1530 N ECHO PARK AVE 90026
Certificate Information: 1530 N ECHO PARK AVE 90026
- Application / Permit
- 20010-10000-02909
- Plan Check / Job No.
- B20LA15526
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY RESIDENCE IN FRONT OF PROPERTY.
- Permit Issued
- Issued on 6/16/2021
- Issuing Office
- Current Status
- CofO Issued on 4/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/6/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/15/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 10/19/2020 | APPLICANT |
| Applicant returned to address corrections | 3/2/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 3/18/2021 | MAHNAZ NOURHASHEMI |
| Issued | 6/16/2021 | APPLICANT |
| CofO in Progress | 4/19/2023 | ALIZAH MAYAGOITIA |
| Permit Finaled | 4/23/2023 | DEROLD HAUFF |
| CofO Issued | 4/23/2023 | DEROLD HAUFF |
| Permit Finaled | 4/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 11/9/2020 | RICHARD REASER |
| Hydrant and Access approval | Cleared | 2/10/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 2/11/2021 | MARTIN FRAGOSO |
| Address approval | Cleared | 2/22/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | RENZ SORIANO |
| Permit | Cleared | 2/22/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 2/22/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 2/22/2021 | RENZ SORIANO |
| GPI Written Notices | Cleared | 3/16/2021 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 3/16/2021 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/1/2021 | Approved | HAMIK HARTOUNIAN |
| Deputy Grading | 7/6/2021 | Partial Approval | RUBEN SALAS |
| Piling/Pier/Caisson | 7/8/2021 | Approved | SCOTT FINNILA |
| Deputy Reinf. Concrete | 7/9/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 7/15/2021 | Approved | THOMAS LOGRASSO |
| Special/Order Compliance | 7/15/2021 | Approved | RUBEN SALAS |
| PLUMBING-Rough | 7/20/2021 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 7/23/2021 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/11/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2021 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2021 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 8/18/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 8/18/2021 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 10/15/2021 | Partial Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 12/21/2021 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/22/2021 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 12/22/2021 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 12/22/2021 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 12/22/2021 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/22/2021 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 12/22/2021 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/6/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/12/2022 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/12/2022 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/4/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 3/4/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 3/4/2022 | Conditional Approval | THOMAS LOGRASSO |
| Drywall Nailing | 3/11/2022 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 7/1/2022 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/27/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 2/27/2023 | Approved | THOMAS LOGRASSO |
| Final | 2/27/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 2/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 2/27/2023 | SGSOV Not Required | THOMAS LOGRASSO |
| Service/Power Release | 2/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 2/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 4/12/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 4/12/2023 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 4/12/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 4/12/2023 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/18/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/18/2023 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/18/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 4/18/2023 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 4/18/2023 | Approved | ALIZAH MAYAGOITIA |