407-407 1/2 E 70TH ST 90003
Certificate Information: 407-407 1/2 E 70TH ST 90003
- Application / Permit
- 20010-10000-03267
- Plan Check / Job No.
- B20LA17020
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) DETACHED 2-CAR GARAGE
- Permit Issued
- Issued on 8/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | DANIEL YIP |
| Corrections Issued | 10/21/2020 | DANIEL YIP |
| Quality Review Completed | 10/28/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 10/30/2020 | APPLICANT |
| Plan Check Approved | 2/11/2021 | DANIEL YIP |
| Plan Check Approved | 3/3/2022 | DANIEL YIP |
| Issued | 8/9/2022 | APPLICANT |
| CofO in Progress | 1/5/2023 | LILIANA PORTILLO |
| Permit Finaled | 1/19/2023 | DEROLD HAUFF |
| CofO Issued | 1/19/2023 | DEROLD HAUFF |
| Permit Finaled | 1/19/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/29/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/28/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/28/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/31/2022 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/10/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 1/4/2023 | Approved | LILIANA PORTILLO |
| Final | 1/4/2023 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 1/4/2023 | Approved | LILIANA PORTILLO |
| HVAC-Final | 1/4/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 1/4/2023 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 1/4/2023 | SGSOV Not Required | LILIANA PORTILLO |
| Service/Power Release | 1/4/2023 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 1/4/2023 | Approved | LILIANA PORTILLO |
| Service/Power Release | 1/12/2023 | Approved | LILIANA PORTILLO |