8526 N GOTHIC AVE 91343
Certificate Information: 8526 N GOTHIC AVE 91343
- Application / Permit
- 20010-10000-03107
- Plan Check / Job No.
- B20LA16337
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. PROPOSED DETACHED (36' X 32.5' ) ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 8/24/2021
- Issuing Office
- Current Status
- CofO Issued on 4/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | MICHAEL LOPEZ |
| Corrections Issued | 10/8/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 10/13/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 2/3/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/22/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 3/14/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 4/26/2021 | MICHAEL LOPEZ |
| Issued | 8/24/2021 | APPLICANT |
| CofO in Progress | 8/2/2024 | RAUL OLAGI |
| CofO in Progress | 8/21/2024 | JUAN VALENZUELA |
| No Progress | 8/22/2024 | RAUL OLAGI |
| CofO in Progress | 4/10/2025 | RAUL OLAGI |
| CofO in Progress | 4/10/2025 | RAUL OLAGI |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
| CofO Issued | 4/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/27/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/28/2020 | GUILLERMO PETRA |
| ZA Case | Cleared | 12/23/2020 | LAUREN PADICK |
| Hydrant and Access approval | Cleared | 12/25/2020 | JEREMY CARTER |
| Construction near power lines | Cleared | 1/26/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/26/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 4/9/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 4/12/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Zaian Construction; Lic. No.: 1065937-B | 18212 BATHURST STREET PORTER RANCH, CA 91326 |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/24/2021 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 11/12/2021 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 12/1/2021 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2021 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Partial Approval | RAUL OLAGI |
| HVAC-Rough | 3/8/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 3/8/2022 | Approved | RAUL OLAGI |
| Sewer | 3/8/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 3/8/2022 | Partial Approval | RAUL OLAGI |
| Verify Sprinkler Sign Off | 3/8/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 3/21/2022 | Approved | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Partial Inspection | KRISTEN CAUSEY |
| Shower Pan | 3/21/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 4/18/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 4/18/2022 | Approved | RAUL OLAGI |
| Insulation | 4/18/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 4/18/2022 | Partial Approval | RAUL OLAGI |
| Deputy Wood Construction | 5/5/2022 | Conditional Approval | RAUL OLAGI |
| Drywall Nailing | 5/6/2022 | Approved | ALAN MORELOS |
| Footing/Foundation/Slab | 7/25/2022 | Corrections Issued | ALAN MORELOS |
| Footing/Foundation/Slab | 8/1/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 9/6/2022 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Final | 9/6/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Final | 9/6/2022 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Final | 1/27/2023 | Corrections Issued | RAUL OLAGI |
| Final | 1/27/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 1/27/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 1/27/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 1/27/2023 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 1/27/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 7/22/2024 | Approved | RAUL OLAGI |
| PLUMBING-Final | 7/22/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 7/22/2024 | SGSOV Approved | RAUL OLAGI |
| Final | 8/2/2024 | Not Ready for Inspection | RAUL OLAGI |
| Service/Power Release | 8/2/2024 | Approved | RAUL OLAGI |
| Special/Order Compliance | 8/26/2024 | Corrections Issued | RAUL OLAGI |
| Final | 4/10/2025 | OK to Issue CofO | RAUL OLAGI |