284 S MUIRFIELD ROAD 90004

Certificate Information: 284 S MUIRFIELD ROAD 90004

Application / Permit
20010-10000-03098
Plan Check / Job No.
B20LA16276
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
(N) PATIO COVER WITH SOLAR PANEL
Permit Issued
Issued on 6/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 DANIEL YIP
Corrections Issued 11/2/2020 DANIEL YIP
Quality Review Completed 11/12/2020 ALLEN MANALANSAN
Applicant returned to address corrections 4/20/2021 DANIEL YIP
Plan Check Approved 11/15/2021 DANIEL YIP
Building Plans Picked Up 12/3/2021 APPLICANT
Issued 6/29/2022 APPLICANT
CofO in Progress 6/22/2023 RICHARD DOCKUS
Permit Finaled 7/20/2023 DEROLD HAUFF
CofO Issued 7/20/2023 DEROLD HAUFF
Permit Finaled 7/20/2023 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 2/22/2021 SUKI GERSHENHORN
Low Impact Development Cleared 2/25/2021 SARAH YOUSSEF
Construction near power lines Cleared 3/20/2021 RIDWAN HARDY

Contact Information

Contractor Shaw David Architect; Lic. No.: 370737-B 4346 VICTORIA PARK PL      LOS ANGELES, CA 90019

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/5/2022 Approved ADAM ESCOTO
Footing/Foundation/Slab 7/14/2022 Partial Approval JULIAN AMAYA
METHANE-Barrier 7/14/2022 Partial Approval JULIAN AMAYA
METHANE-Subgrade 7/14/2022 Partial Approval JULIAN AMAYA
Footing/Foundation/Slab 7/20/2022 Partial Approval ADAM ESCOTO
METHANE-Barrier 7/20/2022 Partial Approval ADAM ESCOTO
METHANE-Subgrade 7/20/2022 Partial Approval ADAM ESCOTO
Rough-Elec/Plmb/HVAC 12/13/2022 Corrections Issued RICHARD DOCKUS
Wood Frame 12/13/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 4/13/2023 Approved RICHARD DOCKUS
Final 4/13/2023 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 4/13/2023 Approved RICHARD DOCKUS
METHANE-Barrier 4/13/2023 Approved RICHARD DOCKUS
METHANE-Final 4/13/2023 Approved RICHARD DOCKUS
METHANE-Rough 4/13/2023 Approved RICHARD DOCKUS
METHANE-Subgrade 4/13/2023 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Not Ready RICHARD DOCKUS
Service/Power Release 4/13/2023 Not Required RICHARD DOCKUS
Smoke Detectors 4/13/2023 No Access for Inspection RICHARD DOCKUS
Verify Sprinkler Sign Off 4/13/2023 Approved RICHARD DOCKUS
Final 6/15/2023 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/15/2023 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 6/15/2023 Corrections Issued LILIANA PORTILLO
Drywall Nailing 6/21/2023 Approved RICHARD DOCKUS
Final 6/21/2023 OK to Issue CofO RICHARD DOCKUS
Smoke Detectors 6/21/2023 Approved RICHARD DOCKUS