1351 E PALMS BLVD 90291
Certificate Information: 1351 E PALMS BLVD 90291
- Application / Permit
- 20010-10000-03200
- Plan Check / Job No.
- B20LA16758
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW STATE APPROVED FACTORY BUILT HOME FOR ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 1/26/2021
- Issuing Office
- Current Status
- CofO Issued on 12/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2020 | GEORGE ALVAREZ |
| Corrections Issued | 9/28/2020 | GEORGE ALVAREZ |
| Plan Check Approved | 1/12/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| Issued | 1/26/2021 | APPLICANT |
| CofO in Progress | 10/26/2021 | JOHNNY MIRANDA |
| CofO in Progress | 10/26/2021 | JOHNNY MIRANDA |
| Permit Finaled | 12/23/2021 | KENNETH NAGLE |
| CofO Issued | 12/23/2021 | KENNETH NAGLE |
| Permit Finaled | 12/23/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2020 | DINAH GARIN |
| Sewer availability | Cleared | 10/19/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 11/4/2020 | DINAH GARIN |
| Specific Plan | Cleared | 11/10/2020 | PEDRO AYALA |
Contact Information
| Contractor | Cover Building Technologies; Lic. No.: 1039029-B | 1219 W 135TH STREET GARDENA, CA 90247 |
| Engineer | Sveiven,, Shane; Lic. No.: C89133 | 5900 CANTERBURY DR APT A206 CULVER CITY, CA 90230 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/28/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/13/2021 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 5/13/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Sewer | 5/18/2021 | Approved | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 5/28/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/3/2021 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 6/3/2021 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/3/2021 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 6/4/2021 | Corrections Issued | JOHNNY MIRANDA |
| Special/Order Compliance | 6/4/2021 | Partial Inspection | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 6/28/2021 | Approved | JOHNNY MIRANDA |
| Grounding or Bonding | 6/28/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/7/2021 | Approved | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 7/21/2021 | Partial Approval | PIERRE VEGA |
| Footing/Foundation/Slab | 7/21/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/30/2021 | Approved | JOHNNY MIRANDA |
| Final | 9/30/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 9/30/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 9/30/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 9/30/2021 | SGSOV Not Required | JOHNNY MIRANDA |
| Service/Power Release | 9/30/2021 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 9/30/2021 | Approved | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 9/30/2021 | Approved | JOHNNY MIRANDA |
| Final | 10/5/2021 | OK to Issue CofO | JOHNNY MIRANDA |
| Final | 10/26/2021 | OK to Issue CofO | JOHNNY MIRANDA |