1003 E 52ND ST 90011
Certificate Information: 1003 E 52ND ST 90011
- Application / Permit
- 20010-10000-03198
- Plan Check / Job No.
- B20LA16757
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 27' X 31' 1-STORY A.D.U. AT REAR OF LOT PER WFPP. (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 12/15/2021
- Issuing Office
- Current Status
- CofO Issued on 7/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/3/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 9/10/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 9/27/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 10/13/2021 | DANIEL SANJUAN |
| Applicant returned to address corrections | 11/3/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 12/2/2021 | AUNG SOE |
| Plan Check Approved | 12/3/2021 | AUNG SOE |
| Issued | 12/15/2021 | APPLICANT |
| Building Plans Picked Up | 12/17/2021 | APPLICANT |
| CofO in Progress | 7/1/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
| CofO Issued | 7/9/2022 | DEROLD HAUFF |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/5/2021 | MARTIN FRAGOSO |
| Address approval | Cleared | 8/20/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 8/27/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 10/21/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/27/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/27/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 2/3/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 2/8/2022 | Partial Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 2/8/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 2/11/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/9/2022 | Not Ready for Inspection | HORACE FULTZ |
| HVAC-Rough | 3/9/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 3/9/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 3/10/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/10/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/17/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2022 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 3/17/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Insulation | 3/24/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 3/24/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/31/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/31/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 3/31/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 3/31/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 3/31/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 3/31/2022 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 3/31/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 4/6/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 4/6/2022 | Approved | JOAQUIN GREENOUGH |
| Sewer | 4/6/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 5/9/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/9/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 5/9/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 5/9/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 5/9/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 5/9/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 6/17/2022 | Not Ready for Inspection | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Approved | HORACE FULTZ |
| Service/Power Release | 6/17/2022 | Approved | HORACE FULTZ |
| PLUMBING-Final | 6/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 6/22/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 6/28/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 6/28/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| HVAC-Final | 6/28/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 6/28/2022 | Approved | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 6/28/2022 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 6/28/2022 | Approved | JOAQUIN GREENOUGH |