE 90011

Certificate Information: 907-907 1/2 E VERNON AVE 90011

Application / Permit
20010-10000-03323
Plan Check / Job No.
B20LA17382
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 2-STORY (16' MAX HEIGHT) DUPLEX (TWO ADU'S) PER STATE LAW GCS 65852.2(e)(1)(D).
Permit Issued
Issued on 6/23/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 MICHAEL LOPEZ
Corrections Issued 11/12/2020 MICHAEL LOPEZ
Quality Review Completed 11/26/2020 PRANITA SHAH
Applicant returned to address corrections 10/15/2021 MICHAEL LOPEZ
Building Plans Picked Up 11/5/2021 APPLICANT
Applicant returned to address corrections 11/30/2021 MICHAEL LOPEZ
Plan Check Approved 6/17/2022 MICHAEL LOPEZ
Issued 6/23/2022 APPLICANT
CofO in Progress 9/16/2023 ALEJANDRO DE ARTOLA
Permit Finaled 10/4/2023 DEROLD HAUFF
CofO Issued 10/4/2023 DEROLD HAUFF
Permit Finaled 10/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/22/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 1/7/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 1/7/2021 MATTHEW CRAIG
Sewer availability Cleared 1/8/2021 CECILIO NAVARRO
Community Plan Implem. Overlay Cleared 2/10/2021 JOHN KIM
Frnt yard landscape/Water mgmt Cleared 3/9/2021 ANACANY HURTADO
Miscellaneous Cleared 3/9/2021 ANACANY HURTADO
Low Impact Development Cleared 8/5/2021 SARAH YOUSSEF
"D" conditions Cleared 8/24/2021 HELEN JADALI
Community Plan Implem. Overlay Cleared 8/24/2021 HELEN JADALI
Community Plan Implem. Overlay Cleared 12/7/2021 CINDY QI
Redevelopment Project Area Cleared 12/13/2021 GRACIELA ACOSTA
Roof/Waste drainage to street Cleared 12/15/2021 CINDY QI
Highway dedication Cleared 1/4/2022 CINDY QI
Community Plan Implem. Overlay Cleared 6/8/2022 WALTER RAMIREZ

Contact Information

Contractor J C Construction; Lic. No.: 756599-B 13721 DE ALCALA DR      LA MIRADA, CA 90638
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/15/2022 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 7/27/2022 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 8/1/2022 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 8/3/2022 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Partial Approval RYAN SALAZAR
Green Building Rough 8/29/2022 Not Ready for Inspection RYAN SALAZAR
Verify Sprinkler Sign Off 8/29/2022 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/14/2022 Corrections Issued SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Corrections Issued SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Partial Approval SHAVONNE ESPINOZA
BUILDING-Rough-Frame 10/19/2022 Corrections Issued SHAVONNE ESPINOZA
Green Building Rough 10/19/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Verify Sprinkler Sign Off 10/19/2022 Approved SHAVONNE ESPINOZA
Underground Mechanical 10/24/2022 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 11/8/2022 Conditional Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Partial Approval RYAN SALAZAR
Green Building Rough 11/8/2022 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 11/8/2022 Corrections Issued RYAN SALAZAR
BUILDING-Rough-Frame 11/15/2022 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 11/15/2022 Conditional Approval RYAN SALAZAR
Interior/Exterior Lathing 11/15/2022 Partial Approval RYAN SALAZAR
PLUMBING-Rough 11/15/2022 Approved RYAN SALAZAR
Insulation 12/2/2022 Not Ready for Inspection JULIAN AMAYA
Service/Power Release 12/2/2022 Not Ready for Inspection JULIAN AMAYA
Wood Frame 12/2/2022 Not Ready for Inspection JULIAN AMAYA
Footing/Foundation/Slab 12/20/2022 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 12/30/2022 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 1/3/2023 Not Ready for Inspection MICHAEL LEWIS
Footing/Foundation/Slab 1/3/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 5/2/2023 Approved BRENDAN MORELLI
Underground Mechanical 5/2/2023 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 5/9/2023 Corrections Issued BRENDAN MORELLI
Green Building Rough 5/9/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 5/15/2023 Approved STUART CHAPMAN
HVAC-Rough 5/15/2023 Approved STUART CHAPMAN
Insulation 5/15/2023 Approved STUART CHAPMAN
Drywall Nailing 5/23/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 6/6/2023 Approved BRENDAN MORELLI
PLUMBING-Final 6/28/2023 Corrections Issued BRENDAN MORELLI
Gas Test 7/5/2023 Partial Approval BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Approved BRENDAN MORELLI
Gas Test 7/10/2023 Approved BRENDAN MORELLI
PLUMBING-Final 7/10/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 7/21/2023 Corrections Issued BRENDAN MORELLI
Final 7/21/2023 Corrections Issued BRENDAN MORELLI
Green Building Final 7/21/2023 Approved BRENDAN MORELLI
HVAC-Final 7/21/2023 Approved BRENDAN MORELLI
Service/Power Release 7/21/2023 Approved BRENDAN MORELLI
Smoke Detectors 7/21/2023 Approved BRENDAN MORELLI
Final 7/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/8/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/13/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/15/2023 Approved ALEJANDRO DE ARTOLA
Final 9/15/2023 OK to Issue CofO ALEJANDRO DE ARTOLA