306-308 E 49TH ST 90011
Certificate Information: 306-308 E 49TH ST 90011
- Application / Permit
- 20010-10000-03270
- Plan Check / Job No.
- B20LA17043
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE.
- Permit Issued
- Issued on 12/8/2020
- Issuing Office
- Current Status
- CofO Issued on 9/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 10/19/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 10/28/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 10/30/2020 | APPLICANT |
| Plan Check Approved | 12/8/2020 | SERGIO GUTIERREZ |
| Issued | 12/8/2020 | APPLICANT |
| CofO in Progress | 9/15/2021 | JOAQUIN GREENOUGH |
| Permit Finaled | 9/16/2021 | DEROLD HAUFF |
| CofO Issued | 9/16/2021 | DEROLD HAUFF |
| Permit Finaled | 9/16/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/5/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 11/6/2020 | YVAINNE GALSIM |
| Sewer availability | Cleared | 11/6/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 11/10/2020 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 11/12/2020 | CELINA MORENO |
| Highway dedication | Cleared | 11/16/2020 | CECILIO NAVARRO |
| Frnt yard landscape/Water mgmt | Cleared | 11/17/2020 | TERRI OSBORNE |
| Permit | Cleared | 11/25/2020 | JAMES MORALEZ |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/5/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2021 | Partial Approval | ROBERT MCDOWELL |
| PLUMBING-Rough | 2/5/2021 | Partial Approval | ROBERT MCDOWELL |
| Sewer | 2/5/2021 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 2/5/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 2/10/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2021 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 3/19/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 6/29/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/29/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 6/29/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/29/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/1/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/1/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/1/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/1/2021 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 7/1/2021 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/2/2021 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 7/2/2021 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/9/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/9/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/16/2021 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/16/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/31/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 8/31/2021 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Green Building Final | 8/31/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 8/31/2021 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 8/31/2021 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/31/2021 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 8/31/2021 | Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 8/31/2021 | Approved | JOAQUIN GREENOUGH |