142 W 84TH ST 90003
Certificate Information: 142 W 84TH ST 90003
- Application / Permit
- 20010-10000-03188
- Plan Check / Job No.
- B20LA16710
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING AT FRONT. (1 OF 2)
- Permit Issued
- Issued on 1/26/2021
- Issuing Office
- Current Status
- CofO Issued on 10/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | KEVIN MORALES |
| Corrections Issued | 9/29/2020 | KEVIN MORALES |
| Quality Review Completed | 10/1/2020 | EUGENE BARBEAU |
| Plan Check Approved | 1/19/2021 | KEVIN MORALES |
| Issued | 1/26/2021 | APPLICANT |
| Building Plans Picked Up | 1/27/2021 | APPLICANT |
| CofO in Progress | 10/15/2021 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 10/20/2021 | DEROLD HAUFF |
| CofO Issued | 10/20/2021 | DEROLD HAUFF |
| Permit Finaled | 10/20/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 11/18/2020 | JUAN ASHTON |
| Low Impact Development | Cleared | 12/22/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/22/2020 | JUAN ASHTON |
| Hydrant and Access approval | Cleared | 1/4/2021 | MATTHEW CRAIG |
| Frnt yard landscape/Water mgmt | Cleared | 1/14/2021 | SARAHI ORTEGA |
Contact Information
| Contractor | New World Construction; Lic. No.: 864461-B | 838 E 93RD STREET LOS ANGELES, CA 90002 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/23/2021 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 2/23/2021 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 3/1/2021 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 4/14/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/5/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 5/5/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/5/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/6/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 5/6/2021 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 5/6/2021 | Approved | EUGENE CASSIDY |
| Insulation | 5/10/2021 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 5/10/2021 | Not Ready for Inspection | DAVID FEILER |
| Drywall Nailing | 5/17/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Insulation | 5/17/2021 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 5/17/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/24/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/4/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 8/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/4/2021 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 8/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/9/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 10/14/2021 | OK to Issue CofO | ALEJANDRO DE ARTOLA |