1351 E PALMS BLVD 90291

Certificate Information: 1351 E PALMS BLVD 90291

Application / Permit
20010-10000-03200
Plan Check / Job No.
B20LA16758
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW STATE APPROVED FACTORY BUILT HOME FOR ACCESSORY DWELLING UNIT
Permit Issued
Issued on 1/26/2021
Issuing Office
Current Status
CofO Issued on 12/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2020 APPLICANT
Assigned to Plan Check Engineer 9/28/2020 GEORGE ALVAREZ
Corrections Issued 9/28/2020 GEORGE ALVAREZ
Plan Check Approved 1/12/2021 RICARDO RAMIREZ
Building Plans Picked Up 1/14/2021 APPLICANT
Issued 1/26/2021 APPLICANT
CofO in Progress 10/26/2021 JOHNNY MIRANDA
CofO in Progress 10/26/2021 JOHNNY MIRANDA
Permit Finaled 12/23/2021 KENNETH NAGLE
CofO Issued 12/23/2021 KENNETH NAGLE
Permit Finaled 12/23/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 10/15/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/19/2020 DINAH GARIN
Sewer availability Cleared 10/19/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 11/4/2020 DINAH GARIN
Specific Plan Cleared 11/10/2020 PEDRO AYALA

Contact Information

Contractor Cover Building Technologies; Lic. No.: 1039029-B 1219 W 135TH STREET      GARDENA, CA 90247
Engineer Sveiven,, Shane; Lic. No.: C89133 5900 CANTERBURY DR APT A206      CULVER CITY, CA 90230

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/28/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 5/13/2021 Corrections Issued KEVIN SARGSYAN
Sewer 5/13/2021 Not Ready for Inspection KEVIN SARGSYAN
Sewer 5/18/2021 Approved JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 5/28/2021 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 6/3/2021 Partial Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 6/3/2021 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 6/3/2021 Partial Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 6/4/2021 Corrections Issued JOHNNY MIRANDA
Special/Order Compliance 6/4/2021 Partial Inspection PIERRE VEGA
Excavation/Setback/Form/Re-Bar 6/28/2021 Approved JOHNNY MIRANDA
Grounding or Bonding 6/28/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 7/7/2021 Approved JOHNNY MIRANDA
Deputy Drilled-In Anchors 7/21/2021 Partial Approval PIERRE VEGA
Footing/Foundation/Slab 7/21/2021 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 9/30/2021 Approved JOHNNY MIRANDA
Final 9/30/2021 Corrections Issued JOHNNY MIRANDA
Green Building Final 9/30/2021 Approved JOHNNY MIRANDA
Green Building Rough 9/30/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 9/30/2021 SGSOV Not Required JOHNNY MIRANDA
Service/Power Release 9/30/2021 Approved JOHNNY MIRANDA
Smoke Detectors 9/30/2021 Approved JOHNNY MIRANDA
Verify Sprinkler Sign Off 9/30/2021 Approved JOHNNY MIRANDA
Final 10/5/2021 OK to Issue CofO JOHNNY MIRANDA
Final 10/26/2021 OK to Issue CofO JOHNNY MIRANDA