292-294 E 49TH ST 90011

Certificate Information: 292-294 E 49TH ST 90011

Application / Permit
20010-10000-03261
Plan Check / Job No.
B20LA17018
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY DUPLEX WITH ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 12/29/2020
Issuing Office
Current Status
CofO Issued on 7/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 DANIEL YIP
Corrections Issued 10/19/2020 DANIEL YIP
Quality Review Completed 10/28/2020 ALLEN MANALANSAN
Building Plans Picked Up 10/30/2020 APPLICANT
Plan Check Approved 12/10/2020 DANIEL YIP
Issued 12/29/2020 APPLICANT
CofO in Progress 7/23/2021 ALEJANDRO DE ARTOLA
Permit Finaled 7/27/2021 DEROLD HAUFF
CofO Issued 7/27/2021 DEROLD HAUFF
Permit Finaled 7/27/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/4/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 11/4/2020 RENZ SORIANO
Sewer availability Cleared 11/5/2020 RENZ SORIANO
Hydrant and Access approval Cleared 11/10/2020 KURT CORRAL
Highway dedication Cleared 11/16/2020 RENZ SORIANO
Low Impact Development Cleared 11/17/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/17/2020 CELINA MORENO
Trees in Parkway Cleared 11/17/2020 JOHN KIM
Permit Cleared 11/24/2020 JAMES MORALEZ

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/13/2021 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/5/2021 Partial Approval ROBERT MCDOWELL
PLUMBING-Rough 2/5/2021 Partial Approval ROBERT MCDOWELL
Sewer 2/5/2021 Approved ROBERT MCDOWELL
Underground Mechanical 2/5/2021 Approved ROBERT MCDOWELL
Insulation 2/10/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 2/23/2021 Partial Approval ROBERT MCDOWELL
Deputy Wood Construction 3/3/2021 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 3/23/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 3/23/2021 Approved ROBERT MCDOWELL
Green Building Rough 3/23/2021 Approved ROBERT MCDOWELL
HVAC-Rough 3/23/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 3/23/2021 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 3/23/2021 Approved ROBERT MCDOWELL
Insulation 4/6/2021 Approved ROBERT MCDOWELL
Drywall Nailing 4/15/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 4/15/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 7/2/2021 Approved ALEJANDRO DE ARTOLA
Final 7/2/2021 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/2/2021 Approved ALEJANDRO DE ARTOLA
Gas Test 7/2/2021 Approved ALEJANDRO DE ARTOLA
Green Building Final 7/2/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 7/2/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 7/2/2021 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/2/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 7/2/2021 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 7/2/2021 Approved ALEJANDRO DE ARTOLA
Final 7/22/2021 OK to Issue CofO ALEJANDRO DE ARTOLA