3806-3808 S BUDLONG AVE 90037

Certificate Information: 3806-3808 S BUDLONG AVE 90037

Application / Permit
20010-10000-03187
Plan Check / Job No.
B20LA16707
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW DUPLEX WITH ATTACHED GARAGE AT REAR. (2 OF 2)
Permit Issued
Issued on 5/17/2021
Issuing Office
Current Status
CofO Issued on 10/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 KEVIN MORALES
Corrections Issued 10/27/2020 KEVIN MORALES
Quality Review Completed 11/2/2020 EUGENE BARBEAU
Plan Check Approved 4/28/2021 KEVIN MORALES
Issued 5/17/2021 APPLICANT
Building Plans Picked Up 5/19/2021 APPLICANT
CofO in Progress 10/18/2022 SABAS ALONSO
CofO Issued 10/21/2022 DEROLD HAUFF
Permit Finaled 10/21/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/25/2020 RENZ SORIANO
Address approval Cleared 11/30/2020 RENZ SORIANO
Trees in Parkway Cleared 12/28/2020 JOHN KIM
Hydrant and Access approval Cleared 1/6/2021 MATTHEW CRAIG
Sewer availability Cleared 2/1/2021 RENZ SORIANO
ZA Case Cleared 2/5/2021 TERRI OSBORNE
ZI Cleared 2/9/2021 TERRI OSBORNE
Frnt yard landscape/Water mgmt Cleared 2/16/2021 TERRI OSBORNE
Low Impact Development Cleared 2/23/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/23/2021 RENZ SORIANO
Highway dedication Cleared 3/25/2021 RENZ SORIANO
Permit Cleared 3/25/2021 RENZ SORIANO

Contact Information

Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 7/16/2021 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 7/19/2021 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/24/2021 Corrections Issued SABAS ALONSO
Green Building Rough 9/24/2021 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 9/24/2021 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 10/29/2021 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval SABAS ALONSO
Green Building Rough 10/29/2021 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 10/29/2021 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 10/29/2021 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 10/29/2021 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 11/23/2021 Not Ready for Inspection SABAS ALONSO
Green Building Rough 11/24/2021 Approved SABAS ALONSO
HVAC-Rough 11/24/2021 Approved SABAS ALONSO
Verify Sprinkler Sign Off 11/24/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/30/2021 Approved SABAS ALONSO
Green Building Rough 11/30/2021 Approved SABAS ALONSO
Rough-Elec/Plmb/HVAC 11/30/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 12/3/2021 Corrections Issued SHAVONNE ESPINOZA
Drywall Nailing 12/30/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Verify Rec and Parks Fee Memo 5/12/2022 Approved HORACE FULTZ
Drywall Nailing 8/3/2022 Approved SABAS ALONSO
Final 8/3/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 8/3/2022 Approved SABAS ALONSO
Green Building Final 8/3/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 8/3/2022 SGSOV Approved SABAS ALONSO
Service/Power Release 8/3/2022 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 8/3/2022 Approved SABAS ALONSO
Final 8/9/2022 Corrections Issued SABAS ALONSO
Service/Power Release 8/9/2022 Approved SABAS ALONSO
Final 10/19/2022 OK to Issue CofO SABAS ALONSO