772 N SARBONNE ROAD 90077

Certificate Information: 772 N SARBONNE ROAD 90077

Application / Permit
20010-10000-02920
Plan Check / Job No.
B20LA15576
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 2 CAR CARPORT. 1 OF 4
Permit Issued
Issued on 4/28/2022
Issuing Office
Current Status
Issued on 4/28/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/27/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 MICHAEL LOPEZ
Corrections Issued 9/10/2020 MICHAEL LOPEZ
Quality Review Completed 10/15/2020 PRANITA SHAH
Applicant returned to address corrections 5/4/2021 MICHAEL LOPEZ
Applicant returned to address corrections 7/29/2021 MICHAEL LOPEZ
Applicant returned to address corrections 8/5/2021 MICHAEL LOPEZ
Applicant returned to address corrections 8/31/2021 MICHAEL LOPEZ
Applicant returned to address corrections 9/20/2021 MICHAEL LOPEZ
Applicant returned to address corrections 9/22/2021 MICHAEL LOPEZ
Applicant returned to address corrections 11/5/2021 MICHAEL LOPEZ
Applicant returned to address corrections 11/29/2021 MICHAEL LOPEZ
Applicant returned to address corrections 1/6/2022 MICHAEL LOPEZ
Applicant returned to address corrections 1/12/2022 MICHAEL LOPEZ
Applicant returned to address corrections 2/10/2022 MICHAEL LOPEZ
Plan Check Approved 3/22/2022 MICHAEL LOPEZ
Issued 4/28/2022 APPLICANT
Building Plans Picked Up 5/2/2022 APPLICANT

Permit Application Clearance Information

ZI Cleared 1/19/2021 DENZEL HENDERSON
BHO/Hillside ordinance Cleared 2/10/2021 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 2/10/2021 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 2/10/2021 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 2/10/2021 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 2/10/2021 ANTHONY MAINEZ
Permit Cleared 2/10/2021 ANTHONY MAINEZ
Sewer availability Cleared 2/10/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 2/17/2021 ANTHONY MAINEZ
Hydrant and Access approval Cleared 2/23/2021 KURT CORRAL
Landscape for retaining wall Cleared 7/26/2021 MIGUEL GAMBOA
Trees in Parkway Cleared 7/28/2021 JOHN KIM
GPI Written Notices Cleared 8/5/2021 BRIAN OLSON
Grading Pre-Inspection Cleared 8/5/2021 BRIAN OLSON
Excavation more than 5-ft deep Cleared 8/11/2021 CALOSHA APPROVED
Low Impact Development Cleared 10/8/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/14/2021 DINAH GARIN
Work Adjacent to Public Way Cleared 10/25/2021 SAUL GARCIA

Contact Information

Architect , ; Lic. No.: C36197       ,
Contractor Dugally Oberfeld Inc; Lic. No.: 862641-B 484 S SAN VICENTE BLVD      LOS ANGELES, CA 90048
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Geologist Feffer,, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/18/2022 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 7/18/2022 Partial Approval CHRISTOPHER WILSON
Deputy Grading 8/10/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Grading 8/11/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Grading 8/12/2022 No Access for Inspection KENNETH NAGLE
Deputy Grading 8/16/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Grading 8/17/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Grading 8/18/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Grading 8/19/2022 Conditional Approval MICHAEL PELHAM
Piling/Pier/Caisson 9/9/2022 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/13/2022 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 9/13/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/18/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Reinforced Concrete Frame 10/20/2022 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 10/24/2022 Corrections Issued CHRISTOPHER WILSON
Reinforced Concrete Frame 10/25/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/3/2022 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 11/15/2022 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 1/23/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/8/2023 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 2/8/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/10/2023 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 2/10/2023 Partial Approval CARLOS MATAMOROS
Grading Pre-Inspection 3/6/2023 Not Ready for Inspection CHRISTOPHER WILSON
Masonry Wall/Backfill 3/6/2023 Not Ready for Inspection CHRISTOPHER WILSON
Piling/Pier/Caisson 3/9/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 4/17/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 4/20/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 5/16/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 6/6/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 6/14/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 6/15/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 6/22/2023 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 6/26/2023 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 7/20/2023 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/26/2023 Partial Approval MICHAEL PELHAM
Reinforced Concrete Frame 8/10/2023 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/17/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 8/29/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 9/12/2023 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 9/13/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 11/3/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 1/10/2024 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 1/17/2024 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 2/23/2024 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 3/20/2024 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 4/18/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/30/2024 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 5/7/2024 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 5/7/2024 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 5/10/2024 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 6/4/2024 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 6/12/2024 Corrections Issued CHRISTOPHER WILSON
Reinforced Concrete Frame 6/12/2024 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Grading 6/18/2024 Conditional Approval MATTHEW JENKINS
Deputy Grading 6/20/2024 Conditional Approval MATTHEW JENKINS
Deputy Grading 6/21/2024 Conditional Approval MATTHEW JENKINS
Deputy Grading 6/24/2024 Conditional Approval MATTHEW JENKINS
Deputy Grading 6/25/2024 Conditional Approval MICHAEL PELHAM
Deputy Grading 6/26/2024 Conditional Approval MICHAEL PELHAM
Deputy Grading 6/27/2024 Conditional Approval MICHAEL PELHAM
Deputy Grading 6/28/2024 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 7/16/2024 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/22/2024 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 7/22/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/29/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/17/2024 Not Ready for Inspection CHRISTOPHER WILSON
Piling/Pier/Caisson 9/19/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/25/2024 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 10/3/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/8/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/17/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/23/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/31/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/16/2025 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 1/27/2025 Partial Approval CHRISTOPHER WILSON
Masonry Wall/Backfill 2/19/2025 Partial Approval CHRISTOPHER WILSON
Masonry Wall/Backfill 2/27/2025 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 2/28/2025 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 3/19/2025 Approved CHRISTOPHER WILSON
HVAC-Rough 3/19/2025 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 3/26/2025 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/16/2025 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/8/2025 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 5/30/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 6/6/2025 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/16/2025 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 6/27/2025 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/30/2025 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/2/2025 Partial Approval CHRISTOPHER WILSON
Gas Test 7/10/2025 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 7/10/2025 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/11/2025 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/11/2025 Partial Approval CHRISTOPHER WILSON
Gas Test 7/15/2025 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/21/2025 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/29/2025 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 8/7/2025 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/7/2025 Approved CHRISTOPHER WILSON
Insulation 8/29/2025 Partial Approval CHRISTOPHER WILSON
Wood Frame 9/3/2025 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 Partial Approval CHRISTOPHER WILSON
Wood Frame 10/8/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 10/16/2025 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 11/6/2025 Partial Approval CARLOS MATAMOROS
Insulation 11/6/2025 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 11/10/2025 Partial Approval SEAN HAUPT
HVAC-Rough 11/10/2025 Partial Approval SEAN HAUPT
PLUMBING-Rough 11/10/2025 Partial Approval SEAN HAUPT
Light Gage Steel Frame 11/14/2025 Partial Approval SEAN HAUPT
BUILDING-Rough-Frame 1/7/2026 Conditional Approval CARLOS MATAMOROS
ELECTRICAL-Rough 1/7/2026 Approved CARLOS MATAMOROS
Green Building Rough 1/7/2026 Approved CARLOS MATAMOROS
HVAC-Rough 1/7/2026 Approved CARLOS MATAMOROS
PLUMBING-Rough 1/7/2026 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 1/14/2026 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 1/14/2026 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 2/25/2026 Not Ready for Inspection CHRISTOPHER WILSON
Insulation 3/11/2026 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 3/17/2026 Partial Approval CHRISTOPHER WILSON
Shower Pan 3/17/2026 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 3/25/2026 Partial Approval CHRISTOPHER WILSON
Shower Pan 3/25/2026 Approved CHRISTOPHER WILSON
Insulation 4/2/2026 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 5/1/2026 Partial Approval CHRISTOPHER WILSON
Insulation 5/15/2026 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 5/15/2026 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 5/21/2026 Partial Approval RYAN SALAZAR
Underground Mechanical 5/29/2026 Partial Approval RYAN SALAZAR