5024 E BALTIMORE ST 90042
Certificate Information: 5024 E BALTIMORE ST 90042
- Application / Permit
- 20010-10000-02856
- Plan Check / Job No.
- B20LA15152
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1 STORY DETACHED ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 6/2/2021
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 10/6/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 10/28/2020 | WING SUEN |
| Building Plans Picked Up | 11/4/2020 | APPLICANT |
| Applicant returned to address corrections | 4/23/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 5/14/2021 | CRYSTEL MAALOUF |
| Issued | 6/2/2021 | APPLICANT |
| CofO in Progress | 12/16/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 12/24/2022 | DEROLD HAUFF |
| CofO Issued | 12/24/2022 | DEROLD HAUFF |
| Permit Finaled | 12/24/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/4/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/4/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/4/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/4/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/4/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2020 | CELINA MORENO |
| Sewer availability | Cleared | 12/7/2020 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 1/28/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 5/12/2021 | ANDRES COVARRUBIAS |
| Grading Pre-Inspection | Cleared | 5/14/2021 | CRYSTEL MAALOUF |
| Roof/Waste drainage to street | Cleared | 5/14/2021 | ROSA SILVA |
Contact Information
| Contractor | Advanced General Construction; Lic. No.: 951083-B | 6545 HAZELTINE AVE # 212 VAN NUYS, CA 91401 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/8/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/10/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/12/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/20/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/23/2021 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/4/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 8/17/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 8/20/2021 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 8/20/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 8/24/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 9/20/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 9/20/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/1/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 10/1/2021 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/1/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/6/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/6/2021 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 10/6/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/13/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 10/13/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/13/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/20/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 10/20/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/25/2021 | No Access for Inspection | ADAM ESCOTO |
| HVAC-Rough | 10/25/2021 | No Access for Inspection | ADAM ESCOTO |
| HVAC-Rough | 10/26/2021 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 10/26/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/27/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 11/3/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 11/10/2021 | Approved | MASHEL JONGERT |
| Shower Pan | 11/10/2021 | Approved | MASHEL JONGERT |
| Interior/Exterior Lathing | 11/17/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 3/22/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Final | 3/22/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 3/22/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 3/22/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 3/22/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 3/22/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/22/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 5/4/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 5/4/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 5/4/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 5/4/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 5/4/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/4/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 5/4/2022 | Not Required | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/4/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 7/25/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 7/25/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 7/25/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 9/12/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Final | 9/12/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Pre-Inspection | 11/2/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 12/16/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |