1530 N ECHO PARK AVE 90026

Certificate Information: 1530 N ECHO PARK AVE 90026

Application / Permit
20010-10000-02909
Plan Check / Job No.
B20LA15526
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY RESIDENCE IN FRONT OF PROPERTY.
Permit Issued
Issued on 6/16/2021
Issuing Office
Current Status
CofO Issued on 4/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 MAHNAZ NOURHASHEMI
Corrections Issued 10/6/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 10/15/2020 TIEN JEN WANG
Building Plans Picked Up 10/19/2020 APPLICANT
Applicant returned to address corrections 3/2/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 3/18/2021 MAHNAZ NOURHASHEMI
Issued 6/16/2021 APPLICANT
CofO in Progress 4/19/2023 ALIZAH MAYAGOITIA
Permit Finaled 4/23/2023 DEROLD HAUFF
CofO Issued 4/23/2023 DEROLD HAUFF
Permit Finaled 4/23/2023 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 11/9/2020 RICHARD REASER
Hydrant and Access approval Cleared 2/10/2021 ROBERT DUFF
Low Impact Development Cleared 2/11/2021 MARTIN FRAGOSO
Address approval Cleared 2/22/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 2/22/2021 RENZ SORIANO
Permit Cleared 2/22/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 2/22/2021 RENZ SORIANO
Sewer availability Cleared 2/22/2021 RENZ SORIANO
GPI Written Notices Cleared 3/16/2021 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 3/16/2021 MAHNAZ NOURHASHEMI

Contact Information

Contractor Owner-Builder       ,
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/1/2021 Approved HAMIK HARTOUNIAN
Deputy Grading 7/6/2021 Partial Approval RUBEN SALAS
Piling/Pier/Caisson 7/8/2021 Approved SCOTT FINNILA
Deputy Reinf. Concrete 7/9/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 7/15/2021 Approved THOMAS LOGRASSO
Special/Order Compliance 7/15/2021 Approved RUBEN SALAS
PLUMBING-Rough 7/20/2021 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 7/23/2021 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 8/11/2021 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/12/2021 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Partial Approval THOMAS LOGRASSO
Green Building Rough 8/18/2021 Not Ready for Inspection THOMAS LOGRASSO
Verify Sprinkler Sign Off 8/18/2021 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Corrections Issued THOMAS LOGRASSO
Insulation 10/15/2021 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 12/21/2021 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 12/22/2021 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 12/22/2021 Approved THOMAS LOGRASSO
Green Building Rough 12/22/2021 Approved THOMAS LOGRASSO
HVAC-Rough 12/22/2021 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 12/22/2021 Approved THOMAS LOGRASSO
Verify Sprinkler Sign Off 12/22/2021 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 1/6/2022 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 1/12/2022 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 1/12/2022 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 3/4/2022 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 3/4/2022 Approved THOMAS LOGRASSO
Insulation 3/4/2022 Conditional Approval THOMAS LOGRASSO
Drywall Nailing 3/11/2022 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 7/1/2022 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 2/27/2023 Approved THOMAS LOGRASSO
Drywall Nailing 2/27/2023 Approved THOMAS LOGRASSO
Final 2/27/2023 Corrections Issued THOMAS LOGRASSO
Green Building Final 2/27/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Not Required THOMAS LOGRASSO
Service/Power Release 2/27/2023 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 2/27/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 4/12/2023 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 4/12/2023 Approved THOMAS LOGRASSO
Service/Power Release 4/12/2023 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 4/12/2023 Approved THOMAS LOGRASSO
ELECTRICAL-Final 4/18/2023 Approved ALIZAH MAYAGOITIA
Final 4/18/2023 OK to Issue CofO ALIZAH MAYAGOITIA
HVAC-Final 4/18/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 4/18/2023 Approved ALIZAH MAYAGOITIA
Service/Power Release 4/18/2023 Approved ALIZAH MAYAGOITIA