1038 W 51ST PL 90037

Certificate Information: 1038 W 51ST PL 90037

Application / Permit
20010-10000-03197
Plan Check / Job No.
B20LA16752
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER WFPP
Permit Issued
Issued on 1/31/2022
Issuing Office
Current Status
Issued on 1/31/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/17/2020 APPLICANT
Assigned to Plan Check Engineer 9/21/2020 RICARDO RAMIREZ
Corrections Issued 9/21/2020 RICARDO RAMIREZ
Applicant returned to address corrections 1/5/2022 SAMUEL GONZALEZ
Applicant returned to address corrections 1/12/2022 ZAW HAN
Plan Check Approved 1/18/2022 ZAW HAN
Issued 1/31/2022 APPLICANT
Building Plans Picked Up 2/7/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/30/2020 JEANIE LAM
Permit Cleared 11/30/2020 JEANIE LAM
Low Impact Development Cleared 6/30/2021 ANDRES COVARRUBIAS
Eng Process Fee Ord 176,300 Cleared 7/28/2021 JEANIE LAM
Sewer availability Cleared 7/28/2021 JEANIE LAM
Construction near power lines Cleared 11/2/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 12/17/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 1/12/2022 THAN WIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/3/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/13/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 11/21/2022 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 11/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 11/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 11/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Approved SABAS ALONSO
Green Building Rough 1/24/2023 Approved SABAS ALONSO
PLUMBING-Rough 1/24/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 2/27/2023 Corrections Issued SABAS ALONSO
Green Building Rough 2/27/2023 Approved SABAS ALONSO
HVAC-Rough 2/27/2023 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 2/27/2023 Partial Approval SABAS ALONSO
PLUMBING-Rough 2/27/2023 Approved SABAS ALONSO
Underground Mechanical 2/27/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 2/27/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 3/23/2023 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 3/23/2023 Approved SABAS ALONSO
HVAC-Rough 3/23/2023 Approved SABAS ALONSO
Insulation 4/12/2023 Approved BRENDAN MORELLI
Drywall Nailing 4/26/2023 Approved SABAS ALONSO
Drywall Nailing 4/28/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/11/2023 Approved JOSEPH MCGARRY
Shower Pan 5/11/2023 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 7/9/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Final 9/26/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 9/26/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 9/26/2025 SGSOV Approved BARRY HACHE
Smoke Detectors 9/26/2025 Corrections Issued BARRY HACHE