5561 W CARLIN ST 90016
Certificate Information: 5561 W CARLIN ST 90016
- Application / Permit
- 20010-10000-03321
- Plan Check / Job No.
- B20LA17378
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3-story SFD in the front lot. Garage and recreation room are located in the first floor. Fire sprinkler is provided.
- Permit Issued
- Issued on 8/6/2021
- Issuing Office
- Current Status
- CofO Issued on 11/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | HELEN NGUYEN |
| Corrections Issued | 11/2/2020 | HELEN NGUYEN |
| Quality Review Completed | 11/16/2020 | WING SUEN |
| Applicant returned to address corrections | 3/13/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 6/7/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 6/28/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/14/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/15/2021 | HELEN NGUYEN |
| Building Plans Picked Up | 7/16/2021 | APPLICANT |
| Applicant returned to address corrections | 7/29/2021 | HELEN NGUYEN |
| Plan Check Approved | 8/5/2021 | HELEN NGUYEN |
| Issued | 8/6/2021 | APPLICANT |
| CofO in Progress | 7/7/2022 | JOSE AVILA |
| No Progress | 7/27/2022 | JOSE AVILA |
| CofO in Progress | 10/24/2022 | DONALD CRICHLOW |
| CofO in Progress | 11/4/2022 | JOSE AVILA |
| Permit Finaled | 11/8/2022 | DEROLD HAUFF |
| CofO Issued | 11/8/2022 | DEROLD HAUFF |
| Permit Finaled | 11/8/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 2/22/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 3/8/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/26/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/30/2021 | CELINA MORENO |
| Frnt yard landscape/Water mgmt | Cleared | 5/19/2021 | LOUIS ORTEGA |
Contact Information
| Architect | Obnial,, Cezar V; Lic. No.: C12189 | 39998 QUIGLEY ROAD MURRIETA, CA 92562 |
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | P O BOX 96 SAN GABRIEL, CA 91778 |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 8/13/2021 | Conditional Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 8/13/2021 | Conditional Approval | RUBEN SALAS |
| Pre-Inspection | 8/13/2021 | Not Ready for Inspection | RUBEN SALAS |
| Underground Mechanical | 8/13/2021 | Not Ready for Inspection | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 8/18/2021 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/18/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 8/18/2021 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/23/2021 | Approved | STUART CHAPMAN |
| Underground Mechanical | 9/3/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2021 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 9/30/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Partial Approval | STUART CHAPMAN |
| Deputy Wood Construction | 10/21/2021 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 11/16/2021 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 11/16/2021 | Approved | JOSE AVILA |
| Gas Test | 11/16/2021 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 11/16/2021 | Approved | JOSE AVILA |
| HVAC-Rough | 11/16/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 11/16/2021 | Not Ready for Inspection | JOSE AVILA |
| MERV13>=Rough | 11/16/2021 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 11/16/2021 | Approved | JOSE AVILA |
| Verify Rec and Parks Fee Memo | 11/16/2021 | Corrections Issued | JOSE AVILA |
| Verify Sprinkler Sign Off | 11/16/2021 | Approved | JOSE AVILA |
| Insulation | 11/22/2021 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 11/22/2021 | Approved | JOSE AVILA |
| Insulation | 11/30/2021 | Approved | JOSE AVILA |
| Drywall Nailing | 12/6/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/6/2021 | Approved | JOSE AVILA |
| Shower Pan | 12/6/2021 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/1/2022 | Approved | JOSE AVILA |
| Final | 6/1/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 6/1/2022 | Corrections Issued | JOSE AVILA |
| MERV13>=Final | 6/1/2022 | Corrections Issued | JOSE AVILA |
| MERV13>=Rough | 6/1/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/1/2022 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 6/1/2022 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 6/1/2022 | Approved | JOSE AVILA |
| Structural Steel Frame | 6/1/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 6/10/2022 | Approved | JOSE AVILA |
| HVAC-Final | 6/10/2022 | Approved | JOSE AVILA |
| Service/Power Release | 6/10/2022 | Approved | JOSE AVILA |
| Green Building Final | 6/27/2022 | Approved | JOSE AVILA |
| MERV13>=Final | 6/27/2022 | Approved | JOSE AVILA |
| Final | 7/7/2022 | Partial Approval | JOSE AVILA |