1021 1/2 S STEARNS DR 90035
Certificate Information: 1021 1/2 S STEARNS DR 90035
- Application / Permit
- 20010-10000-03298
- Plan Check / Job No.
- B20LA17208
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of existing 2 car garage into new ADU. Addition of new roof height.
- Permit Issued
- Issued on 1/13/2021
- Issuing Office
- Current Status
- CofO Issued on 7/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | JOE VO |
| Corrections Issued | 10/22/2020 | JOE VO |
| Quality Review Completed | 11/2/2020 | MINYE PAK |
| Plan Check Approved | 12/15/2020 | JOE VO |
| Issued | 1/13/2021 | APPLICANT |
| CofO in Progress | 5/25/2021 | STUART CHAPMAN |
| No Progress | 3/4/2023 | MICHAEL PELHAM |
| Permit Finaled | 7/11/2026 | DEROLD HAUFF |
| CofO Issued | 7/11/2026 | DEROLD HAUFF |
| Permit Finaled | 7/11/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/9/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 11/9/2020 | WALLIE JONG |
| Sewer availability | Cleared | 11/9/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2020 | WALLIE JONG |
| HPOZ | Cleared | 12/10/2020 | JONATHAN KAPLAN |
| Historic monument | Cleared | 12/10/2020 | JONATHAN KAPLAN |
Contact Information
| Contractor | Golden Star Construction; Lic. No.: 933982-B | 2726 LEXINGTON AVENUE EL MONTE, CA 91733 |
| Engineer | Lu,, Ining; Lic. No.: S3042 | 47 E LAS FLORES AVENUE ARCADIA, CA 91006 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/4/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/1/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 3/1/2021 | Conditional Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/8/2021 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 3/8/2021 | Approved | SCOTT FINNILA |
| HVAC-Rough | 3/11/2021 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 3/11/2021 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 3/17/2021 | Approved | STUART CHAPMAN |
| Wood Frame | 3/17/2021 | Approved | STUART CHAPMAN |
| Drywall Nailing | 3/23/2021 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 3/23/2021 | Not Ready for Inspection | RUBEN SALAS |
| Interior/Exterior Lathing | 4/21/2021 | Approved | ALAN MORELOS |
| Pre-Inspection | 4/21/2021 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 5/14/2021 | Approved | STUART CHAPMAN |
| Final | 5/14/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 5/14/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 5/14/2021 | Approved | STUART CHAPMAN |
| METHANE-Final | 5/14/2021 | Approved | STUART CHAPMAN |
| METHANE-Rough | 5/14/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 5/14/2021 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 5/14/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 5/25/2021 | Approved | STUART CHAPMAN |
| Final | 5/25/2021 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 5/25/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 5/25/2021 | Approved | STUART CHAPMAN |