443 E VERNON AVE 90011

Certificate Information: 443 E VERNON AVE 90011

Application / Permit
20010-10000-03276
Plan Check / Job No.
B20LA17065
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW THREE (3) STORY TYPE V-A 13 UNIT 100% AFFORDABLE APARTMENT BUILDING (TWO LOW INCOME AND 11 LOW INCOME). TOC TIER 2 WITH BASE INCENTIVES ONLY
Permit Issued
Issued on 10/20/2021
Issuing Office
Current Status
CofO Issued on 2/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 MANUEL MONTUFAR
Corrections Issued 10/9/2020 MANUEL MONTUFAR
Quality Review Completed 10/15/2020 RODOLFO ARIAS
Applicant returned to address corrections 3/2/2021 MANUEL MONTUFAR
Green Plans Picked Up 4/9/2021 APPLICANT
Applicant returned to address corrections 4/13/2021 MANUEL MONTUFAR
Applicant returned to address corrections 4/16/2021 MANUEL MONTUFAR
Applicant returned to address corrections 4/21/2021 MANUEL MONTUFAR
Applicant returned to address corrections 4/27/2021 MANUEL MONTUFAR
Applicant returned to address corrections 5/7/2021 MANUEL MONTUFAR
Plan Check Approved 8/27/2021 MANUEL MONTUFAR
Issued 10/20/2021 APPLICANT
Building Plans Picked Up 10/22/2021 APPLICANT
CofO in Progress 2/2/2024 MARTIN TAVITIAN
CofO in Progress 2/2/2024 MARTIN TAVITIAN
CofO Issued 2/6/2024 ERNESTO CORRAL
Permit Finaled 2/6/2024 ERNESTO CORRAL

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 12/22/2020 HELEN JADALI
Historic Resource Verification Cleared 2/1/2021 MICAELA TORRES-GIL
Address approval Cleared 2/18/2021 WALLIE JONG
Sewer availability Cleared 2/22/2021 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 3/2/2021 JASON CHAN
Opn space landscape/Water mgmt Cleared 3/2/2021 JASON CHAN
Bicycle Parking Cleared 3/3/2021 ELAINE LEI
Redevelopment Project Area Cleared 3/8/2021 DAVID URITA
Eng Process Fee Ord 176,300 Cleared 3/16/2021 PAMELA TENEZA
Building over 36-ft Cleared 4/1/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/1/2021 CALOSHA APPROVED
Green Code Cleared 4/9/2021 AARON COSTA
Community Plan Implem. Overlay Cleared 4/15/2021 THAN WIN
Community Plan Implem. Overlay Cleared 4/16/2021 KEVIN ARUCAN
Driveway location Cleared 4/16/2021 KEVIN ARUCAN
Highway dedication Cleared 4/20/2021 RENZ SORIANO
Permit Cleared 4/20/2021 RENZ SORIANO
Density Bonus 12.22.A.31 Cleared 4/26/2021 NICHOLAS KAWAZOE
Density Bonus 12.22.A.31 Cleared 4/26/2021 NICHOLAS KAWAZOE
Trees in Parkway Cleared 4/26/2021 JOHN KIM
Community Plan Implem. Overlay Cleared 4/29/2021 JOHN KIM
Hydrant and Access approval Cleared 5/13/2021 KURT CORRAL
Fire Marshal Fire Life Safety Cleared 6/2/2021 VIDAL GARCIA
Community Plan Implem. Overlay Cleared 6/3/2021 RIDWAN HARDY
Construction near power lines Cleared 6/3/2021 RIDWAN HARDY
Low Impact Development Cleared 7/2/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/6/2021 WALLIE JONG
Work Adjacent to Public Way Cleared 8/10/2021 CHIU TAM
DAS Clearance Cleared 8/19/2021 MANUEL MONTUFAR
Miscellaneous Cleared 8/27/2021 MANUEL MONTUFAR

Contact Information

Contractor Owner-Builder       ,
Engineer Afshar,, Rouzbeh; Lic. No.: C87032 1133 CAMELBACK ST 9038      NEWPORT BEACH, CA 92658
Engineer Bozorgnia,, Behrouz; Lic. No.: C79581 1557 WESTWOOD BLVD 145      LOS ANGELES, CA 90024
Engineer Molai,, Mohamad Ali; Lic. No.: L9192 24308 BURBANK BLVD      WOODLAND HILLS, CA 91367

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/6/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/10/2021 Partial Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 12/10/2021 Partial Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 1/12/2022 Partial Approval SORIN CIRSTOIU
Deputy Wood Construction 1/26/2022 Conditional Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Partial Approval RUSSELL BONVOULOIR
Deputy Wood Construction 2/3/2022 Approved SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 2/3/2022 Partial Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Partial Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Partial Inspection SORIN CIRSTOIU
Deputy Wood Construction 3/1/2022 Conditional Approval JONATHAN QUACH
Green Building Rough 4/5/2022 Partial Approval SORIN CIRSTOIU
Verify Sprinkler Sign Off 4/5/2022 Partial Approval SORIN CIRSTOIU
Wood Frame 4/5/2022 Partial Approval SORIN CIRSTOIU
Insulation 5/6/2022 Partial Inspection JONATHAN QUACH
Insulation 5/11/2022 Partial Approval SORIN CIRSTOIU
Insulation 5/25/2022 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 5/25/2022 Partial Approval SORIN CIRSTOIU
Deputy Wood Construction 5/26/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Approved RUSSELL BONVOULOIR
Insulation 6/3/2022 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 6/29/2022 Partial Approval RUSSELL BONVOULOIR
Insulation 6/29/2022 Approved RUSSELL BONVOULOIR
Drywall Nailing 7/8/2022 Approved RUSSELL BONVOULOIR
Drywall Nailing 7/25/2022 Partial Approval RUSSELL BONVOULOIR
Interior/Exterior Lathing 8/1/2022 Approved RUSSELL BONVOULOIR
Drywall Nailing 9/8/2022 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 9/23/2022 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 9/23/2022 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 11/7/2022 Partial Inspection RUSSELL BONVOULOIR
Green Building Final 3/17/2023 Partial Approval MARTIN TAVITIAN
Green Building Final 4/5/2023 Not Ready for Inspection ALAN MORELOS
Special/Order Compliance 5/17/2023 Approved MARTIN TAVITIAN
Final 8/24/2023 Not Ready for Inspection MARTIN TAVITIAN
Footing/Foundation/Slab 8/24/2023 Approved MARTIN TAVITIAN
Green Building Final 8/24/2023 Not Ready for Inspection MARTIN TAVITIAN
Green Building Rough 8/24/2023 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Not Ready MARTIN TAVITIAN
Smoke Detectors 8/24/2023 Not Ready for Inspection MARTIN TAVITIAN
Verify Sprinkler Sign Off 8/24/2023 Partial Inspection MARTIN TAVITIAN
Wood Frame 8/24/2023 Not Ready for Inspection MARTIN TAVITIAN
Special/Order Compliance 11/16/2023 Partial Inspection MARTIN TAVITIAN
Final 2/2/2024 OK to Issue CofO MARTIN TAVITIAN
Green Building Final 2/2/2024 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 2/2/2024 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 2/2/2024 Approved MARTIN TAVITIAN
Verify Sprinkler Sign Off 2/2/2024 Approved MARTIN TAVITIAN
Wood Frame 2/2/2024 Approved MARTIN TAVITIAN