16111 W SAN JOSE ST 91344
Certificate Information: 16111 W SAN JOSE ST 91344
- Application / Permit
- 20010-10000-03037
- Plan Check / Job No.
- B20LA16080
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED DETACHED ADU PER ORDINANCE 2-STORY 1 OF 2
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Current Status
- CofO Issued on 1/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | CARLOS MONTES |
| Corrections Issued | 10/7/2020 | CARLOS MONTES |
| Quality Review Completed | 10/28/2020 | WING SUEN |
| Applicant returned to address corrections | 1/25/2021 | CARLOS MONTES |
| Plan Check Approved | 2/8/2021 | CARLOS MONTES |
| Issued | 2/19/2021 | APPLICANT |
| Building Plans Picked Up | 2/26/2021 | APPLICANT |
| CofO in Progress | 12/23/2021 | MICHAEL TEMPLE |
| CofO Issued | 1/29/2022 | MICHAEL SMITH |
| Permit Finaled | 1/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/16/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 11/19/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/7/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 1/7/2021 | MARTIN FRAGOSO |
| Construction near power lines | Cleared | 1/14/2021 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 1/19/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mejia,, Fernando Finuliar; Lic. No.: C54382 | 8305 DUCOR AVE WEST HILLS, CA 91304 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/4/2021 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 3/10/2021 | Corrections Issued | MARK JOHNSON |
| ELECTRICAL-Rough | 3/31/2021 | Not Ready for Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 4/12/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 5/4/2021 | Not Ready for Inspection | MARK JOHNSON |
| Drywall Nailing | 5/4/2021 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Rough | 5/4/2021 | Not Ready for Inspection | MARK JOHNSON |
| Verify Sprinkler Sign Off | 5/4/2021 | Not Ready for Inspection | MARK JOHNSON |
| Wood Frame | 5/4/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 5/19/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 5/19/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 6/2/2021 | Approved | MARK JOHNSON |
| Wood Frame | 6/2/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 6/9/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 6/9/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 6/9/2021 | Approved | MARK JOHNSON |
| Verify Sprinkler Sign Off | 6/9/2021 | Approved | MARK JOHNSON |
| Insulation | 6/16/2021 | Approved | MARK JOHNSON |
| Shower Pan | 6/16/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 6/18/2021 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 6/24/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/16/2021 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Final | 10/21/2021 | Approved | MARK JOHNSON |
| Final | 12/15/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 12/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 12/15/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 12/16/2021 | SGSOV Not Ready | MARK JOHNSON |
| Final | 12/21/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Final | 12/21/2021 | Approved | MICHAEL TEMPLE |
| PLUMBING-Final | 12/21/2021 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 12/21/2021 | SGSOV Approved | MICHAEL TEMPLE |
| Smoke Detectors | 12/21/2021 | Approved | MICHAEL TEMPLE |
| Final | 12/23/2021 | OK to Issue CofO | MICHAEL TEMPLE |
| Service/Power Release | 12/23/2021 | Approved | MICHAEL TEMPLE |