15153 W NURMI ST 91342
Certificate Information: 15153 W NURMI ST 91342
- Application / Permit
- 20010-10000-03074
- Plan Check / Job No.
- B20LA16157
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c) & (d)
- Permit Issued
- Issued on 5/27/2021
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | LAMAR DAVIS |
| Corrections Issued | 10/7/2020 | LAMAR DAVIS |
| Quality Review Completed | 10/15/2020 | TU HUA |
| Applicant returned to address corrections | 2/3/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 2/17/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 2/24/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 3/17/2021 | LAMAR DAVIS |
| Plan Check Approved | 5/12/2021 | LAMAR DAVIS |
| Issued | 5/27/2021 | APPLICANT |
| CofO in Progress | 11/9/2022 | ARAM AVEDISIAN |
| No Progress | 11/10/2022 | ARAM AVEDISIAN |
| CofO in Progress | 11/15/2022 | ARAM AVEDISIAN |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
| CofO Issued | 11/19/2022 | MICHAEL SMITH |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/25/2021 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 1/27/2021 | BARTON HOLMES |
| Miscellaneous | Cleared | 2/4/2021 | LAMAR DAVIS |
| Hydrant and Access approval | Cleared | 2/18/2021 | KURT CORRAL |
| GPI Written Notices | Cleared | 3/12/2021 | TIMOTHY POWELL |
| Construction near power lines | Cleared | 3/17/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 4/26/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/29/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/11/2021 | Approved | MICHAEL TEMPLE |
| Gas Test | 6/28/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/28/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 7/1/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/1/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/15/2021 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2021 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 12/15/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 12/20/2021 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 12/20/2021 | Corrections Issued | JOHN HAYES |
| Gas Test | 1/6/2022 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 1/6/2022 | Partial Approval | JOHN HAYES |
| Pre-Inspection | 1/11/2022 | Partial Approval | JOHN HAYES |
| Pre-Inspection | 1/11/2022 | Partial Inspection | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 1/27/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 1/27/2022 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 1/27/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 2/1/2022 | Partial Approval | JOHN HAYES |
| Green Building Rough | 2/1/2022 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 2/1/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 2/9/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 2/9/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 2/9/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 2/9/2022 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 2/9/2022 | Approved | JOHN HAYES |
| Pre-Inspection | 2/9/2022 | Partial Inspection | MICHAEL TEMPLE |
| Shower Pan | 2/9/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 2/14/2022 | Approved | JOHN HAYES |
| Green Building Rough | 2/14/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 2/14/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 10/20/2022 | Approved | ROBERT GOLD |
| Final | 10/20/2022 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 10/20/2022 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 10/20/2022 | SGSOV Approved | ROBERT GOLD |
| Service/Power Release | 10/20/2022 | Not Ready for Inspection | ROBERT GOLD |
| Smoke Detectors | 10/20/2022 | Approved | ROBERT GOLD |
| Verify Sprinkler Sign Off | 10/20/2022 | Approved | ROBERT GOLD |
| Final | 10/25/2022 | Corrections Issued | DAVID ANDERSON |
| Service/Power Release | 10/25/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 11/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 11/1/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 11/9/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 11/9/2022 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 11/10/2022 | Corrections Issued | ARAM AVEDISIAN |