752 E 18TH ST 90021
Certificate Information: 752 E 18TH ST 90021
- Application / Permit
- 20010-10000-02716
- Plan Check / Job No.
- B20LA14466
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- NEW STATE APPROVED MODULAR OFFICE BUILDING.
- Permit Issued
- Issued on 6/22/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | VU NGUYEN |
| Corrections Issued | 9/15/2020 | VU NGUYEN |
| Quality Review Completed | 9/15/2020 | RODOLFO ARIAS |
| Building Plans Picked Up | 9/17/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 10/23/2020 | APPLICANT |
| Applicant returned to address corrections | 2/16/2021 | VU NGUYEN |
| Green Plans Picked Up | 2/22/2021 | APPLICANT |
| Applicant returned to address corrections | 5/10/2021 | VU NGUYEN |
| Plan Check Approved | 5/11/2021 | VU NGUYEN |
| Issued | 6/22/2021 | APPLICANT |
| CofO in Progress | 12/28/2021 | JAMES POWERS |
| Permit Finaled | 12/28/2021 | ERNESTO CORRAL |
| CofO Issued | 12/28/2021 | ERNESTO CORRAL |
| Permit Finaled | 12/28/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 2/2/2021 | JOHN KIM |
| Community Plan Implem. Overlay | Cleared | 2/16/2021 | PETE EYRE |
| Historic Resource Verification | Cleared | 2/17/2021 | MICAELA TORRES-GIL |
| Community Plan Implem. Overlay | Cleared | 2/19/2021 | RENZ SORIANO |
| Green Code | Cleared | 2/19/2021 | AARON COSTA |
| Roof/Waste drainage to street | Cleared | 2/19/2021 | RENZ SORIANO |
| Permit | Cleared | 2/22/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2021 | RENZ SORIANO |
| Green Code | Cleared | 2/24/2021 | RODOLFO ARIAS |
| Sewer availability | Cleared | 2/24/2021 | RENZ SORIANO |
| Redevelopment Project Area | Cleared | 2/25/2021 | DAVID URITA |
| DAS Clearance | Cleared | 4/1/2021 | VU NGUYEN |
| Community Plan Implem. Overlay | Cleared | 4/12/2021 | HELEN JADALI |
| Community Plan Implem. Overlay | Cleared | 4/12/2021 | HELEN JADALI |
Contact Information
| Contractor | De La Peza Construction; Lic. No.: 531927-B | 3859 MOUNTAIN VIEW AVENUE PASADENA, CA 91107 |
| Engineer | Nieman,, Adam M; Lic. No.: C91181 | 11624 N 151ST LANE SURPRISE, AZ 85379 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/20/2021 | Corrections Issued | DAVID TSAU |
| Footing/Foundation/Slab | 9/10/2021 | Partial Approval | DAVID TSAU |
| Deputy Steel/Welding | 10/14/2021 | Partial Approval | JAMES POWERS |
| Final | 12/1/2021 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 12/1/2021 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 12/1/2021 | SGSOV No Gas | JAMES POWERS |
| Smoke Detectors | 12/1/2021 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 12/1/2021 | Approved | JAMES POWERS |
| Wood Frame | 12/1/2021 | Approved | JAMES POWERS |
| Final | 12/3/2021 | Partial Approval | JAMES POWERS |
| Final | 12/23/2021 | Not Ready for Inspection | JAMES POWERS |
| Final | 12/28/2021 | OK to Issue CofO | JAMES POWERS |