12355 W NEBRASKA AVE 90025

Certificate Information: 12355 W NEBRASKA AVE 90025

Application / Permit
20010-10000-02786
Plan Check / Job No.
B20LA14640
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW, 30. 5' X 30.2', TWO STORY, FULLY SPRINKLE RED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) & (d)
Permit Issued
Issued on 12/11/2020
Issuing Office
Current Status
CofO Issued on 2/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 SERGIO GUTIERREZ
Corrections Issued 8/25/2020 SERGIO GUTIERREZ
Quality Review Completed 9/2/2020 KESETE HAREGOT
Building Plans Picked Up 9/3/2020 APPLICANT
Applicant returned to address corrections 11/5/2020 SERGIO GUTIERREZ
Plan Check Approved 12/11/2020 SERGIO GUTIERREZ
Issued 12/11/2020 APPLICANT
CofO in Progress 2/1/2023 DAVID FEILER
Permit Finaled 2/9/2023 DANIEL ORRANTE
CofO Issued 2/9/2023 DANIEL ORRANTE
Permit Finaled 2/9/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/9/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/10/2020 DINAH GARIN
Sewer availability Cleared 9/10/2020 DINAH GARIN
Specific Plan Cleared 9/22/2020 RICHARD REASER
Hydrant and Access approval Cleared 9/30/2020 KURT CORRAL
Specific Plan Cleared 10/19/2020 PEDRO AYALA
Specific Plan Cleared 10/26/2020 RICHARD REASER
Low Impact Development Cleared 12/3/2020 ANDRES COVARRUBIAS
Stormwater Pollution Mitigatn Cleared 12/3/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/9/2020 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/23/2020 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/23/2020 Approved OGANES TARAKHCHYAN
Deputy Reinf. Concrete 12/24/2020 No Access for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 12/24/2020 Partial Approval OGANES TARAKHCHYAN
Sewer 12/24/2020 Partial Approval OGANES TARAKHCHYAN
Sewer 1/5/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/23/2021 Partial Approval OGANES TARAKHCHYAN
Pre-Inspection 3/23/2021 Approved OGANES TARAKHCHYAN
Pre-Inspection 3/24/2021 Corrections Issued KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval OGANES TARAKHCHYAN
Sewer 4/12/2021 Approved OGANES TARAKHCHYAN
Wood Frame 4/26/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 5/6/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 5/6/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 5/6/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/14/2021 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 6/15/2021 Approved JACK MATTILLO
Pre-Inspection 6/15/2021 Partial Approval JACK MATTILLO
Underground Mechanical 6/15/2021 Partial Inspection JACK MATTILLO
ELECTRICAL-Rough 6/18/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/25/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/28/2021 Partial Approval OGANES TARAKHCHYAN
Insulation 6/30/2021 Approved OGANES TARAKHCHYAN
Drywall Nailing 7/9/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/12/2021 Approved OGANES TARAKHCHYAN
Service/Power Release 9/29/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 11/4/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Smoke Detectors 11/4/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 11/4/2021 Approved OGANES TARAKHCHYAN
HVAC-Final 12/13/2022 Approved ASHLEY THOMPSON
PLUMBING-Final 12/13/2022 Approved ASHLEY THOMPSON
ELECTRICAL-Final 12/14/2022 Approved ASHLEY THOMPSON
ELECTRICAL-Final 12/20/2022 Approved ASHLEY THOMPSON
Gas Test 12/20/2022 Approved ASHLEY THOMPSON
Green Building Final 12/20/2022 Corrections Issued ASHLEY THOMPSON
Smoke Detectors 12/20/2022 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 1/17/2023 Approved CLAYTON GRAHAM
Final 1/17/2023 Corrections Issued CLAYTON GRAHAM
Green Building Final 1/17/2023 Approved CLAYTON GRAHAM
Green Building Rough 1/17/2023 Approved CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 1/17/2023 SGSOV Approved CLAYTON GRAHAM
Final 2/1/2023 OK to Issue CofO DAVID FEILER