3659 S SOMERSET DR 90016

Certificate Information: 3659 S SOMERSET DR 90016

Application / Permit
20010-10000-03320
Plan Check / Job No.
B20LA17372
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2 Story Detached Accessory Dwelling Unit with attached 2 car garage per Ordinance LAMC12.22 A.33 (c)&(d). All work per Engineer Design.
Permit Issued
Issued on 11/8/2021
Issuing Office
Current Status
CofO Issued on 11/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2020 APPLICANT
Assigned to Plan Check Engineer 1/13/2021 ZAW HAN
Corrections Issued 1/21/2021 ZAW HAN
Quality Review Completed 2/2/2021 GARO TELMI
Building Plans Picked Up 2/8/2021 APPLICANT
Applicant returned to address corrections 10/1/2021 ZAW HAN
Plan Check Approved 10/4/2021 ZAW HAN
Issued 11/8/2021 APPLICANT
CofO in Progress 11/6/2025 CHARLES BOGHOSKHAN
Permit Finaled 11/10/2025 DEROLD HAUFF
CofO Issued 11/10/2025 DEROLD HAUFF
Permit Finaled 11/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/26/2021 THOMAS LANG
Permit Cleared 2/26/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 3/19/2021 THOMAS LANG
Low Impact Development Cleared 8/13/2021 YVAINNE GALSIM
Construction near power lines Cleared 9/7/2021 RIDWAN HARDY
Construction within easement Cleared 9/7/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 9/28/2021 THOMAS LANG
Sewer availability Cleared 9/28/2021 THOMAS LANG

Contact Information

Contractor N B K Construction; Lic. No.: 987864-B 16738 LAKESHORE DR H40      LAKE ELSINORE, CA 92530
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 12/15/2021 No Access for Inspection JOAQUIN GREENOUGH
Underground Mechanical 12/15/2021 No Access for Inspection JOAQUIN GREENOUGH
Pre-Inspection 12/17/2021 Corrections Issued ANTHONY EGSON
Underground Mechanical 1/24/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 2/10/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/16/2022 Approved ANTHONY EGSON
Drywall Nailing 3/3/2022 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 3/3/2022 Approved ANTHONY EGSON
Green Building Rough 3/3/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 3/14/2022 Approved ANTHONY EGSON
Deputy Wood Construction 4/5/2022 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 4/7/2022 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 10/11/2022 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 7/31/2023 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 7/31/2023 Approved ANTHONY EGSON
PLUMBING-Rough 7/31/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 12/20/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 12/20/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Partial Approval STUART CHAPMAN
Pre-Inspection 3/11/2024 Partial Inspection ANTHONY EGSON
Insulation 3/20/2024 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 3/20/2024 Approved ANTHONY EGSON
Shower Pan 3/20/2024 Approved ANTHONY EGSON
Insulation 3/26/2024 Approved ANTHONY EGSON
Drywall Nailing 4/8/2024 Partial Approval BRENDAN MORELLI
Green Building Rough 4/8/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 4/8/2024 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Final 7/24/2025 Corrections Issued LUIS CASTRO
Final 7/24/2025 Corrections Issued LUIS CASTRO
HVAC-Final 7/24/2025 Corrections Issued LUIS CASTRO
PLUMBING-Final 7/24/2025 Corrections Issued LUIS CASTRO
Drywall Nailing 9/12/2025 No Access for Inspection LUIS CASTRO
Final 9/12/2025 No Access for Inspection LUIS CASTRO
Green Building Final 9/12/2025 No Access for Inspection LUIS CASTRO
Green Building Rough 9/12/2025 No Access for Inspection LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Ready LUIS CASTRO
Service/Power Release 9/12/2025 No Access for Inspection LUIS CASTRO
Smoke Detectors 9/12/2025 No Access for Inspection LUIS CASTRO
HVAC-Final 9/16/2025 Corrections Issued LUIS CASTRO
Rough-Elec/Plmb/HVAC 9/16/2025 Corrections Issued LUIS CASTRO
Drywall Nailing 10/30/2025 Conditional Approval LUIS CASTRO
ELECTRICAL-Final 10/30/2025 Approved LUIS CASTRO
Final 10/30/2025 Corrections Issued LUIS CASTRO
Green Building Final 10/30/2025 Not Ready for Inspection LUIS CASTRO
Green Building Rough 10/30/2025 Approved LUIS CASTRO
HVAC-Final 10/30/2025 Approved LUIS CASTRO
PLUMBING-Final 10/30/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Approved LUIS CASTRO
Service/Power Release 10/30/2025 Not Ready for Inspection LUIS CASTRO
Smoke Detectors 10/30/2025 Approved LUIS CASTRO
Drywall Nailing 11/5/2025 Approved LUIS CASTRO
ELECTRICAL-Final 11/5/2025 Approved LUIS CASTRO
Final 11/5/2025 OK to Issue CofO LUIS CASTRO
Green Building Final 11/5/2025 Approved LUIS CASTRO
Green Building Rough 11/5/2025 Approved LUIS CASTRO
HVAC-Final 11/5/2025 Approved LUIS CASTRO
PLUMBING-Final 11/5/2025 Approved LUIS CASTRO
Service/Power Release 11/5/2025 Approved LUIS CASTRO
Drywall Nailing 11/6/2025 Not Ready for Inspection LUIS CASTRO
Green Building Rough 11/6/2025 Approved LUIS CASTRO