632-632 1/2 W 94TH

Certificate Information: 632-632 1/2 W 94TH

Application / Permit
20010-10000-02793
Plan Check / Job No.
B20LA14706
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 11/24/2020
Issuing Office
Current Status
CofO Issued on 7/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 CARLOS MONTES
Corrections Issued 9/17/2020 CARLOS MONTES
Quality Review Completed 10/15/2020 WING SUEN
Building Plans Picked Up 10/20/2020 APPLICANT
Applicant returned to address corrections 11/12/2020 CARLOS MONTES
Plan Check Approved 11/24/2020 CARLOS MONTES
Issued 11/24/2020 APPLICANT
CofO in Progress 5/12/2021 EUGENE CASSIDY
Permit Finaled 7/15/2021 DEROLD HAUFF
CofO Issued 7/15/2021 DEROLD HAUFF
Permit Finaled 7/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 10/26/2020 TERRI OSBORNE
Trees in Parkway Cleared 10/27/2020 JOHN KIM
Address approval Cleared 10/30/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/30/2020 JEANIE LAM
Highway dedication Cleared 10/30/2020 JEANIE LAM
Permit Cleared 10/30/2020 JEANIE LAM
Sewer availability Cleared 10/30/2020 JEANIE LAM
Hydrant and Access approval Cleared 11/3/2020 MATTHEW CRAIG
Low Impact Development Cleared 11/6/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/12/2020 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/7/2020 Approved EUGENE CASSIDY
Deputy Other (see comments) 12/9/2020 No Access for Inspection ELMER BLAND
Deputy Reinf. Concrete 12/9/2020 No Access for Inspection ELMER BLAND
PLUMBING-Rough 12/17/2020 Partial Approval EUGENE CASSIDY
Sewer 12/17/2020 Approved EUGENE CASSIDY
Underground Mechanical 12/17/2020 Approved EUGENE CASSIDY
Wood Frame 12/17/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/22/2020 Partial Approval EUGENE CASSIDY
Insulation 12/22/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/30/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/26/2021 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 1/26/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 1/29/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 1/29/2021 Approved EUGENE CASSIDY
Green Building Rough 1/29/2021 Approved EUGENE CASSIDY
HVAC-Rough 1/29/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 1/29/2021 Approved EUGENE CASSIDY
Insulation 2/2/2021 Approved EUGENE CASSIDY
Drywall Nailing 2/9/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 2/9/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 4/16/2021 Approved EUGENE CASSIDY
Final 4/16/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 4/16/2021 Approved EUGENE CASSIDY
HVAC-Final 4/16/2021 Approved EUGENE CASSIDY
PLUMBING-Final 4/16/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/16/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 4/16/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 4/16/2021 Approved EUGENE CASSIDY
Final 5/12/2021 OK to Issue CofO EUGENE CASSIDY
Service/Power Release 5/12/2021 Approved EUGENE CASSIDY