240 N MADISON AVE 90004

Certificate Information: 240 N MADISON AVE 90004

Application / Permit
20010-10000-02872
Plan Check / Job No.
B20LA07162
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
TRASH ENCLOSURE FOR CHARTER SCHOOL
Permit Issued
Issued on 3/17/2021
Issuing Office
Current Status
CofO Issued on 4/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2020 APPLICANT
Assigned to Plan Check Engineer 5/28/2020 YOUNG KIM
Corrections Issued 6/9/2020 YOUNG KIM
Quality Review Completed 6/26/2020 ALLEN MANALANSAN
Building Plans Picked Up 7/2/2020 APPLICANT
Applicant returned to address corrections 8/24/2020 YOUNG KIM
Applicant returned to address corrections 8/29/2020 YOUNG KIM
Applicant returned to address corrections 9/10/2020 YOUNG KIM
Applicant returned to address corrections 11/4/2020 YOUNG KIM
Applicant returned to address corrections 11/10/2020 YOUNG KIM
Green Plans Picked Up 12/11/2020 APPLICANT
Applicant returned to address corrections 2/3/2021 YOUNG KIM
Applicant returned to address corrections 2/5/2021 YOUNG KIM
Plan Check Approved 3/5/2021 YOUNG KIM
Issued 3/17/2021 APPLICANT
CofO in Progress 4/19/2022 DAVID BURKHEAD
CofO Issued 4/19/2022 ERNESTO CORRAL
Permit Finaled 4/19/2022 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 10/14/2020 YOUNG KIM
CPC Cleared 1/13/2021 KENTON TRINH
Specific Plan Cleared 1/13/2021 KENTON TRINH
Redevelopment Project Area Cleared 1/15/2021 DAVID URITA

Contact Information

Architect Csda, Design Group; Lic. No.: C35165 889 N. DOUGLAS STREET   SUITE 100    EL SEGUNDO, CA 90245
Contractor Consolidated Contracting Services Inc; Lic. No.: 475813-B 181 AVENIDA LA PATA   SUITE 200    SAN CLEMENTE, CA 92673
Engineer Masulis,, Derrick; Lic. No.: S6228 401 S MERIDIAN AVE      ALHAMBRA, CA 91801

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/9/2021 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 7/9/2021 Not Ready for Inspection DAVID BURKHEAD
METHANE-Barrier 7/9/2021 Approved DAVID BURKHEAD
METHANE-Rough 7/9/2021 Approved DAVID BURKHEAD
METHANE-Subgrade 7/9/2021 Approved DAVID BURKHEAD
Structural Steel Frame 7/9/2021 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 7/9/2021 Approved DAVID BURKHEAD
Masonry Wall/Backfill 10/22/2021 Partial Approval DANIEL COLLINS
Masonry Wall/Backfill 12/2/2021 Partial Approval DAVID BURKHEAD
Drywall Nailing 4/5/2022 Approved DAVID BURKHEAD
Final 4/5/2022 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 4/5/2022 Approved DAVID BURKHEAD
Green Building Final 4/5/2022 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 4/5/2022 Approved DAVID BURKHEAD
Reinforced Masonry Frame 4/5/2022 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 4/5/2022 SGSOV No Gas DAVID BURKHEAD
Smoke Detectors 4/5/2022 Approved DAVID BURKHEAD
Structural Steel Frame 4/5/2022 Approved DAVID BURKHEAD
Wood Frame 4/5/2022 Approved DAVID BURKHEAD
Final 4/18/2022 OK to Issue CofO DAVID BURKHEAD
Green Building Final 4/18/2022 Approved DAVID BURKHEAD