8315 S MCCONNELL AVE 90045

Certificate Information: 8315 S MCCONNELL AVE 90045

Application / Permit
20010-10000-02837
Plan Check / Job No.
B20LA15018
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING WTIH ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 2/11/2021
Issuing Office
Current Status
CofO Issued on 7/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 DANIEL YIP
Corrections Issued 9/21/2020 DANIEL YIP
Quality Review Completed 10/8/2020 ALLEN MANALANSAN
Building Plans Picked Up 10/19/2020 APPLICANT
Applicant returned to address corrections 2/10/2021 DANIEL YIP
Plan Check Approved 2/11/2021 DANIEL YIP
Issued 2/11/2021 APPLICANT
CofO in Progress 7/21/2022 EVAN COOPER
Permit Finaled 7/27/2022 DANIEL ORRANTE
CofO Issued 7/27/2022 DANIEL ORRANTE
Permit Finaled 7/27/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/20/2020 DINAH GARIN
Specific Plan Cleared 12/7/2020 FREDDY GARCIA
Hydrant and Access approval Cleared 12/14/2020 MATTHEW CRAIG
Low Impact Development Cleared 1/28/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/5/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/10/2021 DINAH GARIN
Sewer availability Cleared 2/10/2021 DINAH GARIN

Contact Information

Architect Rezvani,, Farbod; Lic. No.: C32315 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Contractor Di Nalli Construction; Lic. No.: 942979-B 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Engineer Askarian,, Soroosh Namaghi; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/8/2021 Partial Approval DAVID HEINE
Underground Mechanical 3/8/2021 Partial Approval DAVID HEINE
Deputy Reinf. Concrete 3/10/2021 Partial Approval DAVID HEINE
Footing/Foundation/Slab 3/18/2021 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 4/6/2021 Corrections Issued BRENDAN LOONEY
Green Building Rough 4/6/2021 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 4/6/2021 Not Ready for Inspection BRENDAN LOONEY
Special/Order Compliance 4/8/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 4/8/2021 Partial Approval BRENDAN LOONEY
Deputy Wood Construction 4/27/2021 Approved BRENDAN LOONEY
Wood Frame 4/27/2021 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 5/10/2021 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Partial Approval BRENDAN LOONEY
Interior/Exterior Lathing 6/4/2021 Approved PIERRE VEGA
ELECTRICAL-Rough 6/8/2021 Approved BRENDAN LOONEY
HVAC-Rough 6/8/2021 Partial Approval BRENDAN LOONEY
PLUMBING-Rough 6/8/2021 Corrections Issued BRENDAN LOONEY
HVAC-Rough 6/10/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 6/10/2021 Approved BRENDAN LOONEY
Wood Frame 6/10/2021 Approved BRENDAN LOONEY
Insulation 6/22/2021 Conditional Approval BRENDAN LOONEY
Drywall Nailing 6/28/2021 Approved BRENDAN LOONEY
Green Building Rough 6/28/2021 Approved BRENDAN LOONEY
ELECTRICAL-Rough 7/6/2021 Conditional Approval BRENDAN LOONEY
HVAC-Rough 7/6/2021 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 7/6/2021 Partial Approval BRENDAN LOONEY
Wood Frame 7/6/2021 Conditional Approval BRENDAN LOONEY
Interior/Exterior Lathing 7/8/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 1/26/2022 Approved BOBBY KEY
ELECTRICAL-Final 1/26/2022 Approved BOBBY KEY
Final 1/26/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 1/26/2022 Approved BOBBY KEY
HVAC-Final 1/26/2022 Corrections Issued BOBBY KEY
PLUMBING-Final 1/26/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/26/2022 SGSOV Approved BOBBY KEY
Smoke Detectors 1/26/2022 Approved BOBBY KEY
Verify Sprinkler Sign Off 1/26/2022 Approved BOBBY KEY
Final 5/24/2022 Corrections Issued BOBBY KEY
HVAC-Final 5/24/2022 Approved BOBBY KEY
Final 7/21/2022 OK to Issue CofO EVAN COOPER
Green Building Final 7/21/2022 Approved EVAN COOPER
Service/Power Release 7/21/2022 Approved EVAN COOPER