5806 W LEXINGTON AVE 90038

Certificate Information: 5806 W LEXINGTON AVE 90038

Application / Permit
20010-10000-03018
Plan Check / Job No.
B20LA15970
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 5-STORY (TOTAL 17 DWELLING UNITS APARTMENT INCLUDING 2 EXTREMELY LOW INCOME AFFORDABLE UNITS ) OVER A PARKING GARAGE ON GRADE PER DIR-2019-7067-TOC. CONSTRUCTION TYPE OF PARKING LEVEL IS TYPE I-A, RESIDENTIAL LEVELS ARE TYPE V-A. "COMPLY WITH DEPARTMENT ORDER effective date 11/05/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 5/25/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 YOUNG KIM
Disabled Access Plans Picked Up 10/5/2020 APPLICANT
Corrections Issued 12/3/2020 YOUNG KIM
Quality Review Completed 12/4/2020 SAI KHUM
Building Plans Picked Up 12/8/2020 APPLICANT
Applicant returned to address corrections 12/11/2020 YOUNG KIM
Applicant returned to address corrections 12/15/2020 YOUNG KIM
Applicant returned to address corrections 12/22/2020 YOUNG KIM
Applicant returned to address corrections 12/31/2020 YOUNG KIM
Green Plans Picked Up 4/6/2021 APPLICANT
Applicant returned to address corrections 4/13/2021 YOUNG KIM
Applicant returned to address corrections 4/14/2021 YOUNG KIM
Applicant returned to address corrections 4/15/2021 YOUNG KIM
Applicant returned to address corrections 4/29/2021 YOUNG KIM
Applicant returned to address corrections 5/25/2021 YOUNG KIM
Applicant returned to address corrections 2/3/2022 YOUNG KIM
Plan Check Approved 5/4/2022 YOUNG KIM
Issued 5/25/2022 APPLICANT
CofO in Progress 1/8/2025 DAVID BURKHEAD
CofO Issued 1/8/2025 ERNESTO CORRAL
Permit Finaled 1/8/2025 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/20/2021 RENZ SORIANO
Building over 36-ft Cleared 4/8/2021 CALOSHA APPROVED
Address approval Cleared 4/20/2021 RENZ SORIANO
DAS Clearance Cleared 5/19/2021 SHINE LIN
Green Code Cleared 5/26/2021 YOUNG KIM
Trees in Parkway Cleared 6/28/2021 JOHN KIM
Sewer availability Cleared 6/30/2021 WALLIE JONG
Internal circulation Cleared 7/1/2021 MOHAMMAD HASAN
Watercourse Cleared 7/2/2021 SAM NAVID
Hydrant and Access approval Cleared 7/14/2021 MATTHEW CRAIG
Low Impact Development Cleared 11/19/2021 ORVAL HERNANDEZ-MARCI
Construction near power lines Cleared 11/24/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 12/6/2021 ABEL CASILLAS
Fire Marshal Fire Life Safety Cleared 2/25/2022 ANDREW KO
Historic Resource Verification Cleared 3/30/2022 MAX LODER
DCP conditions approval Cleared 4/6/2022 SAI KHUM
Density Bonus 12.22.A.31 Cleared 4/6/2022 RICHARD TRUONG
Frnt yard landscape/Water mgmt Cleared 4/21/2022 RUBEN VASQUEZ
Miscellaneous Cleared 4/21/2022 RUBEN VASQUEZ
Miscellaneous Cleared 4/21/2022 RUBEN VASQUEZ
Opn space landscape/Water mgmt Cleared 4/21/2022 RUBEN VASQUEZ
Prkng lot landscape/Water mgmt Cleared 4/21/2022 RUBEN VASQUEZ
Redevelopment Project Area Cleared 4/27/2022 SUSAN WONG

Contact Information

Architect Bittoni,, Mark Christopher; Lic. No.: C34136 434 N GREENCRAIG ROAD      LOS ANGELES, CA 90049
Contractor Category Construction Llc; Lic. No.: 1041679-B 8271 MELROSE AVE #207      LOS ANGELES, CA 90046
Engineer John,, Benjamin M; Lic. No.: C86018 11918 AVON WY 203      LOS ANGELES, CA 90066
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/15/2022 Approved TED RIES
Excavation/Setback/Form/Re-Bar 9/27/2022 Partial Approval TED RIES
Footing/Foundation/Slab 9/27/2022 Partial Approval TED RIES
Deputy Reinf. Concrete 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 10/5/2022 Partial Approval TED RIES
Masonry Wall/Backfill 10/12/2022 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 10/24/2022 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 11/7/2022 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 11/23/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 12/2/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 2/1/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 2/2/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 2/17/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 3/14/2023 Not Ready for Inspection DAVID BURKHEAD
Structural Steel Frame 3/14/2023 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 3/14/2023 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 3/31/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 3/31/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 3/31/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/10/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 4/10/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 4/10/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 4/20/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 4/20/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 4/20/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 4/27/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 4/27/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 4/27/2023 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 5/11/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/17/2023 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 6/5/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 6/5/2023 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 6/9/2023 Partial Approval RAFAEL ESPINOZA
Green Building Rough 6/9/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/9/2023 Partial Inspection RAFAEL ESPINOZA
Wood Frame 6/12/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 6/28/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 6/28/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 6/28/2023 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Partial Approval DAVID BURKHEAD
Insulation 7/5/2023 Partial Inspection DAVID BURKHEAD
Green Building Rough 7/10/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 7/10/2023 Partial Inspection EDWIN GREGORYONA
Wood Frame 7/10/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/20/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 7/20/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/2/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 8/2/2023 Partial Inspection DAVID BURKHEAD
Insulation 8/8/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/14/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 8/14/2023 Approved DAVID BURKHEAD
Insulation 8/14/2023 Partial Inspection DAVID BURKHEAD
Insulation 8/17/2023 Partial Approval VAHE KELEDJIAN
Drywall Nailing 8/22/2023 Partial Approval DAVID BURKHEAD
Insulation 9/5/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 10/3/2023 Partial Inspection DAVID BURKHEAD
Drywall Nailing 10/11/2023 Partial Approval LARRY ARNICK
Insulation 10/23/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 10/31/2023 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 11/3/2023 Partial Approval DAVID BURKHEAD
Insulation 11/6/2023 Approved DAVID BURKHEAD
Drywall Nailing 11/17/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 11/28/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 11/30/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 12/4/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 6/25/2024 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 7/2/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/15/2024 Partial Approval DAVID BURKHEAD
Pre-Inspection 7/22/2024 Partial Inspection DAVID BURKHEAD
Pre-Inspection 8/1/2024 Partial Inspection DAVID BURKHEAD
Drywall Nailing 1/7/2025 Approved DAVID BURKHEAD
Final 1/7/2025 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 1/7/2025 Approved DAVID BURKHEAD
Green Building Final 1/7/2025 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 1/7/2025 Approved DAVID BURKHEAD
Reinforced Masonry Frame 1/7/2025 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 1/7/2025 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 1/7/2025 Approved DAVID BURKHEAD
Structural Steel Frame 1/7/2025 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 1/7/2025 Approved DAVID BURKHEAD
Wood Frame 1/7/2025 Approved DAVID BURKHEAD
Final 1/8/2025 OK to Issue CofO DAVID BURKHEAD
Green Building Final 1/8/2025 Approved DAVID BURKHEAD