2122-2122 1/2 S 3RD AVE 90008
Certificate Information: 2122-2122 1/2 S 3RD AVE 90008
- Application / Permit
- 20010-10000-02897
- Plan Check / Job No.
- B20LA15442
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX 1 OF 2
- Permit Issued
- Issued on 9/16/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 8/23/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 8/25/2021 | KEN GILL |
| Building Plans Picked Up | 8/29/2022 | APPLICANT |
| Plan Check Approved | 9/16/2022 | CRYSTEL MAALOUF |
| Issued | 9/16/2022 | APPLICANT |
| CofO in Progress | 11/14/2023 | STUART CHAPMAN |
| Permit Finaled | 12/29/2023 | DEROLD HAUFF |
| CofO Issued | 12/29/2023 | DEROLD HAUFF |
| Permit Finaled | 12/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/30/2021 | JEANIE LAM |
| Address approval | Cleared | 1/4/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2022 | PAMELA TENEZA |
| Hydrant and Access approval | Cleared | 1/21/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 3/19/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/25/2022 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 8/24/2022 | KYLE WINSTON |
| Frnt yard landscape/Water mgmt | Cleared | 8/29/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 8/29/2022 | RUBEN VASQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/5/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 12/27/2022 | Partial Approval | CALEB MEISTER |
| Insulation | 12/30/2022 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Partial Approval | CALEB MEISTER |
| Deputy Wood Construction | 3/8/2023 | Conditional Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Rough | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Verify Sprinkler Sign Off | 5/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 5/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 5/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 5/23/2023 | Approved | CALEB MEISTER |
| METHANE-Rough | 5/23/2023 | Approved | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 5/23/2023 | Approved | CALEB MEISTER |
| Shower Pan | 5/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| Verify Sprinkler Sign Off | 5/23/2023 | Approved | CALEB MEISTER |
| Insulation | 5/31/2023 | Corrections Issued | CALEB MEISTER |
| Interior/Exterior Lathing | 5/31/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 6/7/2023 | Approved | CALEB MEISTER |
| Underground Mechanical | 6/28/2023 | Partial Approval | CALEB MEISTER |
| Service/Power Release | 9/27/2023 | No Access for Inspection | CALEB MEISTER |
| Service/Power Release | 10/2/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/7/2023 | Approved | CALEB MEISTER |
| Final | 11/7/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/7/2023 | Approved | CALEB MEISTER |
| Green Building Final | 11/7/2023 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/7/2023 | Approved | CALEB MEISTER |
| MERV13>=Final | 11/7/2023 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 11/7/2023 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 11/7/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 11/7/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 11/13/2023 | Approved | STUART CHAPMAN |
| Final | 11/13/2023 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 11/13/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 11/13/2023 | Approved | STUART CHAPMAN |
| Service/Power Release | 11/13/2023 | Approved | STUART CHAPMAN |