9530 N RESEDA BLVD 1-118 91324

Certificate Information: 9530 N RESEDA BLVD 1-118 91324

Application / Permit
20010-10000-02929
Plan Check / Job No.
B20LA15643
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONSTRUCTION OF 4-STORY MIXED USE BUILDING OVER 2 LEVELS OF BASEMENT PARKING GARAGE; 118 UNITS APARTMENTS, GROUND FLOOR COMMERCIAL RESTAURANT SPACE, AMENITY COURTYARD WITH A POOL AND RECREATION ROOM FACILITIES. THE CONSTRUCTION IS TYPE I-A PODIUM AND GARAGE, AND TYPE V-A WOOD FRAMED UNITS ABOVE.
Permit Issued
Issued on 7/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 SAM CHANG
Building Plans Picked Up 9/28/2020 APPLICANT
Disabled Access Plans Picked Up 10/7/2020 APPLICANT
Corrections Issued 10/16/2020 SAM CHANG
Quality Review Completed 10/23/2020 TIEN JEN WANG
Applicant returned to address corrections 12/1/2020 SAM CHANG
Applicant returned to address corrections 1/6/2021 SAM CHANG
Applicant returned to address corrections 4/30/2021 SAM CHANG
Applicant returned to address corrections 8/20/2021 SAM CHANG
Applicant returned to address corrections 11/22/2021 SAM CHANG
Applicant returned to address corrections 11/30/2021 SAM CHANG
Applicant returned to address corrections 1/13/2022 SAM CHANG
Green Plans Picked Up 1/25/2022 APPLICANT
Applicant returned to address corrections 1/28/2022 SAM CHANG
Plan Check Approved 7/8/2022 SAM CHANG
Issued 7/18/2022 APPLICANT
TCO Issued (Expire Date: 03-08-2025) 9/9/2024 JEFFREY DURAN
CofO in Progress 3/10/2025 GREGORY POMISH
CofO Issued 3/10/2025 RICKEY JACKSON
Permit Finaled 3/10/2025 RICKEY JACKSON

Permit Application Clearance Information

"Q" conditions Cleared 10/28/2020 JASON CHAN
CPC Cleared 10/28/2020 JASON CHAN
Frnt yard landscape/Water mgmt Cleared 10/28/2020 JASON CHAN
Opn space landscape/Water mgmt Cleared 10/28/2020 JASON CHAN
Site Plan review Cleared 10/28/2020 JASON CHAN
Address approval Cleared 12/2/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/7/2020 LEE GUILBEAUX
Driveway location Cleared 12/8/2020 BRANDON WILSON
Highway dedication Cleared 12/8/2020 LEE GUILBEAUX
Internal circulation Cleared 12/8/2020 BRANDON WILSON
Miscellaneous Cleared 3/9/2021 JASON CHAN
Green Code Cleared 3/22/2021 AARON COSTA
Building over 36-ft Cleared 4/7/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/7/2021 CALOSHA APPROVED
Low Impact Development Cleared 6/11/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 6/16/2021 KURT CORRAL
Fire Marshal Fire Life Safety Cleared 6/17/2021 VIDAL GARCIA
DAS Clearance Cleared 6/24/2021 SHINE LIN
Roof/Waste drainage to street Cleared 4/7/2022 CARLOS AGUILERA
Sewer availability Cleared 5/20/2022 LEE GUILBEAUX
Trees in Parkway Cleared 6/1/2022 ADALBERTO VERA
Work Adjacent to Public Way Cleared 6/6/2022 LEE GUILBEAUX
Permit Cleared 6/7/2022 LEE GUILBEAUX
"D" conditions Cleared 6/15/2022 JASON CHAN
Demolition Cleared 6/15/2022 JASON CHAN
Miscellaneous Cleared 6/15/2022 JASON CHAN
"T" removal Cleared 7/6/2022 JASON CHAN

Contact Information

Architect Ha,, Simon Y; Lic. No.: C31188 7902 LOUISE LANE      LA PALMA, CA 90623
Contractor Wpic Construction Llc; Lic. No.: 1029691-B 125 W MAPLE AVE      MONROVIA, CA 91016
Engineer Blunda,, Abraham Matthew; Lic. No.: S6536 1845 W ORANGEWOOD AVE 200      ORANGE, CA 92868
Engineer Cunningham,, William Charbern; Lic. No.: C80129 2745 PARKVIEW DRIVE      THOUSAND OAKS, CA 91362
Geologist Feffer,, Joshua R; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049
Landscape Architect Carroll,, Stephen J.; Lic. No.: LA3977 529 BAUGHMAN AVE      CLAREMONT, CA 91711

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 8/15/2022 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 8/16/2022 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/22/2022 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/23/2022 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/26/2022 Partial Inspection JEFFREY FULTON
Pre-Inspection 9/26/2022 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 9/29/2022 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 9/30/2022 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 9/30/2022 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 10/3/2022 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 10/4/2022 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 10/4/2022 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 10/5/2022 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 10/5/2022 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 10/6/2022 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 10/7/2022 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 10/7/2022 Partial Inspection JEFFREY FULTON
Piling/Pier/Caisson 10/7/2022 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 10/14/2022 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 10/14/2022 Not Ready for Inspection JEFFREY FULTON
Piling/Pier/Caisson 10/14/2022 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 10/21/2022 Partial Inspection JEFFREY FULTON
Piling/Pier/Caisson 10/21/2022 Partial Inspection JEFFREY FULTON
Piling/Pier/Caisson 10/28/2022 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 11/4/2022 Not Ready for Inspection RICKEY JACKSON
Footing/Foundation/Slab 12/9/2022 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/19/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/20/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/21/2022 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 12/21/2022 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/22/2022 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/22/2022 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/23/2022 Conditional Approval JEFFREY FULTON
Special/Order Compliance 12/23/2022 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/27/2022 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/27/2022 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 12/27/2022 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/28/2022 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/29/2022 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 12/29/2022 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/30/2022 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/30/2022 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 1/3/2023 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 1/9/2023 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 1/9/2023 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 1/9/2023 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 1/9/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 1/9/2023 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 1/12/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 1/13/2023 Conditional Approval JEFFREY FULTON
Special/Order Compliance 1/13/2023 Partial Inspection JEFFREY FULTON
Wall Anchors 1/13/2023 Partial Inspection JOHN KITCKO
Deputy Shotcrete 1/19/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 1/19/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 1/20/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 1/20/2023 Not Ready for Inspection EDWIN GREGORYONA
Piling/Pier/Caisson 1/20/2023 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 1/20/2023 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 1/20/2023 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 1/23/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 1/23/2023 Not Ready for Inspection JEFFREY FULTON
Masonry Wall/Backfill 1/23/2023 Not Ready for Inspection JEFFREY FULTON
Pre-Inspection 1/23/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 1/23/2023 Approved BRIAN KELLY
Green Building Rough 1/24/2023 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 1/24/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 1/24/2023 Approved BRIAN KELLY
Verify Sprinkler Sign Off 1/24/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 1/25/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 1/25/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 1/25/2023 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 1/25/2023 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 1/25/2023 Partial Inspection JEFFREY FULTON
Special/Order Compliance 1/25/2023 Approved BRIAN KELLY
Deputy Shotcrete 1/26/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 1/26/2023 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 1/26/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 1/27/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 1/30/2023 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 1/30/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 1/31/2023 Conditional Approval JEFFREY FULTON
Reinforced Concrete Frame 1/31/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 2/1/2023 Conditional Approval JEFFREY FULTON
Green Building Rough 2/1/2023 Not Ready for Inspection JEFFREY FULTON
Masonry Wall/Backfill 2/1/2023 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 2/1/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 2/1/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 2/2/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 2/2/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 2/2/2023 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 2/2/2023 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 2/2/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 2/3/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 2/3/2023 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 2/6/2023 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 2/6/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 2/7/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 2/8/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 2/9/2023 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 2/9/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 2/10/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 2/10/2023 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 2/10/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 2/13/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 2/15/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 2/16/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 2/16/2023 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 2/23/2023 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 2/23/2023 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 2/23/2023 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 2/23/2023 Not Ready for Inspection STEVEN LEVITT
Verify Sprinkler Sign Off 2/23/2023 Not Ready for Inspection JEFFREY FULTON
Piling/Pier/Caisson 2/27/2023 No Access for Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 2/28/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 3/1/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 3/2/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 3/3/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 3/3/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 3/6/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 3/7/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 3/8/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 3/8/2023 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 3/8/2023 Not Ready for Inspection STEVEN LEVITT
Deputy Pre-Stress Concrete 3/9/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 3/9/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 3/10/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 3/13/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 3/13/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 3/14/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 3/15/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 3/15/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 3/16/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 3/16/2023 Conditional Approval JEFFREY FULTON
Green Building Rough 3/16/2023 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 3/16/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 3/16/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 3/17/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 3/17/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 3/20/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 3/20/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 3/21/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 3/22/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 3/23/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 3/23/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 3/24/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 3/24/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 3/24/2023 Conditional Approval JEFFREY FULTON
Reinforced Concrete Frame 3/24/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 3/28/2023 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/28/2023 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 3/29/2023 Conditional Approval JEFFREY FULTON
Final 3/29/2023 Not Ready for Inspection JEFFREY FULTON
Green Building Final 3/29/2023 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 3/29/2023 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 3/29/2023 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 3/29/2023 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 3/29/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 3/29/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 3/29/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 3/30/2023 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 3/30/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 3/31/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 3/31/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 3/31/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 3/31/2023 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 3/31/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 4/3/2023 Conditional Approval JEFFREY FULTON
Green Building Rough 4/3/2023 Not Ready for Inspection JEFFREY FULTON
Masonry Wall/Backfill 4/3/2023 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 4/3/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 4/3/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 4/4/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 4/4/2023 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 4/4/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 4/5/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 4/5/2023 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 4/5/2023 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 4/5/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 4/6/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 4/6/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 4/6/2023 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 4/6/2023 Partial Inspection JEFFREY FULTON
Reinforced Masonry Frame 4/6/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 4/7/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 4/7/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 4/7/2023 Partial Inspection JEFFREY FULTON
Insulation 4/11/2023 Not Ready for Inspection JEFFREY FULTON
Masonry Wall/Backfill 4/11/2023 Partial Inspection JEFFREY FULTON
Reinforced Masonry Frame 4/11/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 4/12/2023 Conditional Approval JEFFREY FULTON
Green Building Rough 4/12/2023 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 4/12/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 4/12/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 4/13/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 4/13/2023 Conditional Approval JEFFREY FULTON
Reinforced Masonry Frame 4/13/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 4/14/2023 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 4/14/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 4/17/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 4/17/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 4/17/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 4/17/2023 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 4/17/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 4/18/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 4/18/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 4/18/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 4/18/2023 Conditional Approval JEFFREY FULTON
Light Gage Steel Frame 4/18/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 4/19/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 4/19/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 4/19/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 4/20/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 4/20/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 4/20/2023 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 4/20/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 4/21/2023 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 4/21/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 4/26/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 4/27/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 4/28/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 5/1/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 5/2/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 5/3/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 5/4/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 5/4/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 5/5/2023 Conditional Approval DEANDRE HOFFMAN
Deputy Pre-Stress Concrete 5/9/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 5/10/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 5/11/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 5/11/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 5/12/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 5/12/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 5/15/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 5/16/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 5/17/2023 Conditional Approval JEFFREY FULTON
Reinforced Concrete Frame 5/17/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 5/18/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 5/19/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 5/22/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 5/23/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 5/24/2023 Conditional Approval JEFFREY FULTON
Reinforced Concrete Frame 5/24/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 5/25/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 5/26/2023 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 5/26/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 5/30/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 6/1/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 6/2/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 6/5/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 6/6/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 6/7/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 6/8/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 6/8/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 6/9/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 6/12/2023 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 6/12/2023 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 6/12/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 6/12/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 6/13/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 6/14/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 6/15/2023 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 6/15/2023 Partial Inspection JEFFREY FULTON
Deputy Pre-Stress Concrete 6/16/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 6/16/2023 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 6/20/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 6/21/2023 Not Ready for Inspection JEFFREY FULTON
Masonry Wall/Backfill 6/21/2023 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 6/22/2023 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 6/23/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 6/28/2023 Conditional Approval JEFFREY FULTON
Special/Order Compliance 6/28/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 6/29/2023 Conditional Approval JEFFREY FULTON
Special/Order Compliance 6/29/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 7/5/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 7/6/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 7/7/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 7/10/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 7/11/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 7/12/2023 Conditional Approval JEFFREY FULTON
Deputy Drilled-In Anchors 7/13/2023 Conditional Approval JEFFREY FULTON
Green Building Rough 7/18/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 7/18/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 7/18/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 7/19/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 7/20/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 7/20/2023 Partial Inspection JEFFREY FULTON
Wood Frame 7/20/2023 Corrections Issued JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 7/21/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 7/21/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 7/21/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 7/21/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 8/8/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/8/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/8/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 8/11/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/11/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/11/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/15/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 8/15/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 8/15/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/15/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/15/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 8/16/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/16/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/16/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/17/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 8/17/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 8/18/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 8/29/2023 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 8/29/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/29/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/29/2023 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 8/30/2023 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/30/2023 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/31/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 9/1/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 9/1/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 9/1/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 9/5/2023 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 9/8/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 9/8/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 9/8/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 9/21/2023 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 9/21/2023 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 9/21/2023 Not Ready for Inspection DANIEL VARNUM
Wood Frame 9/21/2023 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 9/29/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 9/29/2023 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/11/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 10/11/2023 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 10/11/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/11/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 10/11/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 10/17/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 10/17/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/17/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 10/17/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 10/23/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 10/23/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/23/2023 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Inspection JEFFREY FULTON
Insulation 10/24/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/25/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Partial Inspection JEFFREY FULTON
Wood Frame 10/26/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 10/27/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 10/27/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/27/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 10/27/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 10/30/2023 Partial Inspection JEFFREY FULTON
Insulation 10/31/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/2/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 11/2/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 11/2/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 11/2/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 11/2/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/3/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Partial Inspection JEFFREY FULTON
Insulation 11/3/2023 Corrections Issued JEFFREY FULTON
Drywall Nailing 11/9/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 11/9/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Inspection JEFFREY FULTON
Insulation 11/14/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/15/2023 Partial Inspection JEFFREY FULTON
Insulation 11/15/2023 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 11/16/2023 Conditional Approval JEFFREY FULTON
Drywall Nailing 11/21/2023 Partial Approval JOHN KITCKO
Insulation 11/21/2023 Partial Approval JOHN KITCKO
Insulation 11/27/2023 Partial Inspection JEFFREY FULTON
Wood Frame 11/27/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 11/28/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 11/28/2023 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 11/28/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 11/28/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 11/28/2023 Partial Inspection JEFFREY FULTON
Insulation 11/29/2023 Partial Inspection JEFFREY FULTON
Wood Frame 11/29/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/30/2023 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Partial Inspection JEFFREY FULTON
Wood Frame 11/30/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/4/2023 Partial Inspection JEFFREY FULTON
Insulation 12/4/2023 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 12/5/2023 Conditional Approval JEFFREY FULTON
Drywall Nailing 12/5/2023 Partial Inspection JEFFREY FULTON
Wood Frame 12/5/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/6/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 12/6/2023 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/6/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/6/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/7/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Partial Inspection JEFFREY FULTON
Insulation 12/7/2023 Corrections Issued JEFFREY FULTON
Drywall Nailing 12/11/2023 Partial Inspection JEFFREY FULTON
Insulation 12/11/2023 Partial Inspection JEFFREY FULTON
Wood Frame 12/11/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/12/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 12/12/2023 Partial Inspection JEFFREY FULTON
Insulation 12/12/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/12/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/12/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Wood Construction 12/13/2023 Conditional Approval JEFFREY FULTON
Drywall Nailing 12/13/2023 Partial Inspection JEFFREY FULTON
Insulation 12/13/2023 Partial Inspection JEFFREY FULTON
Wood Frame 12/13/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/18/2023 Partial Inspection JEFFREY FULTON
Insulation 12/18/2023 Partial Inspection JEFFREY FULTON
Wood Frame 12/18/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 12/19/2023 Partial Inspection JEFFREY FULTON
Insulation 12/19/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/20/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Partial Inspection JEFFREY FULTON
Insulation 12/21/2023 Partial Inspection JEFFREY FULTON
Wood Frame 12/21/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/26/2023 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 12/26/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/27/2023 Partial Inspection JEFFREY FULTON
Insulation 12/27/2023 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 12/27/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/28/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 12/28/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 12/28/2023 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/28/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/28/2023 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/29/2023 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 12/29/2023 Partial Inspection JEFFREY FULTON
Wood Frame 12/29/2023 Partial Inspection JEFFREY FULTON
Green Building Rough 1/2/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 1/2/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 1/2/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 1/2/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/3/2024 Partial Inspection JEFFREY FULTON
Insulation 1/3/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 1/3/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/4/2024 Partial Inspection JEFFREY FULTON
Insulation 1/4/2024 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 1/4/2024 Partial Inspection JEFFREY FULTON
Wood Frame 1/4/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/5/2024 Partial Inspection JEFFREY FULTON
Wood Frame 1/5/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/8/2024 Corrections Issued JEFFREY FULTON
Drywall Nailing 1/8/2024 Partial Inspection MELVIN GIRTON
Green Building Rough 1/8/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 1/8/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 1/9/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/9/2024 Partial Inspection MELVIN GIRTON
Drywall Nailing 1/10/2024 Partial Inspection JEFFREY FULTON
Insulation 1/10/2024 Partial Inspection JEFFREY FULTON
Wood Frame 1/10/2024 Partial Inspection JEFFREY FULTON
Insulation 1/11/2024 Partial Inspection JEFFREY FULTON
Special/Order Compliance 1/11/2024 Partial Inspection MELVIN GIRTON
Wood Frame 1/11/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/12/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 1/12/2024 Partial Inspection JEFFREY FULTON
Insulation 1/16/2024 Partial Inspection JEFFREY FULTON
Special/Order Compliance 1/16/2024 Partial Inspection MELVIN GIRTON
Wood Frame 1/16/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/17/2024 Partial Inspection JEFFREY FULTON
Insulation 1/17/2024 Partial Inspection JEFFREY FULTON
Special/Order Compliance 1/17/2024 Partial Inspection MELVIN GIRTON
Wood Frame 1/17/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/18/2024 Partial Inspection JEFFREY FULTON
Wood Frame 1/18/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/19/2024 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 1/19/2024 Partial Inspection JEFFREY FULTON
Insulation 1/19/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 1/19/2024 Corrections Issued JEFFREY FULTON
Special/Order Compliance 1/19/2024 Partial Inspection MELVIN GIRTON
Verify Sprinkler Sign Off 1/19/2024 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 1/22/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 1/23/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 1/23/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 1/23/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 1/23/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/24/2024 Partial Inspection JEFFREY FULTON
Insulation 1/24/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/25/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 1/25/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 1/26/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 1/26/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 1/26/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 1/26/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 1/26/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/29/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 1/29/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/30/2024 Partial Inspection JEFFREY FULTON
Wood Frame 1/30/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/31/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 1/31/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 1/31/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 1/31/2024 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 2/1/2024 Partial Inspection JEFFREY FULTON
Wood Frame 2/1/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/2/2024 Partial Inspection JEFFREY FULTON
Insulation 2/2/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/6/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 2/6/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 2/6/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 2/6/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 2/6/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/7/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 2/8/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 2/8/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 2/8/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 2/8/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 2/8/2024 Partial Inspection JEFFREY FULTON
Insulation 2/9/2024 Partial Inspection JEFFREY FULTON
Wood Frame 2/9/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/12/2024 Partial Inspection JEFFREY FULTON
Insulation 2/12/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 2/12/2024 Partial Inspection JEFFREY FULTON
Wood Frame 2/12/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 2/13/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 2/13/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 2/13/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 2/13/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/14/2024 Partial Inspection JEFFREY FULTON
Insulation 2/14/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/15/2024 Partial Inspection JEFFREY FULTON
Insulation 2/16/2024 Partial Inspection JEFFREY FULTON
Wood Frame 2/16/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 2/20/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/21/2024 Corrections Issued JEFFREY FULTON
Insulation 2/21/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 2/22/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 2/22/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 2/22/2024 Partial Inspection JEFFREY FULTON
Wood Frame 2/22/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/23/2024 Partial Inspection JEFFREY FULTON
Insulation 2/23/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 2/27/2024 Partial Approval JOHN KITCKO
Drywall Nailing 2/28/2024 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 2/29/2024 Partial Approval GREGORY POMISH
Drywall Nailing 3/1/2024 Partial Approval GREGORY POMISH
Green Building Rough 3/4/2024 Partial Inspection GREGORY POMISH
Insulation 3/4/2024 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 3/4/2024 Partial Inspection GREGORY POMISH
Wood Frame 3/4/2024 Partial Inspection GREGORY POMISH
Insulation 3/5/2024 Partial Approval GREGORY POMISH
Green Building Rough 3/6/2024 Partial Inspection GREGORY POMISH
Insulation 3/6/2024 Partial Inspection GREGORY POMISH
Interior/Exterior Lathing 3/6/2024 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 3/6/2024 Partial Inspection GREGORY POMISH
Drywall Nailing 3/8/2024 Partial Approval GREGORY POMISH
Drywall Nailing 3/12/2024 Partial Approval GREGORY POMISH
Drywall Nailing 3/15/2024 Partial Approval GREGORY POMISH
Wood Frame 3/19/2024 Partial Approval GREGORY POMISH
Green Building Rough 4/22/2024 Approved GREGORY POMISH
Interior/Exterior Lathing 4/22/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 4/22/2024 Partial Inspection GREGORY POMISH
Wood Frame 4/22/2024 Partial Approval GREGORY POMISH
Deputy Drilled-In Anchors 4/23/2024 Conditional Approval GREGORY POMISH
Drywall Nailing 4/23/2024 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Partial Inspection GREGORY POMISH
Deputy Drilled-In Anchors 4/24/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 4/26/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 4/26/2024 Not Ready for Inspection GREGORY POMISH
Light Gage Steel Frame 4/26/2024 Not Ready for Inspection GREGORY POMISH
Masonry Wall/Backfill 4/26/2024 Not Ready for Inspection GREGORY POMISH
Drywall Nailing 5/7/2024 Partial Approval ROBERT DAVIS
Special/Order Compliance 7/1/2024 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 7/10/2024 Partial Inspection GREGORY POMISH
Special/Order Compliance 7/17/2024 Partial Inspection GREGORY POMISH
Special/Order Compliance 7/23/2024 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 7/24/2024 Partial Inspection GREGORY POMISH
Final 8/8/2024 Corrections Issued GREGORY POMISH
Footing/Foundation/Slab 8/8/2024 Partial Inspection GREGORY POMISH
Green Building Final 8/8/2024 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 8/8/2024 Partial Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 8/8/2024 SGSOV Approved GREGORY POMISH
Smoke Detectors 8/8/2024 Approved GREGORY POMISH
Verify Sprinkler Sign Off 8/8/2024 Not Ready for Inspection GREGORY POMISH
Wood Frame 8/8/2024 Partial Inspection GREGORY POMISH
Pre-Inspection 8/15/2024 Partial Inspection GREGORY POMISH
Pre-Inspection 8/16/2024 Partial Inspection GREGORY POMISH
Pre-Inspection 8/19/2024 Partial Inspection GREGORY POMISH
Pre-Inspection 8/21/2024 Corrections Issued GREGORY POMISH
Final 9/7/2024 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 9/7/2024 Approved GREGORY POMISH
Green Building Final 9/7/2024 Approved GREGORY POMISH
Reinforced Concrete Frame 9/7/2024 Approved GREGORY POMISH
Verify Sprinkler Sign Off 9/7/2024 Approved GREGORY POMISH
Wood Frame 9/7/2024 Approved GREGORY POMISH
Special/Order Compliance 2/11/2025 Partial Inspection GREGORY POMISH
Final 3/10/2025 OK to Issue CofO GREGORY POMISH