4985 W 3RD ST 90020
Certificate Information: 4985 W 3RD ST 90020
- Application / Permit
- 20010-10000-02944
- Plan Check / Job No.
- B20LA15722
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU PER 12.22 A33 C & D AND PER ADM-2020-3562-ADU
- Permit Issued
- Issued on 11/20/2021
- Issuing Office
- Current Status
- CofO Issued on 3/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | STARR CHEN |
| Corrections Issued | 9/12/2020 | STARR CHEN |
| Quality Review Completed | 10/7/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 10/9/2020 | APPLICANT |
| Applicant returned to address corrections | 7/29/2021 | STARR CHEN |
| Plan Check Approved | 9/3/2021 | STARR CHEN |
| Issued | 11/20/2021 | APPLICANT |
| CofO in Progress | 1/23/2023 | RICHARD DOCKUS |
| Permit Finaled | 3/7/2023 | DANIEL ORRANTE |
| CofO Issued | 3/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| HPOZ | Cleared | 10/29/2020 | LYDIA CHAPMAN |
| Hydrant and Access approval | Cleared | 11/23/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 12/31/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2021 | JEANIE LAM |
| Sewer availability | Cleared | 1/11/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 6/4/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 7/15/2021 | ORVAL HERNANDEZ-MARCI |
Contact Information
| Contractor | Ramos Manuel; Lic. No.: 937994-B | 29021 BOUQUET CANYON RD SP 341 SANTA CLARITA, CA 91390 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/9/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Barrier | 2/9/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 2/9/2022 | Partial Approval | ARTHUR SARGSYAN |
| METHANE-Subgrade | 2/9/2022 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/15/2022 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 4/27/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 4/27/2022 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 4/27/2022 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 4/27/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 4/27/2022 | Approved | ARTHUR SARGSYAN |
| Verify Sprinkler Sign Off | 4/27/2022 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 5/11/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 5/11/2022 | Approved | ARTHUR SARGSYAN |
| Insulation | 6/1/2022 | Corrections Issued | ADAM ESCOTO |
| Interior/Exterior Lathing | 6/1/2022 | Partial Approval | ADAM ESCOTO |
| Shower Pan | 6/1/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Insulation | 6/8/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 6/8/2022 | Approved | ADAM ESCOTO |
| Shower Pan | 6/8/2022 | Approved | ADAM ESCOTO |
| Drywall Nailing | 6/24/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Rough | 10/13/2022 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 10/28/2022 | SGSOV Not Ready | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 11/21/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 11/21/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Final | 12/1/2022 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 12/1/2022 | Approved | RICHARD DOCKUS |
| Green Building Final | 12/1/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 12/1/2022 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 12/1/2022 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Rough | 1/6/2023 | Approved | RICHARD DOCKUS |
| HVAC-Final | 1/11/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 1/11/2023 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 1/11/2023 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 1/11/2023 | Approved | RICHARD DOCKUS |
| Final | 1/20/2023 | OK to Issue CofO | RICHARD DOCKUS |
| Service/Power Release | 1/20/2023 | Approved | RICHARD DOCKUS |