13850 W MULHOLLAND DR 90210

Certificate Information: 13850 W MULHOLLAND DR 90210

Application / Permit
20010-10000-03137
Plan Check / Job No.
B20LA16439
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Building (to permitted use)
Work Description
NEW BATHROOM BUILDING W/ COVER DECK AND ROOF DECK FOR POOL USE 3 OF 5
Permit Issued
Issued on 9/16/2022
Issuing Office
Metro
Current Status
Issued on 9/16/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 SAM CHANG
Corrections Issued 10/30/2020 SAM CHANG
Quality Review Completed 11/6/2020 TIEN JEN WANG
Building Plans Picked Up 11/18/2020 APPLICANT
Applicant returned to address corrections 5/23/2022 SAM CHANG
Applicant returned to address corrections 8/26/2022 SAM CHANG
Plan Check Approved 9/12/2022 SAM CHANG
Issued 9/16/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/21/2021 RAYMOND MUGAMBWA
BHO/Hillside ordinance Cleared 2/26/2021 RAYMOND MUGAMBWA
BHO/Hillside ordinance Cleared 2/26/2021 RAYMOND MUGAMBWA
Highway dedication Cleared 2/26/2021 RAYMOND MUGAMBWA
Hydrant and Access approval Cleared 5/27/2021 KURT CORRAL
Miscellaneous Cleared 6/24/2021 MARC WOERSCHING
Low Impact Development Cleared 7/4/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/13/2021 ANTHONY MAINEZ
Miscellaneous Cleared 8/26/2022 BRENNEN OBETO
Specific Plan Cleared 8/26/2022 BRENNEN OBETO
GPI Written Notices Cleared 8/29/2022 SAM CHANG
Grading Pre-Inspection Cleared 8/29/2022 SAM CHANG
Green Code Cleared 8/29/2022 SAM CHANG
BHO/Hillside ordinance Cleared 9/6/2022 CATHERINE ADROVER
Sewer availability Cleared 9/7/2022 DINAH GARIN

Contact Information

Contractor Salehipour Sassan Abolghasem; Lic. No.: 1046288-B 1290 N LAKE AVE SUITE 204      PASADENA, CA 91101
Engineer Gharibans,, Armineh H; Lic. No.: S3801 18544 BRYMER STREET      NORTHRIDGE, CA 91326
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/3/2023 Partial Approval BRENDAN LOONEY
PLUMBING-Rough 11/3/2023 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 11/14/2023 Not Ready for Inspection BRENDAN LOONEY
Pre-Inspection 11/20/2023 Partial Approval BRENDAN LOONEY
Special/Order Compliance 11/20/2023 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 2/27/2024 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 3/13/2024 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 4/3/2024 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 5/13/2024 Partial Approval SEAN HAUPT
PLUMBING-Rough 5/13/2024 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Partial Approval SEAN HAUPT
PLUMBING-Rough 6/25/2024 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 7/8/2024 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 12/17/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 3/24/2025 Approved SEAN HAUPT
ELECTRICAL-Rough 3/24/2025 Approved SEAN HAUPT
HVAC-Rough 3/24/2025 Approved SEAN HAUPT
Insulation 5/22/2025 Approved SEAN HAUPT
HVAC-Final 2/17/2026 Approved CARLOS MATAMOROS
PLUMBING-Final 2/17/2026 Approved CARLOS MATAMOROS