424-424 1/2 E 30TH ST 90011
Certificate Information: 424-424 1/2 E 30TH ST 90011
- Application / Permit
- 20010-10000-03257
- Plan Check / Job No.
- B20LA17001
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX WITH 4 PARKING SPACES
- Permit Issued
- Issued on 2/17/2021
- Issuing Office
- Current Status
- CofO Issued on 10/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/20/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/27/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 10/30/2020 | APPLICANT |
| Applicant returned to address corrections | 1/5/2021 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 1/25/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 2/17/2021 | MAHNAZ NOURHASHEMI |
| Issued | 2/17/2021 | APPLICANT |
| CofO in Progress | 10/12/2022 | HORACE FULTZ |
| Permit Finaled | 10/14/2022 | DEROLD HAUFF |
| CofO Issued | 10/14/2022 | DEROLD HAUFF |
| Permit Finaled | 10/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/16/2020 | JEANIE LAM |
| Permit | Cleared | 11/16/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2020 | JEANIE LAM |
| Sewer availability | Cleared | 11/17/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 12/17/2020 | MATTHEW CRAIG |
| Highway dedication | Cleared | 1/6/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 1/6/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/7/2021 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 1/13/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Gemilyan Karen; Lic. No.: 801955-B | 18841 PASADERO DRIVE TARZANA, CA 91356 |
| Engineer | Hakemi,, Fahim; Lic. No.: S5160 | 26982 MARBELLA MISSION VIEJO, CA 92691 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/30/2021 | Approved | ROBERT MCDOWELL |
| Posting Pre-Inspection | 3/30/2021 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 3/30/2021 | Approved | ROBERT MCDOWELL |
| Wood Frame | 4/27/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Partial Approval | ROBERT MCDOWELL |
| Green Building Rough | 5/7/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 5/7/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Wood Frame | 5/11/2021 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 6/15/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 6/15/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 8/9/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 8/9/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 8/9/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/10/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/10/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/10/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/24/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 8/24/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/14/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 9/14/2021 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Final | 9/14/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 9/14/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 9/14/2021 | Corrections Issued | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 9/14/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/15/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 9/15/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/21/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 9/21/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/4/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 10/4/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 10/4/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/8/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/14/2021 | Approved | JOAQUIN GREENOUGH |
| Insulation | 10/14/2021 | Approved | JOAQUIN GREENOUGH |
| Special/Order Compliance | 10/14/2021 | Approved | HECTOR ALIKHAN |
| Drywall Nailing | 10/22/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 10/22/2021 | Approved | JOAQUIN GREENOUGH |
| Sewer | 2/8/2022 | Approved | JOAQUIN GREENOUGH |
| Pre-Inspection | 2/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/19/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 4/19/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 5/23/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 5/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 5/23/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 5/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 5/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 6/6/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 6/6/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 6/6/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 6/6/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 6/9/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Final | 6/9/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 6/9/2022 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 6/9/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 7/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 7/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/22/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 7/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 7/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 8/4/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 8/4/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 8/4/2022 | Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 8/4/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 10/12/2022 | OK to Issue CofO | HORACE FULTZ |