6802-6802 1/2 S 11TH AVE 90043

Certificate Information: 6802-6802 1/2 S 11TH AVE 90043

Application / Permit
20010-10000-02939
Plan Check / Job No.
B20LA15692
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-STORY REAR DUPLEX
Permit Issued
Issued on 2/17/2022
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 DANIEL YIP
Corrections Issued 10/7/2020 DANIEL YIP
Quality Review Completed 10/14/2020 ALLEN MANALANSAN
Applicant returned to address corrections 4/7/2021 DANIEL YIP
Plan Check Approved 1/28/2022 DANIEL YIP
Issued 2/17/2022 APPLICANT
Building Plans Picked Up 3/11/2022 APPLICANT
CofO in Progress 5/23/2023 ENRIQUE MIRELES
Permit Finaled 3/29/2024 DEROLD HAUFF
CofO Issued 3/29/2024 DEROLD HAUFF
Permit Finaled 3/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/14/2020 CECILIO NAVARRO
Trees in Parkway Cleared 1/25/2021 JOHN KIM
Low Impact Development Cleared 8/11/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/4/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/13/2021 CECILIO NAVARRO
Sewer availability Cleared 11/1/2021 JEANIE LAM
Hydrant and Access approval Cleared 1/19/2022 KURT CORRAL

Contact Information

Contractor Jimenez Builders Inc; Lic. No.: 1049508-B 4832 W 112TH ST      INGLEWOOD, CA 90304
Engineer Morales,, Wilfrido; Lic. No.: C67533 6834 GEORGIA AVE      BELL, CA 90201
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/29/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 4/5/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 4/12/2022 No Access for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 4/25/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/16/2022 Corrections Issued ENRIQUE MIRELES
Green Building Rough 8/16/2022 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 8/16/2022 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 8/24/2022 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 8/24/2022 Approved ENRIQUE MIRELES
HVAC-Rough 8/24/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/24/2022 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 8/24/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/29/2022 Approved ENRIQUE MIRELES
Insulation 8/29/2022 Approved ENRIQUE MIRELES
Drywall Nailing 9/19/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 9/19/2022 Approved ENRIQUE MIRELES
Sewer 10/24/2022 Approved ALIZAH MAYAGOITIA
Gas Test 10/31/2022 Approved ENRIQUE MIRELES
Underground Mechanical 10/31/2022 Approved ENRIQUE MIRELES
Grading Pre-Inspection 11/7/2022 Approved ENRIQUE MIRELES
Underground Mechanical 11/7/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/20/2023 Approved ENRIQUE MIRELES
Final 3/20/2023 Corrections Issued ENRIQUE MIRELES
Gas Test 3/20/2023 Approved ENRIQUE MIRELES
Green Building Final 3/20/2023 Approved ENRIQUE MIRELES
HVAC-Final 3/20/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 3/20/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/20/2023 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 3/20/2023 Approved ENRIQUE MIRELES
Smoke Detectors 3/20/2023 Approved ENRIQUE MIRELES
Final 5/8/2023 Corrections Issued ENRIQUE MIRELES
Final 5/19/2023 OK to Issue CofO ENRIQUE MIRELES