3427 S BUCKINGHAM ROAD 90016
Certificate Information: 3427 S BUCKINGHAM ROAD 90016
- Application / Permit
- 20010-10000-03284
- Plan Check / Job No.
- B20LA17128
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY 19' X 25' ADU AT REAR OF LOT.
- Permit Issued
- Issued on 4/5/2021
- Issuing Office
- Current Status
- CofO Issued on 2/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 9/26/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 1/25/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 2/3/2021 | LUKE GONZALES |
| Plan Check Approved | 3/18/2021 | AUNG SOE |
| Issued | 4/5/2021 | APPLICANT |
| Building Plans Picked Up | 4/12/2021 | APPLICANT |
| CofO in Progress | 2/9/2024 | JUSTIN HAWLEY |
| Permit Finaled | 2/19/2024 | DEROLD HAUFF |
| CofO Issued | 2/19/2024 | DEROLD HAUFF |
| Permit Finaled | 2/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 10/7/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 10/8/2020 | RENZ SORIANO |
| Highway dedication | Cleared | 1/5/2021 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2021 | RENZ SORIANO |
| Flood clearance | Cleared | 3/8/2021 | BRYAN GATHUKA |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | 20501 VENTURA BLVD #135 WOODLAND HILLS, CA 91364 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/28/2021 | Partial Approval | DAVID FEILER |
| Pre-Inspection | 4/28/2021 | Not Ready for Inspection | DAVID FEILER |
| Underground Mechanical | 4/28/2021 | Partial Approval | DAVID FEILER |
| FLOOD-Elevation Certificate | 5/10/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/10/2021 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 5/10/2021 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 5/10/2021 | Approved | STUART CHAPMAN |
| Sewer | 2/18/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 2/18/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2022 | Partial Approval | STUART CHAPMAN |
| Sewer | 3/1/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/21/2022 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 3/21/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 3/21/2022 | Corrections Issued | STUART CHAPMAN |
| Wood Frame | 3/21/2022 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 3/31/2022 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 3/31/2022 | Corrections Issued | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 3/31/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Shower Pan | 3/31/2022 | Approved | STUART CHAPMAN |
| Wood Frame | 3/31/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 4/6/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/6/2022 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 4/6/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 4/13/2022 | Approved | STUART CHAPMAN |
| Sewer | 5/25/2022 | Approved | SCOTT FINNILA |
| FLOOD-Proofing Certificate | 3/2/2023 | Corrections Issued | DONALD CRICHLOW |
| BUILDING-Rough-Frame | 2/9/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 2/9/2024 | Approved | JUSTIN HAWLEY |
| FLOOD-Elevation Certificate | 2/9/2024 | Approved | JUSTIN HAWLEY |
| FLOOD-Proofing Certificate | 2/9/2024 | Approved | JUSTIN HAWLEY |
| Final | 2/9/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 2/9/2024 | Approved | JUSTIN HAWLEY |
| Green Building Final | 2/9/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 2/9/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 2/9/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 2/9/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 2/9/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Service/Power Release | 2/9/2024 | Approved | JUSTIN HAWLEY |
| Smoke Detectors | 2/9/2024 | Approved | JUSTIN HAWLEY |