1964 N UPPERTON PL 90042

Certificate Information: 1964 N UPPERTON PL 90042

Application / Permit
20010-10000-03312
Plan Check / Job No.
B20LA17363
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY GARAGE & ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 6/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 CRYSTEL MAALOUF
Corrections Issued 11/2/2020 CRYSTEL MAALOUF
Quality Review Completed 11/19/2020 WING SUEN
Building Plans Picked Up 11/20/2020 APPLICANT
Applicant returned to address corrections 4/23/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 5/3/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 12/3/2021 CRYSTEL MAALOUF
Plan Check Approved 6/10/2022 CRYSTEL MAALOUF
Issued 6/16/2022 APPLICANT
CofO in Progress 4/29/2025 BRENDAN MORELLI
No Progress 4/30/2025 DEROLD HAUFF
CofO in Progress 4/30/2025 DEROLD HAUFF
CofO in Progress 7/3/2025 DEROLD HAUFF
Permit Finaled 7/24/2025 DEROLD HAUFF
CofO Issued 7/24/2025 DEROLD HAUFF
Permit Finaled 7/24/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/3/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 12/3/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 12/3/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 7/8/2021 CECILIO NAVARRO
Sewer availability Cleared 7/8/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 7/23/2021 KURT CORRAL
Low Impact Development Cleared 3/9/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 3/15/2022 WALLIE JONG
GPI Written Notices Cleared 6/10/2022 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 6/10/2022 CRYSTEL MAALOUF

Contact Information

Architect , ; Lic. No.: C34339 340 N AVENUE 51      LOS ANGELES, CA 90042
Contractor A Grade Construction; Lic. No.: 925835-B 1443 EAST WASHINGTON BLVD #107      PASADENA, CA 91104
Engineer Ibarra,, Marco Antonio; Lic. No.: C74010 16 N MARENGON AVE STE 604      PASADENA, CA 91101

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 7/18/2022 Conditional Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 8/10/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 8/10/2022 Not Ready for Inspection CRAIG VAUGHAN
Piling/Pier/Caisson 8/10/2022 Partial Approval CRAIG VAUGHAN
Underground Mechanical 8/10/2022 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 8/15/2022 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 9/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 9/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/12/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 12/12/2022 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 12/12/2022 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 12/12/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 12/12/2022 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 12/12/2022 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 12/13/2022 Approved CRAIG VAUGHAN
Deputy Wood Construction 12/16/2022 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 12/20/2022 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Rough 12/20/2022 Not Ready for Inspection RUBEN SALAS
Green Building Rough 12/20/2022 Not Ready for Inspection RUBEN SALAS
HVAC-Rough 12/20/2022 Not Ready for Inspection RUBEN SALAS
Sewer 12/20/2022 Approved RUBEN SALAS
Shower Pan 12/20/2022 Approved RUBEN SALAS
Underground Mechanical 12/20/2022 Approved RUBEN SALAS
Verify Sprinkler Sign Off 12/20/2022 Corrections Issued RUBEN SALAS
BUILDING-Rough-Frame 3/31/2023 Conditional Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/31/2023 Approved CRAIG VAUGHAN
Green Building Rough 3/31/2023 Approved CRAIG VAUGHAN
HVAC-Rough 3/31/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 3/31/2023 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 3/31/2023 Approved CRAIG VAUGHAN
HVAC-Rough 4/13/2023 Approved CRAIG VAUGHAN
Insulation 4/13/2023 Approved CRAIG VAUGHAN
Drywall Nailing 4/28/2023 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 4/28/2023 Partial Approval CRAIG VAUGHAN
Pre-Inspection 1/2/2024 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 5/28/2024 Approved ALIZAH MAYAGOITIA
Final 5/28/2024 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/28/2024 Approved ALIZAH MAYAGOITIA
Green Building Final 5/28/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Not Required ALIZAH MAYAGOITIA
Service/Power Release 5/28/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 5/28/2024 No Access for Inspection ALIZAH MAYAGOITIA
Final 1/30/2025 Not Ready for Inspection BRENDAN MORELLI
Service/Power Release 1/30/2025 Approved BRENDAN MORELLI
Smoke Detectors 1/30/2025 Approved BRENDAN MORELLI
Final 4/29/2025 OK to Issue CofO BRENDAN MORELLI
Special/Order Compliance 5/14/2025 Corrections Issued BRENDAN MORELLI