15809 S MENLO AVE 90247
Certificate Information: 15809 S MENLO AVE 90247
- Application / Permit
- 20010-10000-03268
- Plan Check / Job No.
- B20LA17024
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED ACCESSORY DWELLING UNIT PER LAMC LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 9/22/2020 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 12/7/2020 | DANIEL YIP |
| Applicant returned to address corrections | 3/22/2021 | FERNANDO FLORES |
| Plan Check Approved | 3/23/2021 | FERNANDO FLORES |
| Issued | 5/24/2021 | APPLICANT |
| Building Plans Picked Up | 5/27/2021 | APPLICANT |
| CofO in Progress | 5/17/2022 | ALIZAH MAYAGOITIA |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| CofO Issued | 8/20/2022 | DEROLD HAUFF |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/16/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 12/24/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2020 | CHINH DINH |
| Sewer availability | Cleared | 12/24/2020 | CHINH DINH |
| Low Impact Development | Cleared | 3/11/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/23/2021 | CHINH DINH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/11/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/15/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/18/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 6/25/2021 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 6/30/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2021 | Partial Approval | JOHN KLARIN |
| Wood Frame | 7/23/2021 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 8/13/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 8/13/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/13/2021 | Approved | EUGENE CASSIDY |
| Insulation | 8/19/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Interior/Exterior Lathing | 8/19/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 8/19/2021 | Approved | ANSON MAGLASANG |
| Shower Pan | 8/19/2021 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 8/23/2021 | Approved | ANSON MAGLASANG |
| Insulation | 8/23/2021 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 8/23/2021 | Partial Approval | ANSON MAGLASANG |
| Interior/Exterior Lathing | 9/2/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/15/2021 | Approved | EUGENE CASSIDY |
| Final | 10/15/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/15/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 10/15/2021 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/15/2021 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 10/15/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 10/15/2021 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 10/15/2021 | Approved | EUGENE CASSIDY |
| Final | 10/29/2021 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 10/29/2021 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Final | 10/29/2021 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Final | 10/29/2021 | Corrections Issued | CRAIG DAVIS |
| Service/Power Release | 10/29/2021 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 12/9/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 12/9/2021 | Approved | JOHN KLARIN |
| Service/Power Release | 12/9/2021 | Not Ready for Inspection | JOHN KLARIN |
| Final | 4/25/2022 | Not Ready for Inspection | JOHN KLARIN |
| Service/Power Release | 4/25/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 5/17/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/17/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/17/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 5/17/2022 | Approved | ALIZAH MAYAGOITIA |