520-522 E 21ST ST 90011
Certificate Information: 520-522 E 21ST ST 90011
- Application / Permit
- 20010-10000-02851
- Plan Check / Job No.
- B20LA15100
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE BUILDING FACING 21ST STREET
- Permit Issued
- Issued on 1/11/2021
- Issuing Office
- Current Status
- CofO Issued on 8/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 9/23/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/1/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 10/7/2020 | APPLICANT |
| Plan Check Approved | 12/4/2020 | MAHNAZ NOURHASHEMI |
| Issued | 1/11/2021 | APPLICANT |
| CofO in Progress | 7/27/2021 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 8/5/2021 | DEROLD HAUFF |
| CofO Issued | 8/5/2021 | DEROLD HAUFF |
| Permit Finaled | 8/5/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/13/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 10/14/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 10/16/2020 | CECILIO NAVARRO |
| Frnt yard landscape/Water mgmt | Cleared | 11/18/2020 | TERRI OSBORNE |
| Low Impact Development | Cleared | 11/25/2020 | JORGE MEJIA LEMUS |
| Permit | Cleared | 11/25/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 11/30/2020 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/8/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/10/2021 | Approved | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 2/12/2021 | No Access for Inspection | ELMER BLAND |
| PLUMBING-Rough | 2/19/2021 | Partial Approval | ROBERT MCDOWELL |
| Wood Frame | 2/19/2021 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Partial Approval | ROBERT MCDOWELL |
| Insulation | 2/22/2021 | Partial Approval | ROBERT MCDOWELL |
| PLUMBING-Rough | 2/22/2021 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2021 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 4/7/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 4/7/2021 | Approved | ROBERT MCDOWELL |
| Rough-Elec/Plmb/HVAC | 4/7/2021 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 4/7/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 4/9/2021 | Approved | ROBERT MCDOWELL |
| Special/Order Compliance | 4/9/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 4/28/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/28/2021 | Approved | OSVALDO PARAMO |
| Final | 7/22/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/26/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/26/2021 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Gas Test | 7/26/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/26/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/26/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/26/2021 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/26/2021 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/26/2021 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/26/2021 | Approved | ALEJANDRO DE ARTOLA |