6256 N RADFORD AVE 91606

Certificate Information: 6256 N RADFORD AVE 91606

Application / Permit
20010-10000-03292
Plan Check / Job No.
B20LA17195
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan - New detached ADU
Permit Issued
Issued on 4/16/2021
Issuing Office
Current Status
Issued on 4/16/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/18/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 ARSALAN SHABESTARI
Corrections Issued 10/26/2020 ARSALAN SHABESTARI
Quality Review Completed 11/4/2020 MINYE PAK
Applicant returned to address corrections 12/5/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 2/11/2021 ARSALAN SHABESTARI
Plan Check Approved 2/18/2021 ARSALAN SHABESTARI
Issued 4/16/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/12/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 11/13/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/17/2020 GUILLERMO PETRA
Sewer availability Cleared 11/17/2020 GUILLERMO PETRA
Construction near power lines Cleared 1/20/2021 RIDWAN HARDY
Construction within easement Cleared 1/20/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/27/2021 Approved DANIEL DREW
PLUMBING-Rough 4/27/2021 Partial Approval DANIEL DREW
Sewer 4/27/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 6/3/2021 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/3/2021 Approved JENNIFER RABUCHIN
Green Building Rough 6/3/2021 Corrections Issued JENNIFER RABUCHIN
Special/Order Compliance 6/3/2021 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 6/3/2021 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 6/9/2021 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 6/14/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 6/14/2021 Approved ARAM AVEDISIAN
Green Building Rough 6/14/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 6/14/2021 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 6/14/2021 Approved ARAM AVEDISIAN
Insulation 7/1/2021 Approved DANIEL DREW
Drywall Nailing 7/8/2021 Approved DANIEL DREW
Drywall Nailing 8/9/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/9/2021 Approved JAVIER RAMOS JR
Shower Pan 8/9/2021 Approved JAVIER RAMOS JR
ELECTRICAL-Final 10/13/2021 Approved DANIEL DREW
Final 10/13/2021 Not Ready for Inspection DANIEL DREW
Green Building Final 10/13/2021 Approved DANIEL DREW
HVAC-Final 10/13/2021 Approved DANIEL DREW
PLUMBING-Final 10/13/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 10/13/2021 SGSOV Approved DANIEL DREW
Service/Power Release 10/13/2021 Approved DANIEL DREW
Smoke Detectors 10/13/2021 Approved DANIEL DREW