712-712 1/2 W 81ST ST 90044

Certificate Information: 712-712 1/2 W 81ST ST 90044

Application / Permit
20010-10000-03104
Plan Check / Job No.
B20LA16325
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2 STORY DUPLEX
Permit Issued
Issued on 2/14/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 HERNAN ARREOLA
Corrections Issued 10/8/2020 HERNAN ARREOLA
Quality Review Completed 10/13/2020 ALLEN MANALANSAN
Building Plans Picked Up 10/16/2020 APPLICANT
Applicant returned to address corrections 2/1/2023 HERNAN ARREOLA
Plan Check Approved 2/14/2023 HERNAN ARREOLA
Issued 2/14/2023 APPLICANT
CofO in Progress 12/4/2024 MICHAEL LEWIS
Permit Finaled 12/12/2024 DEROLD HAUFF
CofO Issued 12/12/2024 DEROLD HAUFF
Permit Finaled 12/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/2/2020 JUAN ASHTON
Hydrant and Access approval Cleared 1/6/2021 MATTHEW CRAIG
Sewer availability Cleared 6/8/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/9/2022 PAMELA TENEZA
Low Impact Development Cleared 10/12/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 10/18/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/31/2023 Partial Inspection LILIANA PORTILLO
Pre-Inspection 4/6/2023 Partial Inspection LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 4/12/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 4/12/2023 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 4/19/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 4/25/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Corrections Issued STUART CHAPMAN
Deputy Wood Construction 5/24/2023 Conditional Approval MICHAEL LEWIS
HVAC-Rough 7/7/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 7/7/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 8/2/2023 Approved MICHAEL LEWIS
Wood Frame 8/2/2023 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 8/25/2023 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 8/31/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 9/25/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/6/2023 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 10/6/2023 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 10/6/2023 Approved STUART CHAPMAN
Insulation 10/27/2023 Approved MICHAEL LEWIS
Pre-Inspection 11/1/2023 Approved MICHAEL LEWIS
Drywall Nailing 11/9/2023 Corrections Issued MICHAEL LEWIS
Green Building Rough 11/9/2023 Approved MICHAEL LEWIS
Drywall Nailing 11/15/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 4/16/2024 SGSOV Approved MICHAEL LEWIS
Sewer 4/16/2024 Approved MICHAEL LEWIS
Underground Mechanical 4/16/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 10/1/2024 No Access for Inspection SABAS ALONSO
Smoke Detectors 10/1/2024 No Access for Inspection SABAS ALONSO
ELECTRICAL-Final 11/15/2024 Corrections Issued MICHAEL LEWIS
HVAC-Final 11/15/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 11/15/2024 Corrections Issued MICHAEL LEWIS
Smoke Detectors 11/15/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 11/19/2024 Partial Inspection MICHAEL LEWIS
ELECTRICAL-Final 11/26/2024 Approved MICHAEL LEWIS
HVAC-Final 11/26/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 11/26/2024 Approved MICHAEL LEWIS
Smoke Detectors 11/26/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/3/2024 Approved MICHAEL LEWIS
Final 12/3/2024 OK to Issue CofO MICHAEL LEWIS
Green Building Final 12/3/2024 Approved MICHAEL LEWIS
HVAC-Final 12/3/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/3/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 12/3/2024 Approved MICHAEL LEWIS