2316 N SICHEL ST 90031
Certificate Information: 2316 N SICHEL ST 90031
- Application / Permit
- 20010-10000-02978
- Plan Check / Job No.
- B20LA15858
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1 STORY ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 8/24/2021
- Issuing Office
- Current Status
- Issued on 8/24/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 12/2/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 12/14/2020 | WING SUEN |
| Plan Check Approved | 8/12/2021 | CRYSTEL MAALOUF |
| Issued | 8/24/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2021 | CECILIO NAVARRO |
| Highway dedication | Cleared | 1/29/2021 | CECILIO NAVARRO |
| HPOZ | Cleared | 2/1/2021 | JONATHAN KAPLAN |
| Miscellaneous | Cleared | 2/1/2021 | JONATHAN KAPLAN |
| ZI | Cleared | 2/1/2021 | JONATHAN KAPLAN |
| Hydrant and Access approval | Cleared | 2/16/2021 | MATTHEW CRAIG |
| Sewer availability | Cleared | 3/18/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 7/12/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/15/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | American Dream Design & Construction Inc; Lic. No.: 922825-B | P O BOX 6453 ROSEMEAD, CA 91770 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/23/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 9/28/2021 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 9/28/2021 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/2/2021 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2022 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 3/22/2022 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 3/22/2022 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/31/2022 | Approved | OSVALDO PARAMO |
| Green Building Rough | 3/31/2022 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 3/31/2022 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 3/31/2022 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 4/6/2022 | Partial Inspection | SCOTT FINNILA |
| Insulation | 4/6/2022 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 4/6/2022 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 4/21/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/21/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 8/12/2022 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Final | 8/12/2022 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 8/18/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 8/19/2022 | Approved | OSVALDO PARAMO |
| Final | 9/14/2022 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/14/2022 | Approved | OSVALDO PARAMO |
| Green Building Final | 9/14/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 9/14/2022 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 9/14/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 9/14/2022 | Approved | OSVALDO PARAMO |
| Final | 4/5/2023 | Corrections Issued | OSVALDO PARAMO |
| Service/Power Release | 4/5/2023 | Approved | OSVALDO PARAMO |
| Final | 12/14/2023 | Conditional Approval | OSVALDO PARAMO |