142 W 84TH ST 90003

Certificate Information: 142 W 84TH ST 90003

Application / Permit
20010-10000-03188
Plan Check / Job No.
B20LA16710
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING AT FRONT. (1 OF 2)
Permit Issued
Issued on 1/26/2021
Issuing Office
Current Status
CofO Issued on 10/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 KEVIN MORALES
Corrections Issued 9/29/2020 KEVIN MORALES
Quality Review Completed 10/1/2020 EUGENE BARBEAU
Plan Check Approved 1/19/2021 KEVIN MORALES
Issued 1/26/2021 APPLICANT
Building Plans Picked Up 1/27/2021 APPLICANT
CofO in Progress 10/15/2021 ALEJANDRO DE ARTOLA
Permit Finaled 10/20/2021 DEROLD HAUFF
CofO Issued 10/20/2021 DEROLD HAUFF
Permit Finaled 10/20/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/4/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 11/5/2020 JUAN ASHTON
Sewer availability Cleared 11/18/2020 JUAN ASHTON
Low Impact Development Cleared 12/22/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/22/2020 JUAN ASHTON
Hydrant and Access approval Cleared 1/4/2021 MATTHEW CRAIG
Frnt yard landscape/Water mgmt Cleared 1/14/2021 SARAHI ORTEGA

Contact Information

Contractor New World Construction; Lic. No.: 864461-B 838 E 93RD STREET      LOS ANGELES, CA 90002
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/23/2021 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 2/23/2021 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 3/1/2021 Approved ALEJANDRO DE ARTOLA
Deputy Wood Construction 4/14/2021 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 4/20/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 5/5/2021 Approved EUGENE CASSIDY
HVAC-Rough 5/5/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 5/5/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/6/2021 Approved EUGENE CASSIDY
Green Building Rough 5/6/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 5/6/2021 Approved EUGENE CASSIDY
Insulation 5/10/2021 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 5/10/2021 Not Ready for Inspection DAVID FEILER
Drywall Nailing 5/17/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
Insulation 5/17/2021 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/17/2021 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 5/24/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/4/2021 Approved ALEJANDRO DE ARTOLA
Final 8/4/2021 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/4/2021 Approved ALEJANDRO DE ARTOLA
Gas Test 8/4/2021 Approved ALEJANDRO DE ARTOLA
Green Building Final 8/4/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 8/4/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/4/2021 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 8/4/2021 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 8/4/2021 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 8/4/2021 Approved ALEJANDRO DE ARTOLA
Final 8/9/2021 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/14/2021 OK to Issue CofO ALEJANDRO DE ARTOLA